General Federal Construction, Inc. v. James A. Federline, Inc.

393 A.2d 188, 283 Md. 691, 1978 Md. LEXIS 464
CourtCourt of Appeals of Maryland
DecidedNovember 8, 1978
Docket[No. 30, September Term, 1978.]
StatusPublished
Cited by11 cases

This text of 393 A.2d 188 (General Federal Construction, Inc. v. James A. Federline, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Federal Construction, Inc. v. James A. Federline, Inc., 393 A.2d 188, 283 Md. 691, 1978 Md. LEXIS 464 (Md. 1978).

Opinion

Smith, J.,

delivered the opinion of the Court.

We shall here hold that the “one year clause” of the Maryland Statute of Frauds does not bar collection of damages for breach of an oral contract absent an express and specific provision in that contract that it was not to be performed within one year or a clear demonstration by its terms that it was not or could not be so performed. In the circumstances of this case we find that there was a clear demonstration that the contract could not be performed within one year. Thus, there must be a reversal.

This controversy arises from the construction of the Ambulatory Care Facility of Prince George’s General Hospital and Medical Center. Appellant, General Federal Construction, Inc. (General), is a general contractor. Appellee, James A. Federline, Inc. (Federline), submitted a bid to General for a subcontract for the mechanical work on this project. General was awarded the contract for the construction of the facility. It is conceded that Federline’s bid for the mechanical work was used by General in submitting its bid and was the low bid received at that time. General ultimately awarded the subcontract to someone other than Federline. Federline sued General alleging a breach of “an *693 express oral agreement” under which Federline was to do the mechanical portion of the work on the project.

General’s defense in the circuit court included a contention that recovery was barred under the terms of the Statute of Frauds (the statute) as in force in Maryland, now Maryland Code (1957,1978 Repl. Yol.) Art. 39C, § 1 (3), which provides that no action may be brought upon any agreement “not to be performed within the space of one year from the making thereof” unless “the contract or agreement upon which the action is brought, or some memorandum or note of it, is in writing and signed by the party to be charged, or some other person lawfully authorized by him.” This same language is found in the fourth section of the English Statute of Frauds, 29 Charles II, ch. 3, which, by reason of the provisions of Maryland Declaration of Rights Art. 5, was in effect in Maryland until its repeal by Chapter 649 of the Acts of 1971, which enacted a new statute. See 2 J. Alexander, British Statutes in Force in Maryland 509, 534-35 (2d ed„ W. Coe, 1912). The trial judge ruled as a matter of law that the statute did not preclude recovery. A judgment in the amount of $82,800 was entered in favor of Federline against General upon a jury’s verdict in the Circuit Court for Montgomery County. General appealed to the Court of Special Appeals. We granted the writ of certiorari prior to consideration of the case by that court.

For purposes of this case we need only address the first contention presented by General to us, that the trial judge erred in failing to direct a verdict in its favor on the issue of the Statute of Frauds.

There was testimony adduced on behalf of Federline flatly stating that the work could be performed within one year. Although the contract documents considered by prospective general contractors and subcontractors contain no specific statement of the time to be consumed in the project, there is no question but that it was estimated that 600 days would be required for completion. In support of its argument here on the matter of a directed verdict General points to this fact plus certain warranties which the subcontract bid documents required and work as to certain items which those documents *694 specified should be done subsequent to completion of the project.

Under the contract documents a subcontractor who did the work Federline says it was to do was required in certain instances to guarantee that all material and apparatus used would “be new, of first-class quality____” There were a number of instances in which certain work was specified to be performed upon the completion of the project such as demonstrating “proper operation of the plumbing controls,” and seeing that “all construction dirt [was] removed” from roof drains, water closets, urinals and the like. The mechanical contractor was specifically mandated to “provide the necessary skills and labor to assure the proper operation and to provide all required current and preventative maintenance for all equipment and controls provided under [one section of the contract] for a period of one year after substantial completion of the contract.” Also, when the condensor water system was placed in operation the subcontractor was obligated to “furnish a complete water treatment service for control of corrosion, carbonate scale and slime or algae” for the period of “one calendar year after Owner’s acceptance of installation____” The subcontractor was required to give “[a] one year warranty” as to heat pumps “for furnishing parts and labor for replacing any part of the conditioners] which [might become] defective in normal operation, with an additional four year warranty covering replacement of the hermetic compressor at the factory or authorized depot.” Certain other heating equipment was to have a one year warranty “for furnishing parts and labor for replacing any part of the control panel which [might become] defective in normal operation from the date of the original installation.”

In Ellicott v. Peterson, 4 Md. 476, 487-91 (1853), Chief Judge LeGrand carefully reviewed for our predecessors the law relative to the Statute of Frauds and contracts to be performed within one year. Judge McWilliams again examined the law for this Court in Sun Cab Co. v. Carmody, 257 Md. 345, 349-51, 263 A. 2d 1 (1970). He found that since the time of Ellicott the law has been well established in this *695 State that where there is a possibility that a contract may be performed within a year the remedy for breach of the contract is not barred by the Statute of Frauds, notwithstanding the fact that the parties might have intended that operation should extend through a much longer period. The old Maryland authority, W. Brantly, Law of Contracts % 59 at 139 (2d ed. 1922), states, “The statute does not apply if the contract can by any possibility be completed within a year, although the parties may have intended that its operation should extend through a much longer period and in fact it does so extend.” (Footnote omitted.)

Campbell v. Burnett, 120 Md. 214, 87 A. 894 (1913), is correctly cited in 2 A. Corbin, Contracts § 444 at 535 (1950), for the proposition that it makes no difference how long the parties expect the performance to take or how reasonable and accurate those expectations are, if the agreed performance can possibly be completed within a year. The full Corbin statement is:

“It makes no difference how long the agreed performance may be delayed or over how long a period it may in fact be continued. It makes no difference how long the parties expect performance to take or how reasonable and accurate those expectations are, if the agreed performance can possibly be completed within a year. Facts like these do not bring a contract within this provision of section 4. A provision in the contract fixing a maximum period within which performance is to be completed, even though that period is much in excess of one year, does not make the statute applicable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horowitz v. Greenberg
D. Maryland, 2024
Salisbury Building Supply Co. v. Krause Marine Towning Corp.
873 A.2d 452 (Court of Special Appeals of Maryland, 2005)
Heritage Oldsmobile-Imports v. Volkswagen of America, Inc.
264 F. Supp. 2d 282 (D. Maryland, 2003)
Friedman & Fuller, P.C. v. Funkhouser
666 A.2d 1298 (Court of Special Appeals of Maryland, 1995)
Learning Works, Inc. v. Learning Annex, Inc.
830 F.2d 541 (Fourth Circuit, 1987)
Learning Works, Inc. v. The Learning Annex, Inc.
830 F.2d 541 (Fourth Circuit, 1987)
Griffith v. One Investment Plaza Associates
488 A.2d 182 (Court of Special Appeals of Maryland, 1985)
Chesapeake Financial Corp. v. Laird
425 A.2d 1348 (Court of Appeals of Maryland, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
393 A.2d 188, 283 Md. 691, 1978 Md. LEXIS 464, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-federal-construction-inc-v-james-a-federline-inc-md-1978.