General Electric Lighting v. Koncelik, Unpublished Decision (3-31-2006)

2006 Ohio 1655
CourtOhio Court of Appeals
DecidedMarch 31, 2006
DocketNos. 05AP-310, 05AP-323.
StatusUnpublished
Cited by7 cases

This text of 2006 Ohio 1655 (General Electric Lighting v. Koncelik, Unpublished Decision (3-31-2006)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Electric Lighting v. Koncelik, Unpublished Decision (3-31-2006), 2006 Ohio 1655 (Ohio Ct. App. 2006).

Opinions

OPINION
{¶ 1} Joseph Koncelik, Director of Environmental Protection ("Ohio EPA"), appeals from an order of the Environmental Review Appeals Commission ("ERAC"), in which it found restrictions placed in an operating permit for General Electric Lighting ("GEL") were unreasonable. GEL also appeals ERAC's order that denied its motion for summary judgment and ERAC's order that denied its motion to place the burden of proof and burden of proceeding on Ohio EPA.

{¶ 2} As detailed below, Title V is a portion of the federal Clean Air Act, 42 U.S. Code 7661-7661f ("CAA" or "Act"), that establishes a program for the issuance of operating permits to certain individual sources of air pollutants. R.C. 3704.036 authorizes Ohio EPA to issue Title V permits for sources located in Ohio.

{¶ 3} GEL operates a lime glass-melting furnace in Logan, Ohio. GEL applied for a Title V permit in June 1996, and, on September 26, 2001, Ohio EPA issued a Title V permit to GEL. In addition to other restrictions, the permit required GEL to operate its electrostatic precipitator ("ESP") on a glass-production furnace within the range of 13 to 25 kilovolts for the secondary voltage and 21 to 60 milliamps for the secondary current. The ESP controls the emission of particulate matter from the glass-production furnace by using voltage and current to create electric fields in three groups of plates and needles. Each group of plates and needles is a "field" and collects particulate matter from flue gas as it passes through the plates and needles. A later modification of the present permit allowed the first field to operate at a minimum of 7 milliamps and the second and third fields to operate at a minimum of 16.5 milliamps. The permit indicated that the operation of the ESP outside the assigned parameters was a violation, even if the particulate emissions were under 0.2 pounds of emissions per ton of glass produced, which is the limit prescribed in federal regulations. The ESP requirement was in a section of the permit that was federally enforceable by the United States Environmental Protection Agency ("U.S. EPA"), and violations of the requirement could result in daily penalties of approximately $30,000. Ohio EPA asserts that this requirement is a more economical alternative to increasing the testing of the actual emissions from the furnace using a "stack test," each of which costs approximately $10,000 per test. Stack tests are typically performed at least once every three years.

{¶ 4} On October 23, 2001, GEL appealed the permit to ERAC. On November 12, 2002, Ohio EPA filed a motion for partial summary judgment. On November 27, 2002, GEL moved for summary judgment. One of the grounds in GEL's motion, as pertinent to GEL's present appeal, was that the voltage and current conditions were unlawful because they violated R.C. 3704.036(K)'s prohibition against including any "new substantive requirements" in the federally enforceable portion of a Title V permit.

{¶ 5} On August 21, 2003, ERAC ruled on the parties' motions for summary judgment. As pertinent to this appeal, ERAC denied the portion of GEL's motion and granted the portion of Ohio EPA's motion for summary judgment that addressed the issue of the ESP parameters. ERAC found that Ohio EPA's actions were lawful with regard to the setting of the ESP parameters because Ohio Adm. Code3745-77-07(A)(1) requires Title V permits to contain operational requirements and emission limitations that assure compliance with all applicable requirements at the time of issuance. ERAC ordered the parties to proceed to a de novo hearing regarding the reasonableness of the operational restrictions in the Title V permit.

{¶ 6} On November 3, 2003, GEL filed a motion for an order placing the burden of proof and burden of proceeding on Ohio EPA regarding the reasonableness of the operational restrictions on ESP voltage and current. On December 3, 2003, ERAC granted GEL's motion in part, finding that Ohio EPA had the burden of proceeding with evidence, but denied it insofar as it found GEL had the burden of proving that the operational restrictions were not reasonable.

{¶ 7} As a result of settlement negotiations, Ohio EPA and GEL resolved all of the issues pertinent to the pending ERAC appeal except for the reasonableness of the operational restriction related to the power input (voltage and current together) requirements for the ESP. ERAC held a hearing on March 30 and 31, 2004, and thereafter ERAC issued an order finding that, although the permit and the operational restrictions therein were lawful, the restrictions prescribing the power input parameters on GEL's ESP were unreasonable. Ohio EPA has appealed to this court ERAC's final order, and GEL has appealed ERAC's pre-hearing orders in which it denied GEL summary judgment and found it had the burden of proof at the hearing de novo.

{¶ 8} GEL asserts the following assignments of error:

1. The Environmental Review Appeals Commission erred in its denial of Appellant General Electric Lighting's motion for summary judgment on the ground that restrictions on the operation of an air pollution control device initially imposed by the Director of Environmental Protection in a Title V permit to operate are not new substantive requirements prohibited by O.R.C. Section 3704.036(K).

2. The Environmental Review Appeals Commission erred in ruling in a prehearing order that Appellant General Electric Lighting has the burden of proving at the hearing de novo that restrictions on the operation of an air pollution control device introduced by the Director of Environmental Protection in a Title V permit to operate are unlawful or unreasonable.

{¶ 9} Ohio EPA asserts the following assignment of error:

The Director had a valid factual foundation for requiring GE to properly operate its pollution control equipment; therefore, ERAC erred by eliminating the operational restriction that required proper operation.

{¶ 10} In reviewing ERAC orders, this court is guided by the standard contained in R.C. 3745.06. R.C. 3745.06 indicates this court "shall affirm the order" if we find "upon consideration of the entire record and such additional evidence as the court has admitted, that the order is supported by reliable, probative, and substantial evidence and is in accordance with law." "In the absence of such a finding," the court "shall reverse, vacate, or modify the order or make such other ruling as is supported by reliable, probative, and substantial evidence and is in accordance with law." Id. Reliable evidence is evidence that can be trusted. Our Place, Inc. v. Ohio Liquor Control Comm. (1992), 63 Ohio St.3d 570, 571. In order for evidence to be reliable, there must be a reasonable probability that it is true. Id. Probative evidence is evidence that tends to prove the issue in question, while substantial evidence is evidence that carries weight, or evidence that has importance and value. Id.

{¶ 11} Ohio EPA argues that we should begin our analysis with the question of whether the restrictions are reasonable. If we affirm ERAC's finding that they are unreasonable, EPA continues, then we need not reach the question of whether they are unlawful.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oxford Mining Co., L.L.C. v. Nally
2015 Ohio 182 (Ohio Court of Appeals, 2015)
Citizens Against Am. Landfill Expansion v. Koncelik
2014 Ohio 123 (Ohio Court of Appeals, 2014)
Ohio Fresh Eggs v. Wise, 07ap-780 (5-20-2008)
2008 Ohio 2423 (Ohio Court of Appeals, 2008)
Textileather Corp. v. Korleski, 06-Ap-955 (8-14-2007)
2007 Ohio 4129 (Ohio Court of Appeals, 2007)
Citizens Against Megafarm Dairy v. Dailey, 06ap-836 (5-31-2007)
2007 Ohio 2649 (Ohio Court of Appeals, 2007)
Ackison v. Anchor Packing Co., Unpublished Decision (12-20-2006)
2006 Ohio 7099 (Ohio Court of Appeals, 2006)
Wagner v. Anchor Packing Co., Unpublished Decision (12-20-2006)
2006 Ohio 7097 (Ohio Court of Appeals, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
2006 Ohio 1655, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-electric-lighting-v-koncelik-unpublished-decision-3-31-2006-ohioctapp-2006.