General Fire Extinguisher Co. v. Beal-Doyle Dry Goods Co.

160 S.W. 889, 110 Ark. 49, 1913 Ark. LEXIS 366
CourtSupreme Court of Arkansas
DecidedNovember 3, 1913
StatusPublished
Cited by17 cases

This text of 160 S.W. 889 (General Fire Extinguisher Co. v. Beal-Doyle Dry Goods Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Fire Extinguisher Co. v. Beal-Doyle Dry Goods Co., 160 S.W. 889, 110 Ark. 49, 1913 Ark. LEXIS 366 (Ark. 1913).

Opinion

Wood, J.

The Beal-Doyle Dry Goods Company, engaged in the wholesale dry goods business in the city of Little Rock, was occupying a building owned by Marguerite Miller. Fones under the terms of a lease which required the owner to construct and install an automatic sprinkler system, including a tripod and the enclosing of the pipes and other portions thereof in wooden casings. The Memphis Steel Construction Company was employed to erect the steel tripod, upon which the tank rested that supplied the water for the automatic sprinkler system in the building. The legs of the tripod extended from the foundation up through the various floors and the roof of the building, converging under the tank. The holes necessary for extending the legs of this tripod from the foundation through the roof were cut by carpenters preparatory to the work to be done by the Memphis Steel Construction Company in erecting the tripod.

Appellant was employed to install the supply pipe and sprinkling apparatus necessary for the automatic sprinkler system. In connection with this work it became necessary for a conductor pipe to be brought down from the tank through the roof of the building to supply the sprinkler system on the inside with the necessary water. The entire work was completed on the afternoon of Saturday, January 26, 1912. A heavy rain fell the next day. Water came down through the roof of the building and sides of tbe walls where tbe work bad been done, and damaged tbe goods of tbe appellee.

Tbe appellee sued tbe owner of tbe building, tbe Memphis Steel Construction Company, and tbe appellant, setting up tbe requirements of tbe lease as to tbe installation of the automatic sprinkler system, and alleging, in substance, that tbe defendants wholly disregarded their duties by negligently making openings in tbe roof of the building by negligently erecting and constructing tbe tripod and pipes connected with tbe sprinkling system, causing tbe obstruction of tbe flow of water in tbe gutters and on tbe roof; that they negligently permitted debris to accumulate in tbe gutters and large volumes of water to accumulate on tbe roof of tbe building, which overflowed tbe gutters, passed through tbe boles in tbe roof, and fell upon tbe goods of appellee, damaging Same in tbe sum of $5,000, for which appellee asked judgment.

All tbe material allegations of tbe complaint were denied by tbe defendants.

Tbe waterfall upon the roof of tbe building was carried by gutters to tbe northeast corner directly under tbe tank, and there flowed through an opening in tbe wall extending above the roof into the hopper or conductor bead of a gutter attached to tbe wall upon tbe outside and through tbe gutter or down pipe to tbe street or sewer below. After tbe rain it was ascertained that tbe outside down pipe or gutter was stopped up by pieces of 2x4 lumber, water-soaked building paper, pieces of shiplap, mortar chips and other debris from tbe work that bad been done on tbe roof. It was also discovered that tbe supply pipe coming down from tbe tank through' tbe roof into tbe building bad been boxed down to tbe roof and across to tbe north wall. Nails and spikes bad been used in constructing tbe boxing. Tbe roofing or flashing bad been torn and left open. Timbers used in the construction had been set in tbe gutters so as to retard tbe flow of the water, and it was claimed by tbe appellee that all these caused tbe water to back up over the openings in the roof, made by the spikes, and in the negligent construction of the boxing around the pipes, and to flow into the building, all of which produced the damage as alleged.

The questions, of fact in the case at first were as to whether the obstructions complained of caused the damage, and which of the defendants caused' the obstruction.

Judgment, by direction of the court, was in favor of all defendants except the appellant, and it has prosecuted this appeal. So, the question of fact now is as to whether the damage complained of was caused1 by the negligence of the appellant.

1. The appellant asked a peremptory instruction directing a verdict in its favor, and complains here of the refusal of the court to give this instruction, and contends that there was no evidence to sustain the verdict.

The facts concerning this are substantially as follows : The work upon the building occupied some weeks. During this time one heavy rain and other slight rains had fallen, but without damage to the building. The employees of the other defendants who had work to do upon the roof, and in connection with the tripod, cutting holes and making temporary boxing, etc., finished their work about the 19th of January. These employees testified that they kept the roof swept off each njght after finishing their work, and left it free from any material whatever.

On January 17, after the work had practically all been finished, an employee of appellant began work upon the building. He was cautioned to be careful not to leave blocks where they could be washed down into the conductor head and obstruct the flow of the water, and also about nailing into the roof; He was in a considerable hurry to get through with his work. He carried timbers on the roof, consisting of 2x4’s and shiplap. This was necessary for constructing the boxing around the pipe from the tank down into the roof, which work was to be done by the appellant. On the top of the boxing was placed building paper and then sheeting or shiplap. After the employee of appellant had finished his work on Saturday afternoon, there was a heavy rain on the Sunday following.

Banks, a witness on behalf of the appellee, who was called early Monday morning to go upon the roof to repair the defects that had caused the leaking, testified concerning the conditions found by him, as follows: “They boxed right down into the roof, and nailed into the cribbing; they also brought a 2x4 down on the corner facing, and nailed the boxing right into this very corner. They also placed one boxing a little further on the north side of this tripod, that is west of it on the north side. In doing that they had torn the flashing or roofing extending up around this cribbing, and prevented the flow of the water coming in on the north side, as well as part of it on the east side. The flashing was torn by nailing this piece. They nailed a board 2x4 down into the roof. They used some small nails, but there were some spikes used.”

The witness states that that was the cause of the overflow in the building. Continuing, the witness stated that he found the conductor-head of the down-spout or gutter choked up, describing the condition as stated above. He then stated that he tore away the obstruction that had been placed there, and repaired his part of the work that had been destroyed. He said that the blocks that were in the conductor-head were 2x4’s, such as were used by the employees of appellant in boxing around the pipe. He described the obstructions that he found in the gutter, on the roof and in the conductor-head and down in the down-pipe or gutter. He says the boxing, as he found it on the morning of the 29th, after the rain, was not more than three inches from the wall and came right down to the roof. ■ When he left it he left a passageway for the gutter between the cribbing and the walls about two feet wide. There were heavy rains before the boxing was put in by the appellant around the pipe, and no damage occurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Millison v. Ades of Lexington, Inc.
277 A.2d 579 (Court of Appeals of Maryland, 1971)
Easley v. Inglis
346 S.W.2d 206 (Supreme Court of Arkansas, 1961)
Whaley v. Crutchfield
294 S.W.2d 775 (Supreme Court of Arkansas, 1956)
Missouri Pacific Railroad v. Clements
281 S.W.2d 936 (Supreme Court of Arkansas, 1955)
McCollum v. O'NEILL
281 P.2d 493 (Montana Supreme Court, 1955)
Kennedy v. Clayton
227 S.W.2d 934 (Supreme Court of Arkansas, 1950)
American Bitumuls Co. v. Tax Court of Puerto Rico
66 P.R. 364 (Supreme Court of Puerto Rico, 1946)
American Bitumuls Co. v. Tribunal de Contribuciones de Puerto Rico
66 P.R. Dec. 382 (Supreme Court of Puerto Rico, 1946)
Kane v. Carper-Dover Mercantile Co.
177 S.W.2d 4 (Supreme Court of Arkansas, 1944)
Kansas City Southern Railway Co. v. Biggs
28 S.W.2d 68 (Supreme Court of Arkansas, 1930)
Madison-Smith Cadillac Co. v. Wallace
27 S.W.2d 524 (Supreme Court of Arkansas, 1930)
Penn-National Hardware Mutual v. Griffin
296 S.W. 66 (Supreme Court of Arkansas, 1927)
Indianapolis & Cincinnati Traction Co. v. Sherry
116 N.E. 594 (Indiana Court of Appeals, 1917)
Ara v. Rutland
172 S.W. 993 (Court of Appeals of Texas, 1915)
Cook v. Packard Motor Car Co.
92 A. 413 (Supreme Court of Connecticut, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
160 S.W. 889, 110 Ark. 49, 1913 Ark. LEXIS 366, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-fire-extinguisher-co-v-beal-doyle-dry-goods-co-ark-1913.