KNAPPEN, Circuit Judge.

Plaintiffs in error, whom we style defendants, had a contract for altering and extending a building in Cleveland, Ohio, which was to be completed January 1, 1916. In April, 1915, they made a subcontract with defendant in error (the plaintiff), whereby the latter agreed, for a stated price, to furnish and install the metal doors and trim, picture molding, and base, and to apply the hardware, such installation to be completed by October 1, 1915. On October 16, 1915, the building had not progressed far enough to permit plaintiff to begin its work, and on that date plaintiff gave defendants notice of its rescission of the contract, and brought this suit for the recovery of damages sustained by defendants’ failure to permit plaintiff to perform. Defendants denied plaintiffs’ right to rescind, and asked for damages by way of counterclaim for plaintiff’s refusal to perform. The jury was instructed that under the undisputed testimony plaintiff had the right to refuse to go on with its contract, that defendants had thus no right of action under their counterclaim, and that plaintiff, if not then itself in default, was entitled to recover its damages. Plaintiff recovered verdict and judgment for ,$7,500. This proceeding is-brought to review that judgment.

[1-6] 1. The question of prime importance is whether the court rightly held, as-matter of law, that plaintiff had a right to rescind on (October 16th. Defendants’ construction was delayed several months by controversies with the city over questions arising under its building code relating to the height of the building and structural strength, by the unforeseen necessity of deeper foundations, the encountering of [908]*908quicksand and otherwise, all resulting in defendants’ losing their order of priority with the steel manufacturers. For these delays plaintiff was in no wa}?' at fault. Its actual installation could not- begin until the building was ready for the “bucks,” which are heavy steel frames outlining the openings and into which the tile partitions enter, and which thus support the metal work. The bucks could not be put in until the lower floors were laid, and from one to three months thereafter would be required (according as the claims of plaintiff or defendants are accepted) for completing plaintiff’s work.

On July 13, 1915, defendants replied to plaintiff’s inquiry that—

“We expect the steel work to go right ahead now, and in all probability will not require the steel bucks before September or October, and will advise you later on when we receive the steel drawings and give you outlines as to dates of delivery.”

On September 7th defendants replied to like inquiry:

“We expect to have the steel for approximately up to the third floor shipped and erected by the end of next month, and as soon as they start on the upper portion the tile floors will follow right along.’!

In the latter part of September plaintiff learned definitely that the building would not be ready in October for its installation, and it thereupon gave, on October 16th, its notice of rescission. As it turned out, the building was not ready for the bucks before December. It is enough, for present purposes, to say that it must be, and it is, conceded that as the result of the correspondence and dealings between the parties plaintiff waived whatever right it had, to complete the contract by October 1st.

Had time been of the essence of the contract, so far as concerns plaintiff’s right (as distinguished from its obligation) to complete its work by October 1st, and had the waiver been for a definite period or to a definite date, plaintiff would have had the absolute right to cancel at the expiration of that date. General Elec. Co. v. Chattanooga Co. (C. C. A. 6) 241 Fed. 38, 42, 154 C. C. A. 38. But, in our opinion, neither of these conditions existed. The contract did not in terms make time of its essence, so far as concerns the plaintiff’s right to complete by October 1st. Such was the implied effect as to its obligation. But the obligatory provision was for defendants’ benefit. The reason for a difference between the rights of the parties in this respect is clear. Defendants were under contract with the owner to complete by January 1, 1916, with stipulation for damages at $100 per day for delay. The fact that the delay occurred through the fault of the subcontractor would not avoid defendánts’ liability. Plaintiff accordingly agreed to like stipulated damages in case of its delay, but for delays not occurring through its fault it would not be liable. The. contract, moreover, expressly provided for a suspension from time to time of such parts of the work as defendants should require, and for a resumption of performance thereafter according to defendants’ direction, no claim therefor to be made other than an extension of time for completion equivalent to the delay involved. It was also provided that plaintiff’s work should be performed and completed as soon as the progress of the build[909]*909ing should permit, “and at such times and places and in such quantities as may be directed by [defendants].” The only other express requirement as to the time of commencement of plaintiff’s work is that the “steel bucks for doors shall precede, and metal grounds for base and picture molding will immediately follow, the erection of the tile partitions.”

Moreover, the defendants had not in terms promised that the build - ing would be ready for plaintiff by October 1st. At the most thej? had said (on July 13th) that it would not be ready before September or October, with promise of further advice, and (on September 7th) in effect that it was expected that the steel erection would by the last of October have proceeded far enough to permit the commencement of plaintiff’s installation. However, the suspension and other provisions just referred to gave defendants no right arbitrarily or unreasonably to suspend the work. And, as the case shaped itself, the controlling question on this branch of the case is whether the court rightly held, as matter of law, that, under the circumstances mentioned, a delay by which plaintiff would be prevented from beginning work until December or later was an unreasonable delay, which would justify plaintiff in canceling the contract. If so, we are not prepared to say that the notice was invalid because stating, as ground for rescission, that there had been no extension of time for completion beyond October 1st.

We think that, upon this record, the peremptory instruction as to unreasonable delay was erroneous. It is the general rule that questions of reasonable time and reasonable delay are for the jury. The only exception is where the facts are not in dispute and where there is no room for differing inferences. International Co. v. Stadler (C. C. A. 6) 212 Fed. 378, 382, 129 C. C. A. 54; Marmet Co. v. Peoples Co. (C. C. A. 6) 226 Fed. 646, 651, 141 C. C. A. 402. Such is not the case here. The evidence was not in complete harmony. There was testimony (considering it, as we must, most favorably to defendants) tending to show that plaintiff was kept acquainted with the progress of defendants’ work and had the means of knowing with reasonable accuracy what the prospects were from time to time. Notwithstanding the delays, it was in frequent conference with defendants throughout the summer regarding the progress of the work. Its representatives visited Cleveland as often as once a month until October; one of them consulting with defendants about details left open by the contract, at least one of which, details was never settled.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blackmore v. Davis Oil Co.
671 P.2d 334 (Wyoming Supreme Court, 1983)
Viles v. Prudential Ins.
96 F.2d 3 (Tenth Circuit, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
257 F. 906, 169 C.C.A. 56, 1919 U.S. App. LEXIS 2280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gill-v-hale-kilburn-co-ca6-1919.