George Colon & Co. v. Smith

178 A.D. 100, 165 N.Y.S. 165, 1917 N.Y. App. Div. LEXIS 9366

Opinions

Laughlin, J.:

I am of opinion that the judgment in favor of the respondent is right and should be affirmed. The respondent Smith was the owner of premises on the southeast corner of Merriam avenue and University avenue (formerly Aqueduct avenue), borough of The Bronx, New York city. In the month of March, 1913, she entered into a verbal contract with the defendant Fitzgerald for the excavation of the lot with a view [101] to building an apartment house thereon. Fitzgerald was called as a witness by the plaintiff, and the only evidence with respect to the contract is his testimony which, so far as material to the issue presented for decision, is to the effect that it was agreed between him and the owner that he should excavate the earth and rock according to architects’ plans that had been filed with the department of buildings and that he was to receive for his services eighty-five cents per cubic yard for earth and one dollar and ninety cents per cubic yard for rock excavation.

He entered upon and continued in the performance of the. work until the 22d of April, 1913, at which time,- by a contract resting in parol, he sublet the remaining work to the plaintiff at the same rate, but for an additional consideration.

The owner paid Fitzgerald $1,900 on account of the work which he claims covered the work performed prior to the subletting. The president of the plaintiff testified that his company “ continued excavating the premises until the work was complete. ” On completion the further sum of $3,536.30 became due and owing from the owner to Fitzgerald, and from him to the plaintiff for this work, no part of which has been paid. The plaintiff, however, claims that the work performed by Fitzgerald before subletting the unfinished work to it would not amount to $1,900, and on that theory the plaintiff’s claim was for more than the balance owing from the owner. Plaintiff’s Hen was filed on the 4th of April, 1914.

The complaint was dismissed on the ground that the lien was not filed “within ninety days after the completion of the contract, or the final performance of the work, or the final furnishing of the materials, dating from the last item of work performed or materials furnished,” as required by.section 10 of the Lien Law. (Consol. Laws, chap. 33; Laws of 1909, chap. 38).*

One Hess, who was employed and caUed by the plaintiff, testified in answer to a question asked by the court, that the plaintiff considered that it had finished this excavation work in the spring of 1913.

It appears that on the 23d of May, 1913, the owner entered [102] into a contract in writing with the plaintiff “to build the foundation stone walls and put in the concrete footings ” for an apartment house, and plaintiff agreed to complete the work in less than eight working days. The testimony of Fitzgerald, which is uncontroverted, shows that about two days prior to the date of that contract, he introduced Hess, representing the plaintiff, to the owner with a view to obtaining for plaintiff the contract for the foundation walls, and that at that time the excavation was about completed and ready for the construction of the foundation walls. Notwithstanding the fact that the plaintiff by its agreement with the owner contracted to complete its contract work in less than eight days from the twenty-third day of May, it did not commence the work until the twelfth day of June, and then did not finish it until the first of J uly, when, according to the testimony of Colon, the president of the plaintiff, the work was practically completed. The owner testified in substance that she had negotiated a loan upon the theory that the building would be completed and ready for occupancy by tenants in the fall, and that the delay of the plaintiff in performing its contract for the erection of the foundation rendered this impossible, and that for that reason she was unable to procure the loan and was obliged to abandon further work on the building. There- can be no doubt on this and other evidence that the earth and rock excavation covered by the contract between the owner and Fitzgerald and sublet in part to the plaintiff was completed more than ninety days prior to the filing of the lien.

Free access — add to your briefcase to read the full text and ask questions with AI

George Colon & Co. v. Smith, 178 A.D. 100, 165 N.Y.S. 165, 1917 N.Y. App. Div. LEXIS 9366 (N.Y. Ct. App. 1917).

178 A.D. 100 (George Colon & Co. v. Smith) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Milliken Bros., Incorporated v. . City of N.Y.
94 N.E. 196 (New York Court of Appeals, 1911)
Berg v. . Parsons
50 N.E. 957 (New York Court of Appeals, 1898)
Kenney v. . Apgar
93 N.Y. 539 (New York Court of Appeals, 1883)
Mosher v. Lewis
14 A.D. 565 (Appellate Division of the Supreme Court of New York, 1897)
Chambers v. George Vassar's Sons & Co.
81 Misc. 562 (New York Supreme Court, 1913)