Girardeau Contractors, Inc. v. Missouri Highway & Transportation Commission

644 S.W.2d 360, 1982 Mo. App. LEXIS 3396
CourtMissouri Court of Appeals
DecidedDecember 21, 1982
DocketNo. WD33239
StatusPublished
Cited by6 cases

This text of 644 S.W.2d 360 (Girardeau Contractors, Inc. v. Missouri Highway & Transportation Commission) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Girardeau Contractors, Inc. v. Missouri Highway & Transportation Commission, 644 S.W.2d 360, 1982 Mo. App. LEXIS 3396 (Mo. Ct. App. 1982).

Opinion

WASSERSTROM, Judge.

Plaintiff sues for damages under a contract by which it undertook as the prime contractor certain highway work for defendant. Trial commenced before a jury, but at the close of all the evidence the trial court sustained a motion for directed verdict, from which ruling plaintiff appeals. Defendant contends the appeal should be dismissed because plaintiff’s brief here as appellant violates Rule 84.04. That contention is denied. On the merits of the appeal, we affirm.

The work under the contract consisted of removing 7,000 feet of concrete median and [362]*3626,500 feet of double faced guardrail and constructing in place thereof a new continuous concrete median barrier to meet interstate standards. Highway Contractors, a subcontractor hired by plaintiff, removed the old guardrail and stockpiled it in the right-of-way. Defendant took possession of this guardrail material, contending that it had the right to do so. Plaintiff challenges that right and claims damages for defendant’s act in appropriating the guardrail. That dispute gives rise to this lawsuit.

The contract between the parties incorporated the Missouri Standard Specifications for Highway Construction Work, of which three subsections are pertinent here. Section 202.22.2, which is part of the section dealing with “Removal of Improvements” provides that: “Material not designated for salvage will be considered the property of the contractor.... ”

The only portion of the contract or specifications which designate guardrail for salvage is Section 104.9.2 which is part of the section dealing with “Final Cleaning Up.” This section reads as follows:

“The contractor shall cut all brush, grain, grass, and weeds from the entire right-of-way except for improved or selected areas shown on the plans or designated by the engineer, and shall clean and remove from the right-of-way all abandoned fences, telephone and power line facilities, surplus and discarded material, any perishable matter, rubbish, and temporary structures. The vegetation on the right-of-way outside of the construction limits shall not be removed by blad-ing. All guard rail materials within the right-of-wav shall remain the property of the Commission and shall be stored on the right-of-way as directed by the engineer. The contractor shall restore in an acceptable manner all property, both public and private, which may have been damaged on account of the prosecution of the work, and shall leave the right-of-way neat and presentable. All areas outside the rounding of fill slopes and backslopes, on which the existing turf is damaged by the contractor’s operations, shall be restored by the contractor, at his expense, by seeding and mulching such areas at the rates designated in the contract, or as directed by the engineer.” (Underscoring added.)

Following the subsection just quoted, there appears Section 104.9.4 which provides as follows:

“Final cleaning up in accordance with the provisions of Sec 104.9.2 will not be required when the principal part of the contract consists of traffic signals, lighting, signing, fencing, plantings, surfacing, or resurfacing work. When the principal part of the contract consists of these items, the contractor shall remove all excess excavation and all rejected or unused materials and debris from the right-of-way or as directed by the engineer and shall restore to a satisfactory condition all shoulders and slopes defaced by the contractor’s operations ... . ”

The issue for determination in this case is whether the underscored sentence of Section 104.9.2 gives defendant the right to the guardrail material, or whether any right by defendant under that sentence has been eliminated by virtue of Section 104.9.4.

I.

The first question debated by the parties is whether its contract qualifies under Section 104.9.4 as one in which “the principal part of the contract consists of ... resurfacing work.” The evidence shows that under the Commission’s rules and practice, plaintiff could qualify as a prime contractor only if it did a majority of the contract work itself. Plaintiff is a surfacing and resurfacing contractor, and it did do all of the resurfacing work on this job, which consisted of 5.79 miles of four-lane interstate highway surfacing. That part of the contract amounted to $721,200 out of the $900,250 total contract price. The balance of the work consisted of non-surfacing work done by two subcontractors for which the total cost was $179,050.

Despite defendant’s argument that the principal purpose of this contract was [363]*363the construction of a new median, rather than resurfacing, the evidence establishes plaintiff’s contention that the resurfacing here was the principal part of the contract, so as to bring it within the scope and operation of Section 104.9.4.

II.

The second and the more difficult point debated by the parties is whether Section 104.9.4 was intended to eliminate the sentence in Section 104.9.2 granting the defendant the right to the guardrail materials. The trial court deemed the contract to be ambiguous in this regard and gave plaintiff an opportunity of a jury trial to establish the affirmative of that proposition. However, after hearing all of the evidence, the court concluded that there was no real issue of fact for jury determination, and the court directed a verdict for defendant. Plaintiff says that action was error for these reasons: (1) the contract was unambiguous in its favor and the court should have so declared; (2) if the contract was ambiguous, then the resolution of the ambiguity became a jury issue; and (3) in any event this was a contract of adhesion and the jury should have been permitted to pass upon the reasonable expectation of the parties.

Defendant, on the other hand, counters as follows: (1) the contract was unambiguous in its favor and the court should have so declared without hearing any extrinsic evidence; (2) even if the contract were to be considered ambiguous, the evidence did not make a jury question and the court properly interpreted the contract as a matter of law; and (3) the contract here is not one of adhesion. We have concluded that defendant is correct on all three of its points.

A.

Section 104.9.4 plainly states and intended that on resurfacing jobs, such as the one here, the “final cleaning up” shall not be as set forth in Section 104.9.2, but instead shall be as described in the second sentence of Section 104.9.4. That intention left untouched the separate and essentially unrelated sentence in Section 104.9.2 regarding salvage right in the guardrail material.

In our view that reading clearly appears from the language used, and no other intention can reasonably be read into it. Accordingly the trial court should have so declared as a matter of law. J.E. Hathman, Inc. v. Sigma Alpha Episilon Club, 491 S.W.2d 261 (Mo. banc 1973); Harris v. Union Elec. Co., 622 S.W.2d 239 (Mo.App.1981).

Even though the trial court did not rule in favor of defendant on this basis, the judgment may still be affirmed on this ground. Even if a motion for directed verdict is granted on the wrong ground, if the ruling was proper, the reason assigned is immaterial. Stewart v. Zuellig,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilkerson v. Mid-America Cardiology
908 S.W.2d 691 (Missouri Court of Appeals, 1995)
Hasapopoulos v. Murphy
689 S.W.2d 118 (Missouri Court of Appeals, 1985)
Zahorsky v. Griffin, Dysart, Taylor, Penner & Lay, P.C.
690 S.W.2d 144 (Missouri Court of Appeals, 1985)
Arthur v. Jablonow
665 S.W.2d 364 (Missouri Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
644 S.W.2d 360, 1982 Mo. App. LEXIS 3396, Counsel Stack Legal Research, https://law.counselstack.com/opinion/girardeau-contractors-inc-v-missouri-highway-transportation-commission-moctapp-1982.