Genesee Telephone Co. v. Szmigel

174 Misc. 2d 567, 667 N.Y.S.2d 588, 1997 N.Y. Misc. LEXIS 603
New York Supreme Court·Decided February 6, 1997·Published·Cited by 1 cases

Opinion

OPINION OF THE COURT

Edmund A. Calvaruso, J.

Recent Federal legislation has fueled a surge of applications at the local level for cellular communications towers. The towers, often ranging from 100 feet to 250 feet or higher, may not be prohibited by the local municipality.1 Rather, the Telecommunications Act of 1996 preserves local control over placement, construction and modification of new tower applications.

[569] Petitioner Cellular One asked the Town of Irondequoit for permission to construct a new cellular communications tower. After review of the application and hearing, the Board denied both the use and area variances. Petitioner files a CPLR article 78 challenge, and now asks this court to evaluate the denial.

The facts are as follows. On May 6, 1996 the Board heard testimony from Keif Coppins. Mr. Coppins explained the proposed tower would eliminate some problem areas. Specifically, he expected to improve communications in two areas. First was the southern Irondequoit Bay zone. Second, Cellular One wished to improve communications on route 104 near Oakwood Drive and Eastman Kodak. Petitioner suggested significant dropped rates from 7:00 a.m. to 9:00 a.m. and again in the afternoons.

The hearing testimony also accounts that petitioner’s attorney described capacity and coverage weaknesses. He explained that their engineers then analyzed those weaknesses, and provided a target area for the new towers. Petitioners then "bull’s-eyed” a cell site within the target area.

New York law requires the applicant to comply with the standards set forth in Matter of Consolidated Edison Co. v Hoffman (43 NY2d 598 [1978]) and Matter of Cellular Tel. Co. v Rosenberg (82 NY2d 364 [1993]). In Consolidated Edison (supra, at 611), the Court held public utilities, such as the plaintiff, must show "modification is a public necessity * * * required to render safe and adequate service”. An applicant must prove "compelling reasons, economic or otherwise” (at 611), explaining why the proposed request is more feasible than alternative options. Notwithstanding, where the intrusion or burden on the community is minimal, the showing required by the utility should be correspondingly reduced.2

In Rosenberg (supra, at 372-373), another public utilities case, the Court held: "Matter of Consolidated Edison (supra), applies to all public utilities. It also applies to entirely new sitings of facilities, as well as the modification of existing facilities * * * the test we announced in that case, as well as the regulations of the FCC and the PSC, serve to guard against appellants’ concerns about the potential proliferation of similar applications and the inability of local land use officials to exercise control to protect their communities.”

[570] The size of the tower and the impact on local residences place this matter beyond a minimal intrusion or burden. That being the case, it is incumbent upon Cellular One to show compelling reasons why the proposed request is more feasible than other options. The record would indicate Cellular One has failed to do so.

For example, attorney Oliverio described capacity and coverage weaknesses without providing particulars. While the target site within the cell is selected by the engineers, he supplies no quantitative specifics which would allow the Board members to investigate these conclusions. Nor does Mr. Coppins provide the details substantiating the need for another tower.

Moreover, the transcript of the hearing is brimming with Board members asking for alternate site information for the tower. Mr. Coppins told the Board the single location requested was their alternate site. Another request for data on alternate sites was met with this response: 'T don’t know the answer. With the engineering that was done, I am sure that they did it. We got the site after it came through.”

In short, the applicant either refused or was unable to provide any helpful information about other sites for the tower. They could not, or would not, give necessary information to allow the Board to conclude there was a compelling reason to approve this location over other possibilities. Without such information, the Board was left with an inability to exercise control to protect its communities. (Matter of Cellular Tel. Co. v Rosenberg, 82 NY2d 364 [1993], supra; Town Law § 276-b [2], [3].)3

Accordingly, the petitioner’s application shall be denied. While the Telecommunications Act of 1996 bars a blanket prohibition on communications towers, local land use officials still may exercise control to protect their communities by limiting such towers to specific zoning districts, selecting the best possible location after considering the zoning districts within the town, taking precautions to mitigate the visual impacts, and requiring that towers are used by more than one user whenever possible. The Board acted within its providence in denying the application.

Footnotes

Free access — add to your briefcase to read the full text and ask questions with AI

Genesee Telephone Co. v. Szmigel, 174 Misc. 2d 567, 667 N.Y.S.2d 588, 1997 N.Y. Misc. LEXIS 603 (N.Y. Super. Ct. 1997).

174 Misc. 2d 567 (Genesee Telephone Co. v. Szmigel) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

T-Mobile Northeast LLC v. Town of Islip
893 F. Supp. 2d 338 (E.D. New York, 2012)