Gerling & Associates, Inc. v. Gearhouse Broadcast Pty. Ltd.

625 F. App'x 289
CourtCourt of Appeals for the Sixth Circuit
DecidedSeptember 1, 2015
Docket14-3385, 14-3387
StatusUnpublished
Cited by1 cases

This text of 625 F. App'x 289 (Gerling & Associates, Inc. v. Gearhouse Broadcast Pty. Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gerling & Associates, Inc. v. Gearhouse Broadcast Pty. Ltd., 625 F. App'x 289 (6th Cir. 2015).

Opinion

KETHLEDGE, Circuit Judge.

Gerling '& Associates (“Seller”) sold a media trailer to Gearhouse Broadcast *292 (“Buyer”), but delivered the trailer late and in defective condition. Buyer repaired the trailer, rented substitute trucks to broadcast a series of soccer games, and then sued Seller for breach of contract. After a trial, the jury awarded damages to Buyer for the repairs and truck rentals. Seller appeals, arguing among other things that the district court erred by failing to instruct the jury that Buyer had a duty, to mitigate damages. We agree with that argument, vacate the award for repair damages, and remand for a new trial on those damages. We otherwise affirm,.

I.

Seller, an Ohio corporation, makes custom-built trailers that media companies use to broadcast events from remote locations, In February 2010, an Australian media company, Buyer, sought to purchase such a trailer. Buyer’s CEO, Graham Elliot, saw an advertisement on Sellers webr site for a trailer that could be “ready ... within 45 days.” R. 181-3 at 4396. Elliott contacted Seller’s president, Fred Gerling, to ask for details. Gerling responded that Seller could have the trailer “ready for [Buyer’s] acceptance within 55 working days,” and assured Elliott that the trailer would comply with traffic regulations in New South Wales, Australia. R. 181-4 at 4398-99; R. 176 at 3505-06. Elliot explained that his company needed the trailer to broadcast a series of soccer and rugby games. R. 176 at 3511-13.

During further negotiations, Seller proposed a different' delivery date, but Buyer replied that Seller’s proposed timetable was unacceptable: Buyer needed to begin installing equipment on the trailer by July 1 so that it could broadcast games in the fall. R. 181-5 at 4401-03. Seller then offered to have the trailer ready by May 17, 2010, to deliver the trailer to Australia by July 1, and to sell the trailer for $450,000. R.. 181-5 at 4400. Buyer ■ accepted and the parties signed a contract on March 17, 2010. The contract itself did not identify a completion date, but stated that “[t]he completion date quoted is the promised date upon which the unit will be completed[.]” R. 181-1 at 4391.

In late March, Elliot emailed Gerling to express concerns about the width of the trailer: some of the trailer’s drawings showed that it would be wider than 2.5 meters, which was too wide for roads in New South Wales. Gerling responded that the problem would be addressed “in a timely manner.” R. 181-9 at 4411.

The trailer arrived in Australia in early September — about three months late — at which point Buyer discovered that the trailer was still too wide. Buyer also noticed that the trailer’s' metal work and paint finish were shoddy, that the expanding sides of the trailer did hot fully retract, and that the “[g]eneral build quality” Was “very poor.” R. 181-17 at 4434. Buyer contacted an Australian company, Varley Group, 'which provided a quote for the repairs.' After Varley completed the repair work, Buyer received an invoice for the repairs and other work performed on the trailer. Buyer paid the invoice in full.

Around the same time, Buyer rented trucks to broadcast the soccer games. Buyer'also needed "to cover a professional-cycling event, so Buyer purchased and modified a shipping container to serve as a mobile-production facility at the event.

Seller thereafter sued Buyer in the Southern District of Ohio, seeking a declaratory judgment stating that Buyer had breached the terms of the contract’s limited warranty when Buyer hired Varley to repair the trailer, and that Buyer was therefore not entitled to damages. In response, Buyer filed a counterclaim alleging breach of contract and seeking damages *293 incurred in repairing the trailer, renting trucks to broadcast the soccer games, and modifying the shipping container to. broadcast the cycling event.

The case proceeded to trial. After the close of evidence; Seller- moved for judgment as a matter of law, which the district court granted as to the cycling-event claim, but otherwise denied. The jury awarded Buyer 107,793.90 Australian dollars for the repairs and 244,204.40 Australian dollars for the truck rentals. This appeal and cross-appeal followed.

II.

A..

Seller challenges the award of repair damages on two grounds. First, Seller argues that the district court should have granted judgment as a matter of law because, according to Seller, Buyer’s evidence of the repair dafnages was only speculative. We review the district court’s decision de novo. Wallace v. FedEx Corp., 764 F.3d 571, 586 (6th Cir.2014). To prevail on a breach-of-contract claim under Ohio law, which the parties agree applies here, a buyer must provide a “reasonable basis on which [the jury] could calculate” the amount of damages that the seller’s breach caused. World Metals, Inc. v. AGA Gas, Inc., 142 Ohio App.3d 283, 755 N.E.2d 434, 439 (2001). But a buyer need not prove the amount of damages with “mathematical precision.” Bobb Forest Prods., Inc. v. Morbark Indus., Inc., 151 Ohio App.3d 63, 783 N.E.2d 560, 578 (2002).

To show how much Buyer paid to repair the trailer, Buyer provided a quote from Varley indicating that the repair work would cost 123,335.10 Australian dollars, as well as Buyer’s bank records showing that Buyer paid 349,664.10 Australian dollars for those repairs and for other work performed on the trailer. R. 159-9 at 2888; R. 181-21 at 4448. These two documents gave the jury a reasonable basis on which to calculate damages: the bank records showed the total amount that Buyer paid; the Varley (juote showed approximately what portion of the total amount was for the repairs.

Seller responds that the district court should not have considered the Varley quote when deciding whether Buyer presented sufficient evidence as to the repair damages. Specifically,. Seller - says that the quote was inadmissible. hearsay. To answer that, argument on its own terms, a document is hearsay only if it is admitted “to prove the truth of the matter asserted.” Fed.R.Evid. 801(c)(2). The district court made clear that the quote was not offered for that purpose. R. 178 at 3922 (“[The quote] is not in evidence for the truth of the matter. stated therein[,] but just to demonstrate that this, quote was communicated from Varley .to [Buyer].”). Hence the Varley quote was not hearsay.

Moreover, the quote was admissible under the business-records exception to the ■ hearsay rule. See • Fed.R.Evid. 803(6). Seller contends that the quote was inadmissible under this rule because Buyer failed to present a “qualified witness” who was “familiar with [Varley’s] record-keeping system.” Seller Br. at 48. But Buyer did not need to present such a witness to admit the quote.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
625 F. App'x 289, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gerling-associates-inc-v-gearhouse-broadcast-pty-ltd-ca6-2015.