General Heating v. SMD Construction
This text of General Heating v. SMD Construction (General Heating v. SMD Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT
BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING
EXCEPT AS PROVIDED BY RULE 239(d)(2),
SCACR.
THE STATE OF SOUTH CAROLINA
In The Court of Appeals
General Heating and Air Conditioning Co. of Greenville, Inc., Respondent,
v.
SMD Construction, LLC, and Robert L. Scroggs, Jr., Appellants.
Appeal From Spartanburg County
J. Derham Cole, Circuit Court Judge
Unpublished Opinion No. 2005-UP-117
Submitted February 1, 2005 Filed February
16, 2005
AFFIRMED
William S. Brown, Peter G. Siachos, both of Greenville, for Appellants.
David Weldon Gantt, of Greenville, for Respondent.
PER CURIAM: This is an appeal from a breach of contract action in which the circuit court, sitting nonjury, awarded damages and entered judgment in favor of General Heating and Air Conditioning Co. of Greenville, Inc. We affirm.
FACTS
General and SMD Construction entered a contract for work to be performed at a manufacturing facility in Georgia. The first contract was signed on February 22, 2000 and completed in May 2000. General was paid the full amount on this contract. The parties entered a second contract in June 2000. The contract price was $227,541. When General completed the work in November 2000, it was due $49,028 under the contract.
General brought suit against SMD and Robert L. Scroggs, Jr., president of SMD, alleging SMD owed $49,028 on the contract, and Scroggs personally guaranteed payment of the amount owed. SMD filed a counterclaim alleging breach of contract by General and denying Scroggs made a personal guaranty.
John Algary, Vice President of General, testified as to the amount owed by SMD for the work completed. He also stated he met with Scroggs regarding the amount owed, and Scroggs agreed to personally guarantee the payment in exchange for Generals forbearance of filing a mechanics lien. Algary further testified that SMD never lodged a complaint in connection with the work performed by General under the second contract.
Mark Clark, Generals treasurer, testified he met with Scroggs regarding the outstanding payment. Scroggs agreed to personally guarantee the payment owed General in exchange for General not filing a mechanics lien. According to Clark, Scroggs claimed that the filing of the lien would prevent SMD from arranging funding for the money then due General under the contract.
Robert Scroggs, President of SMD, testified there were some problems with the work completed by General, but he was unsure of the time frame, and he did not contact General regarding the problems. He admitted he never wrote General regarding the problem, and the problems were not mentioned in any of the documents generated during the relevant time period. Scroggs acknowledged the weak financial situation of SMD and the need for additional funding. Scroggs denied that he personally guaranteed the payment of the remaining balance due General, asserting instead that he was merely guaranteeing that SMD would pay what was owed.
Michael Bird, also with SMD, testified that he was not satisfied with some of Generals work, although he acknowledged the absence of correspondence to confirm his trial testimony.
The trial court found General had established its claims against SMD for breach of the underlying contract and Scroggs for his personal guaranty for the amount owed. The court found in favor of General on SMDs counterclaims. The court entered judgment in favor of General in the amount of $49,028 plus interest. This appeal followed.
STANDARD OF REVIEW
An action for breach of contract seeking money damages is an action at law. R & G Constr., Inc. v. Lowcountry Regl Transp. Auth., 343 S.C. 424, 430, 540 S.E.2d 113, 117 (Ct. App. 2000). In an action at law, on appeal of a case tried without a jury, the findings of fact of the judge will not be disturbed upon appeal unless found to be without evidence which reasonably supports the judges findings. Townes Assocs. v. City of Greenville, 266 S.C. 81, 86, 221 S.E.2d 773, 775 (1976). The judges findings are equivalent to a jurys findings in a law action. Id.
LAW/ANALYSIS
SMD contends that General failed to meet a condition
precedent in the contract, specifically the provision concerning Generals duty
of satisfactory performance. Scroggs maintains the court erred in finding
he personally guaranteed any amount owed by SMD. We disagree, finding ample
evidence in the record to support the judgment of the able trial judge.
I. Condition Precedent
The contract provided: The Contractor [SMD] agrees to pay the Subcontractor [General] for satisfactory performance of the Contractors Work . . . . A condition precedent entails something that is essential to a right of action. Worley v. Yarborough Ford, Inc., 317 S.C. 206, 210, 452 S.E.2d 622, 624 (Ct. App. 1994). In contract law, the term connotes any fact other than the lapse of time, which, unless excused, must exist or occur before a duty of immediate performance arises. Id. We agree the satisfaction of SMD was a condition precedent to the payment of the contract price, as such finding is not challenged on appeal and it represents the law of this case. Indeed, Algary, Generals vice president, admitted the work had to meet SMDs satisfaction.
The fundamental fallacy in SMDs position is its apparent contention that its trial testimonythat it was not satisfied with Generals workis dispositive. Our standard of review requires us to affirm unless there is no evidence to support the trial judges findings. The court found Generals work was satisfactorily completed, and the record supports such finding. For example, the testimony of Algary and Clark, deemed credible by the fact finder, supports this finding. The trial judge assigned weight to the absence of credible evidence of SMDs purported dissatisfaction with Generals work during the relevant time period prior to litigation, and we find no error in this regard. It was well within the province of the trial judge to view the testimony offered by SMD as self-serving, especially in light of the complete absence of documentation to support its position. As there was evidence to support the trial judges determination of SMDs satisfaction with the work of General, and the corresponding finding that SMD owed the balance of the contract price to General, we affirm the judgment for General on its breach of contract claim against SMD.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
General Heating v. SMD Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-heating-v-smd-construction-scctapp-2005.