GenOn Mid-Atlantic v. Dept. of the Environment

248 Md. App. 253
CourtCourt of Special Appeals of Maryland
DecidedOctober 28, 2020
Docket0883/19
StatusPublished
Cited by3 cases

This text of 248 Md. App. 253 (GenOn Mid-Atlantic v. Dept. of the Environment) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GenOn Mid-Atlantic v. Dept. of the Environment, 248 Md. App. 253 (Md. Ct. App. 2020).

Opinion

GenOn Mid-Atlantic, LLC, et al. v. MDE, et al., Nos. 883, 884 & 885, September Term, 2019. Opinion by Nazarian, J.

ADMINSTRATIVE LAW — QUASI-JUDICIAL AGENCY DISCRETION

The agency’s permitting decisions were not arbitrary and capricious where the agency followed existing federal regulations to set compliance deadlines for coal-powered steam electric power plant point sources instead of holding regulations in abeyance until further rulemaking is held. Circuit Court for Charles County, Case No. 08-CV-18-872 Circuit Court for Montgomery County, Case No. 454414V Circuit Court for Prince George’s County, Case No. CAL18-31471

REPORTED

IN THE COURT OF SPECIAL APPEALS

OF MARYLAND

Nos. 883, 884, 885

September Term, 2019 _________________________

CONSOLIDATED CASES ______________________________________

GENON MID-ATLANTIC, LLC, ET AL.

v.

MARYLAND DEPARTMENT OF THE ENVIRONMENT, ET AL. ______________________________________

Nazarian, Reed, Truffer, Keith R. (Specially Assigned),

JJ. ______________________________________

Opinion by Nazarian, J. ______________________________________ Pursuant to Maryland Uniform Electronic Legal Materials Act (§§ 10-1601 et seq. of the State Government Article) this document is authentic.

Suzanne Johnson Filed: October 28, 2020 2020-10-28 15:30-04:00

Suzanne C. Johnson, Clerk “The rabbit-hole went straight on like a tunnel for some way, and then dipped suddenly down, so suddenly that Alice had not a moment to think about stopping herself before she found herself falling down a very deep well.”1

GenOn Mid-Atlantic, LLC, NRG Chalk Point, LLC, and GenOn Chalk Point, LLC

(collectively “GenOn”) operate three coal-powered steam electric generating power plants

in Maryland. Burning coal produces pollutants, and GenOn needs a permit for each plant

from the Maryland Department of the Environment (the “Department”) to discharge

pollutants into Maryland’s waters. GenOn applied for renewed permits to replace permits

that were expiring. The Department analyzed the applications under existing federal

environmental regulations and issued permits that, everyone agrees, comply with these

regulations in force at the time of issuance.

Why, then, are we here? Well, the federal regulations in place at the time the permits

were issued were promulgated by the United States Environmental Protection Agency

(“EPA”) during an earlier presidential administration, and the current EPA had expressed

an intention to revisit the applicable federal regulation (and, to acknowledge the elephant

in the room, loosen them). At the time the case arose, the EPA had not actually begun the

rulemaking process that is required to act on that intention, but GenOn asked the

Department to issue permits with terms that reflected the (later, hypothetical) compliance

deadlines at which the EPA had hinted but, again, had not yet begun the process of

adopting. 2 After the Department issued permits consistent with the regulations existing at

1 Lewis Carroll, Alice in Wonderland (Colonial Press). 2 Since oral argument, the EPA has issued a final rule (the “2019 Rule”), to take effect December 14, 2020, revising the effluent limitation guidelines (“ELGs”) governing the time, GenOn sought judicial review in the circuit courts of the plants’ respective

counties, and contended that each permit was arbitrary and capricious because the

Department did not await or anticipate the not-yet-revised regulations or give GenOn

additional opportunities to show they couldn’t comply with the deadlines in the existing

regulations. The courts affirmed the Department’s permitting decisions, GenOn appeals,

we consolidated the appeals, and we affirm.

I. BACKGROUND

A. Statutory Framework.

Generally speaking, the federal Clean Water Act (“the Act”) prohibits the

“discharge of any pollutant by any person” into our “navigable waters.” 33 U.S.C.

§§ 1311(a), 1362(7), (12) (2018); see Md. Dept. of Env’t v. Anacostia Riverkeeper, 447

Md. 88, 96 (2016). Some businesses, like GenOn’s coal-powered plants, seek authority

from the EPA to discharge pollutants into the water. See Md. Dept. of Env’t v. Cnty.

Comm’rs of Carroll Cnty., 465 Md. 169, 184–85 (2019). Through the National Pollution

Discharge Elimination System (“NPDES”), the EPA is authorized to issue (or to delegate

to state environmental agencies to issue) discharge permits. But that authority, once

granted, isn’t unfettered—the permits contain restrictions “on the type and quantity of

pollutants that can be released” in order to serve the purpose of the Act. Anacostia

Riverkeeper, 447 Md. at 96 (quoting S. Fla. Water Mgmt. Dist. v. Miccosukee Tribe, 541

discharges of bottom ash transport water and flue gas desulfurization (“FDG”) wastewater. Steam Electric Reconsideration Rule, 85 Fed. Reg. 64,650 (Oct. 13, 2020) (to be codified at 40 C.F.R. pt. 423). The new rule shall be considered “issued” as of October 27, 2020, followed by a 120-day period for judicial review. Id.

2 U.S. 95, 102 (2004)); see 33 U.S.C. § 1342 (2018).

The EPA has the power to delegate its permitting authority to a state so long as the

state establishes “a parallel permitting program” as required under the Act. Carroll Cnty.,

465 Md. at 185; see 33 U.S.C. § 1342(b). The EPA has done this in Maryland, and the

permitting authority is the Department. Anacostia Riverkeeper, 447 Md. at 96; see Md.

Code (1987, 2014 Repl. Vol.), § 9-253 of the Environment Article (“EN”); see COMAR

26.08.04.01. Permits are valid for fixed periods of five years or less, subject to renewal. 33

U.S.C. § 1342(b)(1)(B); EN § 9-328(b). The Act also contains an “anti-backsliding”

prohibition that forbids later permits from containing more lenient conditions than their

predecessors. 33 U.S.C. § 1342(o); see Carroll Cnty., 465 Md. at 185.

The Act defines “water quality standards” that set limits on the concentration of

pollutants in water for public use. Carroll Cnty., 465 Md. at 186; see 33 U.S.C.

§ 1313(c)(2)(A) (2018). To achieve the Act’s water quality standards, permits place

restrictions on pollutants. “Effluent limitation[s]” are “any restriction established by a State

or the Administrator on quantities, rates, and concentrations of chemical, physical,

biological, and other constituents which are discharged . . . into navigable waters . . . .” 33

U.S.C. § 1362(11). The Department incorporates effluent limitation guidelines (“ELGs”)

into the permits it issues. See 40 C.F.R. § 125.3 (2019). ELGs, in turn, address different

classes of pollutants. 33 U.S.C. § 1314(b). Instead of targeting the quantity of pollutants

pushed into our waters by dischargers, ELGs focus on the technology the discharger uses

to clean the types of pollutants discharged into the environment. Id.

3 GenOn’s coal-fired power plants produce two types of pollutants that are at issue

here: flue gas desulfurization (“FGD”) wastewater and bottom ash transport water. Coal-

Free access — add to your briefcase to read the full text and ask questions with AI

Related

108OAG64
Maryland Attorney General Reports, 2023
Maryland Attorney General Opinion 108OAG64
Maryland Attorney General Reports, 2023
Concerned Citizens v. Mont. Cnty. Planning Bd.
Court of Special Appeals of Maryland, 2022
Small MS4 Coalition v. Dept. of Environment
250 Md. App. 388 (Court of Special Appeals of Maryland, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
248 Md. App. 253, Counsel Stack Legal Research, https://law.counselstack.com/opinion/genon-mid-atlantic-v-dept-of-the-environment-mdctspecapp-2020.