Georgene Salmon v. Paul Blake Enterprises, Inc.
This text of Georgene Salmon v. Paul Blake Enterprises, Inc. (Georgene Salmon v. Paul Blake Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
NO. 07-00-0318-CV
IN THE COURT OF APPEALS
FOR THE SEVENTH DISTRICT OF TEXAS
AT AMARILLO
PANEL A
MAY 22, 2001
______________________________
GEORGENE SALMON, APPELLANT
V.
PAUL BLAKE ENTERPRISES, INC., APPELLEE
_________________________________
FROM THE 181 ST DISTRICT COURT OF RANDALL COUNTY;
NO. 45,292-B; HONORABLE SAMUEL C. KISER, JUDGE
_______________________________
Before BOYD, C.J., and REAVIS and JOHNSON, JJ.
Appellant Georgene Salmon challenges judgment rendered by the trial court upon a bench trial confirming the addendum decision by arbitration dated August 5, 1997, and decreeing that Paul Blake Enterprises, Inc. recover $37,145.67, plus interest in the amount of $7,785.31 and attorney’s fees from Salmon. By two issues, Salmon contends that (1) the trial court erred in rendering judgment confirming the arbitration award because she never agreed to arbitrate the issue relating to the foundation work, and (2) that the original decision issued by the arbitrator was a final decision. Based on the rationale expressed herein, we affirm.
In 1996, Salmon employed Blake, by an oral contract, to repair the foundation of her home which work was covered by her homeowner’s policy and funded by a check issued by the insurance company in the amount of $37,145.67. During the course of the foundation work, Salmon requested that Blake perform additional remodeling work and the parties orally agreed on a price of $11,208.23 for the remodeling. After some changes in the remodeling project requested by Salmon when the initial work was completed, Blake submitted his final bill for the remodeling in the amount of $19,736.85. Salmon refused to pay the remodeling bill and also withheld payment on the foundation repair.
Although the parties had not originally agreed to arbitration, without the advice of counsel, Blake and Salmon then entered into a written “Agreement to Arbitrate” through the Better Business Bureau’s alternative dispute resolution service. Among other things, the agreement prepared by the Better Business Bureau provided as follows:
Nature of Dispute:
Customer states original bid for remodeling work to be done was $11,208.23. She received a bill from Mr. Blake in January for $19,736.85. She states she made some changes after getting original bid but was not advised of costs for changes. Ms. Salmon states some of the work still not completed to her satisfaction.
Business states all work was done as requested by customer and that costs incurred for changes to original bid were reasonable and done in good faith.
Decision sought:
Consumer states she is willing to settle the remodeling bill by paying Mr. Blake $15,000 . . . . Business seeks to have this claim denied . . . . Mr. Blake also is seeking release of insurance repair money due to him in the amount of $37,145.67.
After the dispute was submitted to arbitration, the arbitrator issued a decision on July 3, 1997, that upon completion of five items by Blake before July 31, 1997, Blake was to be paid $20,018.18. The July 3 decision declined to make any award for the foundation repairs, because the matter “should be resolved through the insurance company, Georgene Salmon and Paul Blake Construction, since this was not an issue specifically stated in the Agreement to Arbitrate” by Salmon. When Blake completed the five items, Salmon paid the $20,018.18 awarded by the arbitrator. Then, on August 5, 1997, the arbitrator issued an addendum decision requiring Salmon to sign over the $37,145.67 paid by the insurance company or to pay Blake that same amount. Salmon contends that she did not agree to arbitrate the issue relating to the foundation work and that the arbitrator could not render a second decision after his initial decision on July 3, 1997. We disagree.
By her first issue, Salmon contends she did not agree to arbitration of the foundation repair. Although a party cannot be required to submit a dispute to arbitration that the party has not agreed to submit, United Parcel Service, Inc. v. McFall, 940 S.W.2d 716, 718 (Tex.App.--Amarillo 1997, no writ), public policy favors arbitration and any doubt as to whether a particular claim falls within the scope of an arbitration agreement is resolved in favor of arbitration. Prudential Securities, Inc. v. Marshall, 909 S.W.2d 896, 898-99 (Tex. 1995). The weight of this policy is so great that it compels a court to presume that the matter is subject to arbitration until the opponent proves otherwise. United Parcel Service, Inc., 940 S.W.2d at 719. In this review, we must also consider the findings made by the trial judge.
Standard of Review
Findings of fact entered in a case tried to the bench have the same force and dignity as a jury’s verdict upon questions. Anderson v. City of Seven Points, 806 S.W.2d 791, 794 (Tex. 1991). A trial court’s findings of fact are reviewable for legal and factual sufficiency by the same standards applied in reviewing the sufficiency of the evidence supporting a jury’s finding. Id. In reviewing a no evidence issue, we consider only the evidence and reasonable inferences therefrom which, when viewed in their most favorable light, support the court's findings, disregarding all evidence and inferences to the contrary. Lewelling v. Lewelling, 796 S.W.2d 164, 166 (Tex. 1990). If there is more than a scintilla of evidence to support the finding, the no evidence challenge must fail. Id . In considering a factual sufficiency issue, we review all the evidence and reverse only if the challenged finding is so against the great weight and preponderance of the evidence as to be manifestly unjust. Pool v. Ford Motor Co., 715 S.W.2d 629, 635 (Tex. 1986); In re King's Estate, 244 S.W.2d 660, 661 (Tex. 1962). We are not to reweigh the evidence and set aside the finding merely because we feel that a different result is more reasonable. Pool , 715 S.W.2d at 634. The trier of fact is the sole judge of the credibility of the witnesses and the weight given their testimony, Leyva v. Pacheco, 358 S.W.2d 547, 549 (Tex. 1962), and may believe one witness and disbelieve another and resolve inconsistencies in testimony. McGalliard v. Kuhlmann, 722 S.W.2d 694, 697 (Tex. 1986). We are not so bound by the trial court’s conclusions of law, and review those conclusions de novo to determine their correctness. Hydrocarbon Mgt. v. Tracker Exploration, 861 S.W.2d 427, 431 (Tex.App.--Amarillo 1993, no writ).
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Georgene Salmon v. Paul Blake Enterprises, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/georgene-salmon-v-paul-blake-enterprises-inc-texapp-2001.