Geodata Services, Inc. v. WR Grace and Co.

526 So. 2d 922, 1988 WL 45873
CourtDistrict Court of Appeal of Florida
DecidedMay 11, 1988
Docket87-296
StatusPublished
Cited by4 cases

This text of 526 So. 2d 922 (Geodata Services, Inc. v. WR Grace and Co.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Geodata Services, Inc. v. WR Grace and Co., 526 So. 2d 922, 1988 WL 45873 (Fla. Ct. App. 1988).

Opinion

526 So.2d 922 (1988)

GEODATA SERVICES, INC., Appellant/Cross-Appellee,
v.
W.R. GRACE AND COMPANY, Appellee/Cross-Appellant.

No. 87-296.

District Court of Appeal of Florida, Second District.

May 11, 1988.

*923 Maxwell G. Battle, Jr., Tampa, for appellant/cross-appellee.

Julian Clarkson of Holland & Knight, Tallahassee, for appellee/cross-appellant.

SCHOONOVER, Judge.

Geodata Services, Inc. (Geodata) appeals an order striking the $300,000 in punitive damages which the jury had awarded to Geodata from W.R. Grace and Company (Grace). We find no merit in any of Geodata's contentions on this issue and, therefore, affirm that order.

Grace cross-appeals that part of the final judgment in which it was found liable to Geodata for compensatory damages. In Geodata's suit against Grace, Geodata advanced in separate counts four different theories of recovery: (1) breach of contract, (2) quantum meruit, (3) independent tort beyond mere breach of contract fraud, and (4) promissory estoppel. Although we find the evidence was insufficient to support a finding of liability based on the theory of quantum meruit or an independent tort beyond breach of contract, we find the evidence was sufficient to support an award of compensatory damages based either on breach of contract or promissory estoppel. We, accordingly, affirm the final judgment as modified by the trial court's order striking the award of punitive damages.

Grace is engaged in the business of mining and processing phosphate. The record reflects that after entertaining bids from a number of drillers Grace entered into a written contract with Geodata on October 14, 1980, in which Geodata agreed to drill approximately 1300 prospect holes on Grace's land located in northeast Manatee County, Florida. Geodata based its breach of contract count on Grace's alleged failure to negotiate in good faith a request Geodata made for additional compensation for a change in the scope of the work covered by this contract as well as on Grace's termination of the contract. While we agree with the dissent that under the terms of the contract Grace was not required to proceed with the work at the requested additional price if the price was unacceptable to Grace, we find that article III of the contract did require Grace to negotiate with Geodata in "good faith" regarding the requested increase and "to exercise their best efforts to reach a mutual agreement" on this matter. Although article *924 XI of the contract provided that Grace could terminate the contract at any time upon written notice to Geodata, we believe that the evidence was sufficient for the jury to have determined that prior to Grace's attempting to terminate the contract under the provisions of article XI by providing written notice of its intention to terminate, Grace breached article III of the contract by failing or refusing to negotiate with Geodata regarding Geodata's request for additional compensation. See Sound City, Inc. v. Kessler, 316 So.2d 315 (Fla. 1st DCA 1975). See also, Rector v. Larson's Marine, Inc., 479 So.2d 783 (Fla. 2d DCA 1985), review dismissed, 486 So.2d 596 (Fla. 1986).

The phrase "scope of the work" is not defined in the contract. However, article I of the contract entitled "SCOPE OF WORK" contained specifications regarding various aspects of the drilling anticipated by the contract and provided, among other things, that "[h]ole spacing will be approximately 660 feet." The contract provided in article II that the cost in areas accessible to rubber tired equipment would be $3.40/feet whereas in areas accessible to all terrain vehicles the cost would be $7.00/feet. The pertinent part of article III of the contract, entitled "CHANGES IN SCOPE OF WORK," provides as follows:

Owner may increase or decrease the scope of the Work by the addition or elimination of one or more items. The Contractor will submit to Owner within 15 days after receipt of a request for an addition or change to the Work, a detailed statement of the additional costs resulting from such request, together with a statement of any proposed additional fee, if any, representing Contractor's charges for each addition or change requested. No additional fee will be payable in respect of any reduction in the Scope of the Work nor in connection with additions to the Work which do not increase the Scope of the Work. Owner, will, within 15 days after receipt from Contractor of the statements referred to above, notify Contractor in writing of exceptions, if any, to such statements and Owner and Contractor agree to negotiate in good faith and to exercise their best efforts to reach a mutual agreement promptly as to the estimated additional costs and, where applicable, additional fee.

The written contract was amended at least nine times before it was terminated in June 1982. Geodata had requested and received additional compensation for each of these nine amendments. Several of the amendments were for additional holes to be drilled on various properties on which Grace had options. At least one of the amendments, however, changed the drilling pattern of the area covered by the original contract from four holes per forty acres to two holes per forty acres. For this reduction in the number of holes to be drilled, Geodata's president, James E. Bromwell, requested that the price be increased by one dollar per foot. He justified his request based on the increased distance between holes, the time required to travel between holes, and the distance which may be required to obtain water. Similarly, the tenth amendment to the contract, which is the subject of this controversy, had changed the drilling pattern further by reducing the holes to be drilled from two holes per forty acres to one hole per forty acres. Mr. Bromwell requested additional compensation in a letter dated May 25, 1982, and stated therein that this reduction in the number of holes to be drilled had eliminated some of the 150 feet holes but none of the 200 feet holes. He went on to explain how having a larger percentage of deeper holes to drill increased the difficulty and costs of drilling. Mr. Bromwell also testified at trial that reducing the number of holes drilled increased the costs; therefore, the jury had ample evidence from which to conclude that a reduction in the number of holes to be drilled did not necessarily equate with a "reduction in the scope of the work" for which article III provided no additional compensation would be due.

Furthermore, there is no indication that Grace denied Geodata's request for additional compensation and terminated the contract because Geodata was requesting additional compensation for a reduction in *925 the scope of the work. In fact, the record contains a memo dated May 27, 1982, from John T. Brooks, employed by Grace in senior management, to Albert Vondrasek, Grace's manager of phosphate development and expansion, in which Mr. Brooks stated: "The only change from the present drilling cost being requested is an extra $3.60 per foot (total $8.00 per foot) for all drilling beyond 150 feet per hole. This now occurs on 25% of the total holes drilled as opposed to the previous 12.5%. I believe this is a reasonable request." Nor does Mr. Vondrasek's memorandum in response dated June 3, 1982, contain any indication that Geodata was requesting additional compensation for a reduction in the scope of the work. Rather, Mr. Vondrasek stated in the memorandum:

Jim Bromwell's request for additional compensation on all holes from 150 ft. to 200 ft. is denied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WR Grace and Co. v. Geodata Services
547 So. 2d 919 (Supreme Court of Florida, 1989)
Brine v. Fertitta
537 So. 2d 113 (District Court of Appeal of Florida, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
526 So. 2d 922, 1988 WL 45873, Counsel Stack Legal Research, https://law.counselstack.com/opinion/geodata-services-inc-v-wr-grace-and-co-fladistctapp-1988.