General Gas Pipe Line Corp. v. United States

115 Ct. Cl. 1, 1949 U.S. Ct. Cl. LEXIS 2, 1949 WL 4912
CourtUnited States Court of Claims
DecidedDecember 5, 1949
DocketNo. 47742
StatusPublished

This text of 115 Ct. Cl. 1 (General Gas Pipe Line Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Gas Pipe Line Corp. v. United States, 115 Ct. Cl. 1, 1949 U.S. Ct. Cl. LEXIS 2, 1949 WL 4912 (cc 1949).

Opinion

Jones, Chief Judge,

delivered the opinion of the court:

This is a suit under the Contract Settlement Act of 1944 (41U. S. C. Secs. 117 and 113).

Plaintiff’s claim under Section 117 of the act was rejected by the Appeal Board of the Office of Contract Settlement.

This case is an appeal to the Court of Claims under Sections 113 and 114 of the Contract Settlement Act.

The facts are set out in detail in the court’s findings of fact. Briefly they are as follows:

In September 1941 Albert A. Kalo, president of plaintiff corporation, called at the office of the Zone Constructing Quartermaster at Columbus, Ohio, tó present a plan for supplying gas to Fort Knox, Kentucky. Mr. Kalo discussed the matter with Lt. Col. Boss E. Windom, who was in charge of the Repairs and Utilities Branch. At that time the Constructing Quartermaster was not considering any change in the source of the gas supply then being used to furnish Fort Knox. Mr. Kalo outlined a plan to furnish gas at a price of 25 cents per thousand cubic feet, which was considerably lower than the rate then being paid for gas at Fort Knox. He was told to present his plan in writing. Some time previously another company had presented to the Commanding Officer at Fort Knox a proposal which had been forwarded to the Quartermaster General’s Office in Washington, which office on July 25, 1941, determined after investigation that the then supplier of gas at Fort Knox was able to meet all demands, including the increase that would be occasioned by the expected expansion at that Post.

At the time of Mr. Kalo’s visit to Colonel Windom the determination of the Quartermaster General on the other proposal was unknown to Colonel Windom.

[15]*15Mr.. Kalo submitted plaintiff’s proposal in writing, including the construction of a main transmission line about 76 'miles long with a pipe line capacity of from 12 to 16 million cubic feet of gas daily. The estimated cost of construction was stated as approximately $650,000, the construction to be completed within 45 days after receipt of pipe.

Since it was proposed to furnish gas at 25 cents per thousand cubic feet, which would effect a considerable saving to the War Department, Colonel Windom was directed by his superior to take the proposal to Washington for discussion with the Office of the Quartermaster General. That office advised Colonel Windom to submit the proposal in the form of a contract. It was prepared in the form of a bid by plaintiff under date of September 22, 1941. The proposed contract, signed by plaintiff as the bidder, but not accepted by the defendant, was forwarded by Colonel Windom on September 22, 1941, to the Office of the Quartermaster General with a recommendation that it be given consideration and approval and returned at the earliest possible date. A statement to the effect that information had been received from the Commanding Officer at Fort Knox that the present gas supply was inadequate to meet the increased demands of Fort Knox accompanied the proposed contract.

About October 10, 1941, plaintiff was advised by Colonel Windom that priority assistance for obtaining pipe and other materials which Mr. Kalo had said at his first conference would be necessary would not be given by the War Production Board. Mr. Kalo on October 10 advised Colonel Windom in writing that priority assistance was not necessary, as sufficient used pipe had been located.

On October 18,1941, the Office of the Quartermaster General sent a radiogram to the Zone Constructing Quartermaster advising that no contract should be executed until the pipe line was completed, but indicating that the form of the contract would be satisfactory provided certain amendments were made in the proposed liquidated damage clause.

Colonel Windom conveyed this information by letter to the plaintiff and advised that a contract for supplying natural gas at Fort Knox, Kentucky, embodying his proposal, subject to the changes prescribed by the Quartermaster General, [16]*16would be entered into upon completion of the necessary pipe line and other equipment.

Mr. Kalo endeavored to locate pipe and other materials for the construction of the line. The corporation was without funds to finance the line and therefore sought financial assistance. Mr. Kalo wrote Fullerton and Company of Columbus, Ohio, which company considered various means of securing funds for the construction of the line and contacted a number of investment houses, but the vice president of the company, who handled the matter, did not think there was anything definite to offer to any investment house for a firm commitment as to finances. There followed other conversations and letters along the same line.

On May 24, 1942, Colonel Windom was transferred from Columbus and thereafter did not have any contact with Mr. Kalo, nor did he have any further relation with the matter of supplying gas to Fort Knox.

Other correspondence followed in which Mr. Kalo sought to have a contract substituted for the letter of intent or commitment. The Office of the Chief of Engineers, which had succeeded to certain duties previously under the Office of the Quartermaster General, replied to the effect that before the request could be acted upon plaintiff must submit evidence of permission to construct the pipe line in the form of an approved War Production Board application bearing the approval of the Office of War Utilities.

Some time later plaintiff submitted to the War Production Board an application for a permit to construct a pipe line which application was denied by the Office of War Utilities of the War Production Board on October 23, 1943. A copy of the letter denying the application was received in the Office of the Chief of Engineers, which office under date of November 9,1943, advised plaintiff that in view of the denial on the part of the regulatory body the letter of intent issued October 24, 1941, and embracing purchase of gas upon completion of the proposed gas line, was “hereby withdrawn and terminated.”

Mr. Kalo did not give up. He communicated with the [Repairs and Utilities Branch of the War Department at Columbus, Ohio, with further regard to the matter of supplying [17]*17gas to Fort Knox, and in response that office informed plaintiff that no encouragement could be given to its proposal, and on April 21,1944, advised it in writing that tlie letter of intent had been withdrawn and in the letter repeated its termination and withdrawal of the letter of intent.

On February 15, 1946, plaintiff filed with the Contract Settlement Office at Columbus, Ohio, a settlement proposal, together with exhibits, one of which itemized the expenses, in the amount of $50,801.98, purportedly incurred by the company from September 1941 to April 1944 in preparing for the construction of a pipe line to Fort Knox. It also set out anticipated profits from one year’s operation of the pipe line amounting to $212,630. It also included in the proposed settlement an item of settlement expense of $6,000. The settlement proposal was forwarded to the Chief of Engineers who replied that since it did not appear that a definite contract was entered into by the parties, or that any rights accrued to the General Gas Pipe Line Corporation incident to the negotiations, the claim for settlement was denied. Plaintiff appealed to the Appeal Board of the Office of Contract Settlement, which affirmed the action taken by the Chief of Engineers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Penn Foundry & Manufacturing Co.
337 U.S. 198 (Supreme Court, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
115 Ct. Cl. 1, 1949 U.S. Ct. Cl. LEXIS 2, 1949 WL 4912, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-gas-pipe-line-corp-v-united-states-cc-1949.