George H. Swatek, Inc. v. North Star Graphics, Inc.

587 A.2d 629, 246 N.J. Super. 281, 14 U.C.C. Rep. Serv. 2d (West) 1102, 1991 N.J. Super. LEXIS 63
CourtNew Jersey Superior Court Appellate Division
DecidedFebruary 14, 1991
StatusPublished
Cited by10 cases

This text of 587 A.2d 629 (George H. Swatek, Inc. v. North Star Graphics, Inc.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George H. Swatek, Inc. v. North Star Graphics, Inc., 587 A.2d 629, 246 N.J. Super. 281, 14 U.C.C. Rep. Serv. 2d (West) 1102, 1991 N.J. Super. LEXIS 63 (N.J. Ct. App. 1991).

Opinion

246 N.J. Super. 281 (1991)
587 A.2d 629

GEORGE H. SWATEK, INC., PLAINTIFF-RESPONDENT,
v.
NORTH STAR GRAPHICS, INC., DEFENDANT-APPELLANT.

Superior Court of New Jersey, Appellate Division.

Submitted January 23, 1991.
Decided February 14, 1991.

*282 Before Judges MICHELS and GRUCCIO.

Noto & Cuba, attorneys for appellant (Maria Del Gaizo Noto and Brenda A. Cuba, of counsel and on the brief).

Contant, Schuber, Scherby & Atkins, attorneys for respondent (Andrew T. Fede, of counsel and on the brief).

The opinion of the court was delivered by MICHELS, P.J.A.D.

Defendant North Star Graphics, Inc. appeals from a judgment of the Law Division entered on a jury verdict awarding plaintiff George H. Swatek, Inc. $38,586.84 in damages together with $7,041.94 in interest and dismissing its counterclaim.

A brief summary of the facts giving rise to this appeal follows. In February 1986, defendant and plaintiff entered into a contract under which plaintiff was to supply defendant with shipping containers. Plaintiff delivered the first 10,000 containers and defendant paid for them without complaint. In April *283 1986, defendant requested that plaintiff recut the delivered containers so defendant could ship the containers by United Parcel Service. After recutting the containers, plaintiff delivered them, along with an additional quantity, to defendant. Defendant accepted and paid for these containers.

Defendant later learned that the containers did not meet United Parcel Service's strength standards. Eventually, plaintiff developed a protective cushion that enabled the containers to meet the specifications. In mid-April 1986, plaintiff and defendant agreed that plaintiff would supply defendant with approximately 32,000 cushions. Plaintiff testified that the parties did not set a delivery date, however, defendant believed that the cushions were to be shipped by April 28, 1986. Plaintiff started shipping the cushions in mid-May 1986 and continued shipping the cushions until early June 1986. Because the shipments arrived too late for defendant to meet its obligations with its customers, defendant shipped the containers by air using other packaging materials. Defendant refused to pay for the cushions.

Plaintiff instituted this action to recover damages for monies allegedly due under the contract. Defendant counterclaimed for breach of contract, negligent performance of the contract and fraud. Following a lengthy trial, the jury returned a verdict for plaintiff and the court entered judgment accordingly. This appeal followed.

Defendant first contends that the trial court erroneously directed a verdict in favor of plaintiff and therefore, a new trial is warranted. We disagree. We are satisfied from our study of the record and the arguments presented that the trial court properly enforced the parties' stipulation and framed the jury questions in light of that stipulation.

At the commencement of the trial, the parties agreed on the following stipulation as recounted by the trial court:

THE COURT: Okay. The attorneys have asked me to read a stipulation. They have made a stipulation or agreement. They agree the facts are rather than *284 having you prove the fact, it is stipulated by the parties that the Plaintiffs Swatek delivered to Defendants counterclaimant Northstar Graphics, Inc. and or to Browerman Die Cutting, a warehouse hired by Northstar Graphics, Inc., certain goods under invoices totalling $38,586.84. It is also agreed that said amount has not been paid. So, those are the facts in the case the parties agree on.

At the end of the case, plaintiff moved "for a directed verdict at least for the amount requested in the complaint." The trial court did not formally grant or deny this request but rather, stated:

THE COURT: The charge has, it's already been provided. The issue as far as plaintiff's case is concerned, the charge I proposed to make to the jury is not an issue issue, the 38,000 whatever dollars, is not an issue in the case. The only issue in the case is whether there should be a set off for the breach of contract alleged in the counterclaim, or if — or if it exceeds the amount of $38,000 whether there should be judgment in favor of defendant on the counterclaim.

The trial court thereupon framed the first two jury questions as follows:

1. Did defendant Swatek agree to manufacture and deliver the "corner" sets to defendant North Star Graphics, Inc. within a specified time?
Yes ____ No ____
2. If not, did plaintiff Swatek manufacture and deliver the "corner" sets within a reasonable time?
Yes ____ No ____

The jury answered "no" to the first question and "yes" to the second question.

Defendant's claim that the above amounted to a directed verdict in plaintiff's favor is clearly mistaken. Because of the parties' stipulation, the only question remaining was whether the parties agreed on a delivery date for the cushions. The trial court did not render a verdict in plaintiff's favor. Rather, the trial court properly molded the jury questions in accordance with the stipulation of the parties and the facts in the record. Certainly, this was the correct procedure to follow in this case.

We are satisfied that the trial court properly excluded evidence of defendant's air freight expenses, lost profits and injury to good will and reputation. It is perfectly clear that when the seller of goods breaches its contract with the buyer, the buyer can obtain the goods elsewhere and sue the seller for *285 the difference between the contract price and market price, N.J.S.A. 12A:2-712(2), or the buyer can elect to recover damages for non-delivery based on the difference between the market price at the time he learned of the breach and the contract price. N.J.S.A. 12A:2-713. In either case, the buyer can recover incidental and consequential damages. N.J.S.A. 12A:2-715, which allows recovery of these damages, provides:

Buyer's Incidental and Consequential Damages.
(1) Incidental damages resulting from the seller's breach include expenses reasonably incurred in inspection, receipt, transportation and care and custody of goods rightfully rejected, any commercially reasonable charges, expenses or commissions in connection with effecting cover and any other reasonable expense incident to the delay or other breach.
(2) Consequential damages resulting from the seller's breach include
(a) any loss resulting from general or particular requirements and needs of which the seller at the time of contracting had reason to know and which could not reasonably be prevented by cover or otherwise; and
(b) injury to person or property proximately resulting from any breach of warranty.

Damages for lost profits and additional expenses "come within the category of consequential damages." Seaman v. United States Steel Corp., 166 N.J. Super. 467, 471, 400 A.2d 90 (App.Div.), certif. denied, 81 N.J. 282, 405 A.2d 826 (1979). Consequential damages are only recoverable where they "are reasonably foreseeable at the time the contract was entered into." T.M. Long Co., Inc. v. Jarrett, 165 N.J. Super. 117, 119, 397 A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ellen Z. Melick v. David R. Melick
New Jersey Superior Court App Division, 2026
First Specialty Insurance v. Novapro Risk Solutions LP
468 F. Supp. 2d 1321 (D. Kansas, 2007)
In Re Ardent, Inc.
305 B.R. 133 (District of Columbia, 2003)
Danzeisen v. Selective Insurance Co. of America
689 A.2d 798 (New Jersey Superior Court App Division, 1997)
Derfuss v. NJ Mfrs. Ins. Co.
666 A.2d 599 (New Jersey Superior Court App Division, 1995)
Cooper v. Amana
Third Circuit, 1995
PERF. LEASING v. Irwin Lincoln-Mercury
619 A.2d 1024 (New Jersey Superior Court App Division, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
587 A.2d 629, 246 N.J. Super. 281, 14 U.C.C. Rep. Serv. 2d (West) 1102, 1991 N.J. Super. LEXIS 63, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-h-swatek-inc-v-north-star-graphics-inc-njsuperctappdiv-1991.