General Motors Corp. v. Enterprise Heat & Power Co.

86 N.W.2d 257, 350 Mich. 176
CourtMichigan Supreme Court
DecidedNovember 23, 1957
DocketDocket 2, Calendar 47,052
StatusPublished
Cited by11 cases

This text of 86 N.W.2d 257 (General Motors Corp. v. Enterprise Heat & Power Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Motors Corp. v. Enterprise Heat & Power Co., 86 N.W.2d 257, 350 Mich. 176 (Mich. 1957).

Opinion

Sharpe, J.

This cause arises as the result of a claimed overpayment to defendant company of $9,-465 under a contract providing for the installation of an underground fuel network for plaintiff company. The essential facts are not in dispute.

In the fall of 1949, plaintiff company issued to contractors and materialmen requests for quotations for labor and materials to install underground network of storage tanks for gasoline and other fluids required in assembly plant operation. Defendant company made a bid for such work in the amount of $99,318. The bid was accepted by plaintiff and a purchase order was issued in September, 1949.

*178 During the course of the work the parties entered into several alteration agreements whereby the original contract was modified. The revised contract price was $109,018.21. This amount was paid by plaintiff. The price should have been $99,553.21, which resulted in an overpayment of $9,465. Exhibit 13 furnished by defendant was an offer that was accepted by plaintiff for a revision of the contract'and reads in part as follows:

“November 5, 1949
“Oldsmobile Division General Motors Corporation Lansing 21, Michigan
“Attn : Mr. Fred A. Wiles
“Re: ' Bulletin No. 1 — Olds Job #0-49-238
“Gentlemen:
“In answer to your recent letter of November 4, 1949, we are pleased to submit the following revised quotation as requested in the subject bulletin:
“Item #1 — (Revise item #10 of original job #0-49-238.)
“As per original quotation (Item #10) ......................... $1,126
“Less: Credit for 2 Neptune meters 529
Balance: $597
“Add: Additional labor and material cost for installing 2 propor-tioner meters ................. 287
Total: $884
“Item #2 — (Revise item #12 of original job #0-49-238.)
“As per original quotation (Item #12) ......................... $2,531
“Less: Credit for proportioner meters ....................... 1,315
Balance: $1,216
“(No additional labor and material charge on this item.)
*179 “Page No. 2 November 5, 1949
“Item #3 — (Revise item #13 of original job #0-49-238.)
“As per original quotation (Item #13) ......................... $3,098
“Less: Credit for 4 Neptune meters 1,058
Balance: ' $2,040
“Add: Additional labor and material cost for installing propor-tioner meters.................. 2,926
Total: $4,966
“Item #4 — -(Revise item #14 of original job #0-49-238.)
“As per original quotation (Item #14) ......................... $1,391
“Less: Credit for 2 Neptune meters......................... 529-
B alance: $862
“Add: Additional labor and material cost for installing 2 plo-portioner meters .............. 264
Total: $1,126
“Item #5 — (Revise item #15 of original job #0-49-238.)
“As per original quotation (Item #15) ......................... $1,319
“Less: Credit for Lincoln meters 657
Balance: $662
“(No additional labor and material charge on this item.)
“We wish to advise that the above quoted prices include the installation of (Proportioner meters furnished by Oldsmobile) sufficient meters to dispense the quantities required and specified in your original ¡request for quotation.
“Tours very truly
“Enterprise Heat and Power • Company, Inc.
“R. E. Johnson, Engr.”

*180 An analysis of this revised offer clearly shows a reduction from the original contract price in the amount of $611.

Exhibit 33 reads as follows:

“Analysis of Enterprise Heat & Power Quotation November 5, 1949, covering contract revisions specified in Bulletin No. 1 — Job No. 0-49-238
Item Contract Credit Number Amount to Olds Added Net Revised Charge Credit Contract to Olds to Olds Amount
1 (10) .. $1,126 $529 $287 $242 $884
2 (12) .. 2,531 1,315 None 1,315 1,218
3 (13) .. 3,098 1,058 2,926 1,868 4,966
4 (14) .. 1,391 529 264 265 1,126
5 (15) ..•• 1,319 657 None 657 662
Totals .. $9,465 $4,088 $3,477 $611 $8,854”
“(*Additional charge ' on original.)” Olds, appeared in red

This exhibit clearly shows that plaintiff company was entitled to a credit of $611 and that the revised contract amount was $8,854 instead of $9,465.

The cause came on for trial, and at its conclusion the court entered judgment in favor of plaintiff in the sum of $9,465 with interest.

Defendant appeals and urges that they submitted a bid to plaintiff for the installation of certain underground fuel network; that such bid was investigated by plaintiff’s officers, and that it is now too late to claim a mutual mistake. Defendant also urges that when money has been paid with full knowledge of the facts, it cannot be recovered on the ground that the payment was made under a misapprehension of the legal rights of the person paying.

In coming to our conclusion in this cause we have in mind that there was no fraud involved and that both parties had ample opportunity to examine exhibit 13 prior to the making and acceptance of the *181 overpayment. The general rule relative to the right to recover money paid through a mistake of fact is well stated in Smith v. Rubel, 140 Or 422, 426, 427 (13 P2d 1078, 87 ALR 644), where it was said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farm Bureau Mut. Ins. Co. v. Buckallew
685 N.W.2d 675 (Michigan Court of Appeals, 2004)
Farm Bureau Mutual Insurance v. Buckallew
685 N.W.2d 675 (Michigan Court of Appeals, 2004)
Wilson v. Newman
617 N.W.2d 318 (Michigan Supreme Court, 2000)
Adams v. AUTO CLUB INS. ASSOCIATION
397 N.W.2d 262 (Michigan Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
86 N.W.2d 257, 350 Mich. 176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-motors-corp-v-enterprise-heat-power-co-mich-1957.