Get Lifted LLC v. on Site Management Inc

CourtMichigan Court of Appeals
DecidedAugust 6, 2020
Docket349345
StatusUnpublished

This text of Get Lifted LLC v. on Site Management Inc (Get Lifted LLC v. on Site Management Inc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Get Lifted LLC v. on Site Management Inc, (Mich. Ct. App. 2020).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

GET LIFTED, LLC, UNPUBLISHED August 6, 2020 Plaintiff/Counterdefendant-Appellant,

v No. 349345 Macomb Circuit Court ON-SITE MANAGEMENT, INC., LC No. 2018-000793-CB

Defendant/Counterplaintiff-Appellee, and

MEADOWS ASSISTED LIVING, INC., BANK UNITED, N.A., and THEUT PRODUCTS, INC.,

Defendants.

Before: BECKERING, P.J., AND FORT HOOD AND SHAPIRO, JJ.

PER CURIAM.

Plaintiff Get Lifted, LLC (GL), appeals the dismissal of its breach-of-contract case against defendant On-Site Management, Inc (OSM). The trial court dismissed the case on the grounds that GL first substantially breached the parties’ contracts by failing to procure general liability insurance and was thus precluded from maintaining an action for breach of contract. We affirm.

I. BACKGROUND

OSM was the general contractor for the construction of an assisted living facility. OSM hired GL as a subcontractor to perform concrete work on the project. The parties entered into three separate contracts relating to foundational work, the installation of a parking lot, and the pouring of the concrete floor. In December 2017, OSM advised GL in writing that it had “elected to terminate all contracts with [GL].” The stated reason for termination was subpar and untimely work by GL. At that time, GL had completed work on one of the contracts and started work on another. GL brought suit for breach of contract, and OSM countersued for breach of contract.

-1- OSM subsequently paid GL for its completed work. Thus, all that remained of the complaint was GL’s claim for lost profits based on the two contracts that it did not complete before termination.

OSM maintained that its termination of the contracts was not actionable because termination was undertaken after, and in response to, GL’s breach of the contracts’ quality and time demands. In addition, while the case was pending, OSM learned that GL had not had procured general liability insurance as required by the three contracts. Specifically, three months after GL filed suit, OSM discovered water and mold damage that it attributed to GL’s work. OSM’s project manager stated that she contacted the insurance carrier listed on the certificate of insurance provided by GL, but was informed by the carrier that the policy did not cover GL. OSM filed an amended counterclaim asserting breach of contract and fraud based on the lack of insurance. OSM later moved for summary disposition under MCR 2.116(C)(10) asserting that GL had committed two “prior breaches”: (1) untimely and inadequate work; and (2) the failure to obtain insurance.

The trial court determined that there were questions of fact whether the quality and timeliness of GL’s work breached the contracts and OSM does not appeal that ruling. However, the court granted OSM summary disposition of GL’s complaint on the grounds that GL first substantially breached the contract by failing to procure and maintain general liability insurance. For the same reason, the court granted OSM summary disposition on its breach-of-contract counterclaim relating to the lack of insurance. The court denied summary disposition of OSM’s fraud claim, and the parties later stipulated to dismiss the counterclaim in its entirety.

II. ANALYSIS

On appeal, GL argues that the trial court erred in granting summary disposition for three reasons. First, GL argues that its failure to procure general liability insurance was not a substantial breach or that there is at least a question of fact on that matter. Second, GL contends that OSM waived enforcement of the insurance provision. Third, GL suggests that the first-breach rule should not apply in this case because OSM did not know of GL’s failure to obtain insurance at the time the contracts were terminated. We conclude that the trial court did not err in granting OSM summary disposition.1

1 A trial court’s decision on a motion for summary disposition is reviewed de novo. Spiek v Dep’t of Transp, 456 Mich 331, 337; 572 NW2d 201 (1998). A motion under MCR 2.116(C)(10) tests the factual support for a claim. A court must consider the pleadings, affidavits, depositions, admissions, and any other documentary evidence submitted by the parties, and view that evidence in the light most favorable to the nonmoving party to determine if a genuine issue of material fact exists. MCR 2.116(G)(5); Maiden v Rozwood, 461 Mich 109, 118-120; 597 NW2d 817 (1999), reh den 461 Mich 1205 (1999). Summary disposition should be granted if, except as to the amount of damages, there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Babula v Robertson, 212 Mich App 45, 48; 536 NW2d 834 (1995). We agree with GL that whether a substantial breach occurred is a question of fact. However, questions of fact can be decided by courts at the summary-disposition stage when reasonable minds could not differ on the conclusion. See e.g., Brigs v Oakland Co, 276 Mich App 369, 374; 742 NW2d 136

-2- A. SUBSTANTIAL BREACH2

“The rule in Michigan is that one who first breaches a contract cannot maintain an action against the other contracting party for his subsequent breach or failure to perform.” Michaels v Amway Corp, 206 Mich App 644, 650; 522 NW2d 703 (1994) (quotation marks and citation omitted). This rule only applies when the initial breach is substantial. Id. at 650. In determining whether a breach is substantial or material, “the court should consider whether the nonbreaching party obtained the benefit it reasonably expected to receive.” Omnicom of Mich v Gianetti Inv Co, 221 Mich App 341, 348; 561 NW2d 138 (1997).

This case is analogous to Able Demolition v Pontiac, 275 Mich App 577, 578; 739 NW2d 696 (2007), in which the plaintiff-contractor was required to obtain pre-approval letters from the defendant-city’s legal department before demolishing buildings. The contractor demolished several buildings but failed to obtain the letters to proceed as required by the contract. The city declined to make payment and the contractor brought suit. Id. at 580. We held, in part, that the contractor’s failure to obtain pre-approval letters was a substantial breach that precluded the contractor from recovering breach-of-contract damages. In reaching that conclusion, we reasoned as follows:

Though the contract contemplated that [the contractor] would perform demolition services for the city, the contract here is more than a mere services contract. Rather, the contract is a “legal protocol,” and, as such, the critical aspect of the agreement is that any demolition be accomplished in strict compliance with the procedures designated by [the city’s] legal department to minimize the risk of legal liability and the serious violation of citizens’ property rights. A demolition company must ask the city for a letter on the day of each demolition because, in some cases, a property owner may obtain a last-minute temporary restraining order to prevent destruction of a building. Clearly, the city insists on the clause to avoid liability for demolitions that should not, legally, go forward. . . . Because this step is in the contract to protect property rights and to protect the city from exposure to liability, the letter-to-proceed provision is an essential term of the contract and not a mere technicality. Indeed, the term goes to the heart of the agreement and reflects that the parties understood that the underlying action—the demolition of property— carries with it serious legal implications for all parties. [Id. at 585-586.]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Railway Co. v. McCarthy
96 U.S. 258 (Supreme Court, 1878)
Quality Products and Concepts Co. v. Nagel Precision, Inc.
666 N.W.2d 251 (Michigan Supreme Court, 2003)
Spiek v. Department of Transportation
572 N.W.2d 201 (Michigan Supreme Court, 1998)
C. E. Tackels, Inc. v. Fantin
67 N.W.2d 71 (Michigan Supreme Court, 1954)
Walker & Company v. Harrison
81 N.W.2d 352 (Michigan Supreme Court, 1957)
Maiden v. Rozwood
597 N.W.2d 817 (Michigan Supreme Court, 1999)
Detroit Leasing Co. v. City of Detroit
713 N.W.2d 269 (Michigan Court of Appeals, 2006)
Michaels v. Amway Corp.
522 N.W.2d 703 (Michigan Court of Appeals, 1994)
1300 Lafayette East Cooperative, Inc v. Savoy
773 N.W.2d 57 (Michigan Court of Appeals, 2009)
Able Demolition, Inc v. City of Pontiac
739 N.W.2d 696 (Michigan Court of Appeals, 2007)
Briggs v. Oakland County
742 N.W.2d 136 (Michigan Court of Appeals, 2007)
Omnicom of Michigan v. Giannetti Investment Co.
561 N.W.2d 138 (Michigan Court of Appeals, 1997)
Babula v. Robertson
536 N.W.2d 834 (Michigan Court of Appeals, 1995)
Rental Properties Owners Ass'n v. Kent County Treasurer
308 Mich. App. 498 (Michigan Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Get Lifted LLC v. on Site Management Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/get-lifted-llc-v-on-site-management-inc-michctapp-2020.