Gibbs Brothers Construction, Inc. v. Brook Hollow Green, LLC, National Grange Mutual Insurance Company, Continental Development and Construction, Inc., Nicholas S. Psillas, and Marshall Collier, Indivdually and d/b/a P&C Contractors

CourtCourt of Appeals of Tennessee
DecidedApril 19, 2005
DocketM2003-01698-COA-R3-CV
StatusPublished

This text of Gibbs Brothers Construction, Inc. v. Brook Hollow Green, LLC, National Grange Mutual Insurance Company, Continental Development and Construction, Inc., Nicholas S. Psillas, and Marshall Collier, Indivdually and d/b/a P&C Contractors (Gibbs Brothers Construction, Inc. v. Brook Hollow Green, LLC, National Grange Mutual Insurance Company, Continental Development and Construction, Inc., Nicholas S. Psillas, and Marshall Collier, Indivdually and d/b/a P&C Contractors) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gibbs Brothers Construction, Inc. v. Brook Hollow Green, LLC, National Grange Mutual Insurance Company, Continental Development and Construction, Inc., Nicholas S. Psillas, and Marshall Collier, Indivdually and d/b/a P&C Contractors, (Tenn. Ct. App. 2005).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON August 4, 2004 Session

GIBBS BROTHERS CONSTRUCTION, INC. v. BROOK HOLLOW GREEN, LLC, NATIONAL GRANGE MUTUAL INSURANCE COMPANY, CONTINENTAL DEVELOPMENT AND CONSTRUCTION, INC., NICHOLAS S. PSILLAS, AND MARSHALL COLLIER, INDIVIDUALLY AND D/B/A P&C CONTRACTORS

An Appeal from the Chancery Court for Williamson County No. 27249 R. E. Lee Davies, Chancellor

No. M2003-01698-COA-R3-CV - Filed April 19, 2005

This case is about a construction lien. A real estate developer hired a contractor to perform paving work on new roads in a subdivision. After the work was completed, the contractor sent the developer an invoice for the work done, but the developer did not pay. Eventually, the developer paid a portion of the invoice. When no further payments were made, the contractor filed a lien on the developer’s roadway. The contractor then sued the developer to enforce the lien. After the suit was filed, the developer asserted that the contractor’s workmanship was poor and that, as a result, the pavement on the roadway was defective. The trial court found that the contractor had a valid lien and awarded a judgment against the developer and the developer’s surety. The trial court also awarded the contractor prejudgment interest. The developer appeals, asserting that the road was public and not subject to lien, that the trial court made erroneous evidentiary rulings, that the trial court erred in finding that a variance from the listed measurements was permissible under the contract, that it should have been awarded a setoff against the contractor’s judgment, and that the contractor should not have been awarded prejudgment interest. We affirm, finding that the contractor’s lien was valid and enforceable, that the trial court did not err in its evidentiary rulings, that the developer failed to prove damages to setoff, and that the trial court did not abuse his discretion in the award of prejudgment interest.

Rule 3 Appeal; Judgment of the Chancery Court is affirmed

HOLLY M. KIRBY , J., delivered the opinion of the court, in which W. FRANK CRAWFORD , P.J., W.S. and DAVID R. FARMER , J., joined.

David M. Smythe, Nashville, for the Plaintiff/Appellee Gibbs Brothers Construction, Inc. R. Francene Kavin, Brentwood, for Defendant/Appellants Brook Hollow Green, LLC, National Grange Mutual Insurance Company, Continental Development, and Defendant Nicholas Psillas.

Defendant Marshall Collier, pro se.

OPINION

Plaintiff/Appellee Gibbs Brothers Construction, Inc. (“Gibbs”) is a construction company located in Nashville, Tennessee. Defendant/Appellant Brook Hollow Green, LLC (“Brook Hollow”) is a limited liability company in the business of developing real estate. Brook Hollow owned and developed the real property at issue in this case, located in the City of Fairview in Williamson County, Tennessee. The managing member of Brook Hollow is Defendant Continental Development & Construction, Inc. (“Continental”). Defendant Nicholas Psillas (“Psillas”) is the president of Continental. Psillas is also a partner with Defendant Marshall Collier (“Collier”) in a separate entity, Defendant P&C Contractors (“P&C”).1

Brook Hollow planned to build a subdivision on the property. Toward that end, Brook Hollow hired Gibbs to put in roads for the subdivision. Constructing the roads was comprised of four phases: base stone work, asphalt binder work, concrete curb construction, and asphalt topcoat work. The contract between Gibbs and Brook Hollow specified that Gibbs would construct an 8-inch deep limestone base and a layer of asphalt binder 2 inches deep. The fourth step, an asphalt topcoat, was to be added after construction on the subdivision was complete. The contract stated that “[i]nvoices not paid when due are subject to late charges of 1.5% per month.”

For roads such as those at issue in this case, the City of Fairview’s specifications were a minimum of eight inches of crush rock, two inches of binder asphalt, and one and a half inches of topcoat. Plans for the subdivision were drawn up by an engineer with defendant Continental, and were approved by the City of Fairview. The plans indicated an eight-inch stone base and a two-inch asphalt binder, with the notation “+/-” with the measurement requirements. These plans were given to Gibbs for Gibbs’ use in submitting a bid for the roadwork. The bid was submitted in August 1999 and was accepted by Brook Hollow in September 1999. The plans were referenced in the contract between Gibbs and Brook Hollow.

Defendant P&C was responsible for the utility and subgrade work, putting in the roadbed and the preparation for utilities such as sewers and water drainage. This work was necessary to prepare for the base stone and asphalt work by Gibbs. In October 1999, in a separate transaction, P&C hired Gibbs to finish the grading of the roadways. On October 30, 1999, Gibbs invoiced P&C $5,975.00 for this subgrade work. Collier forwarded this invoice to defendant Continental. It was not paid.

1 Continental, Psillas, Collier and P&C were named as defendants in the litigation below, but the trial court ultimately dismissed Gibbs’ claims against them, and that decision was not appealed.

-2- Thereafter, Gibbs commenced work on the first three phases of laying the roadway, that is, the base stone work, the asphalt binder, and construction of the concrete curbs. These first three steps were completed in early November 1999. On November 11, 1999, Gibbs sent Continental an invoice for $107,649.30 for the work completed to that point. This invoice likewise was not paid.

Gibbs’s bookkeeper at the time, James Potts, made a number of telephone calls to Continental in an attempt to collect the invoices. In May 2000, Gibbs received a $50,000.00 check from Brook Hollow. No further payments were received.

In June 2000, Gibbs filed a Notice of Lien for $63,624.30, which represented the balance from two unpaid invoices on the roadwork for the subdivision, minus the $50,000.00 partial payment.2 The Notice of Lien named Brook Hollow as the owner of the property.

On July 31, 2000, Gibbs filed suit against Brook Hollow to enforce the lien and for money damages against Brook Hollow. In October 2000, Gibbs amended the complaint to add defendant National Grange Mutual Insurance Company, as surety for Brook Hollow. In its answer to Gibbs’ first amended complaint, Brook Hollow denied liability and asserted as an affirmative defense that Gibbs’ work was of poor quality. Brook Hollow asserted a claim for the cost of correcting or redoing Gibbs’ work as a setoff against any damages for which it might be held liable.

In April 2001, Gibbs filed a motion to file a second amended complaint, adding as defendants Continental, P&C Contractors, and Psillas and Collier individually. This amendment was permitted by consent. In July 2001, Gibbs filed a motion to amend the complaint again. In the motion, Gibbs alleged that it had inadvertently failed to invoice Brook Hollow for work done on a model home at the site and sought to amend to include a claim for payment for this work, in the amount of $8,793.14. This amendment was likewise permitted by consent.

During the pendency of the litigation, the thickness of the base and the asphalt binder was tested by core drilling on the roadway, performed by Professional Services Industries, Inc. (“PSI”), an engineering and testing facility located in Nashville, Tennessee. PSI was hired by the City of Fairview. PSI submitted a report dated January 13, 2003.

In addition, Brook Hollow hired Dr. Louis Mishu, a geotechnical engineer, to test the paving work done by Gibbs. By letter dated May 22, 2002, Brook Hollow notified Gibbs that it intended to call Dr. Mishu as an expert witness at the trial, scheduled for June 3, 2002. Gibbs filed a motion in limine to exclude Dr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Flake
88 S.W.3d 540 (Tennessee Supreme Court, 2002)
Win Myint and wife Patti KI. Myint v. Allstate Insurance Company
970 S.W.2d 920 (Tennessee Supreme Court, 1998)
McDaniel v. CSX Transportation, Inc.
955 S.W.2d 257 (Tennessee Supreme Court, 1997)
Bowman v. Bowman
836 S.W.2d 563 (Court of Appeals of Tennessee, 1991)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
Hackett v. Smith County
807 S.W.2d 695 (Court of Appeals of Tennessee, 1990)
Otis v. Cambridge Mutual Fire Insurance Co.
850 S.W.2d 439 (Tennessee Supreme Court, 1993)
Spencer Ex Rel. Spencer v. A-1 Crane Service, Inc.
880 S.W.2d 938 (Tennessee Supreme Court, 1994)
State Ex Rel. Balsinger v. Town of Madisonville
435 S.W.2d 803 (Tennessee Supreme Court, 1968)
Estate of Jessee v. White
633 S.W.2d 767 (Court of Appeals of Tennessee, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Gibbs Brothers Construction, Inc. v. Brook Hollow Green, LLC, National Grange Mutual Insurance Company, Continental Development and Construction, Inc., Nicholas S. Psillas, and Marshall Collier, Indivdually and d/b/a P&C Contractors, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gibbs-brothers-construction-inc-v-brook-hollow-green-llc-national-tennctapp-2005.