General Dynamics Information Technology, Inc. v. Wireless Properties, LLC

714 F. Supp. 2d 211, 2010 U.S. Dist. LEXIS 51404, 2010 WL 2070279
CourtDistrict Court, D. Massachusetts
DecidedMay 25, 2010
DocketCivil Action 09-12090-JLT
StatusPublished

This text of 714 F. Supp. 2d 211 (General Dynamics Information Technology, Inc. v. Wireless Properties, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Dynamics Information Technology, Inc. v. Wireless Properties, LLC, 714 F. Supp. 2d 211, 2010 U.S. Dist. LEXIS 51404, 2010 WL 2070279 (D. Mass. 2010).

Opinion

MEMORANDUM

TAURO, District Judge.

I. Introduction

This action arises out of an agreement between Plaintiff General Dynamics Information Technology, Inc., and Defendant Wireless Properties, LLC, by which Plaintiff was to provide Defendant with telecommunication infrastructure support services. Through its Complaint, Plaintiff now seeks to recover overdue payment for *213 services already rendered to Defendant. Presently at issue is Defendant’s Motion to Stay Proceedings and Compel Arbitration [# 10]. For the reasons set forth below, Defendant’s Motion to Stay Proceedings and Compel Arbitration [# 10] is ALLOWED.

II. Background 1

On October 26, 2007, Plaintiff and Defendant entered into a Master Services Agreement (the “MSA”) by which Plaintiff agreed to provide telecommunication infrastructure support services to Defendant. Pursuant to the MSA, Defendant sent Plaintiff periodic requests for price quotations as to specific projects it wished to pursue. Plaintiff provided a statement of work in response and Defendant, in turn, issued a purchase order if it decided to proceed with the project.

Unless the parties explicitly agreed otherwise, the MSA governed the terms of each project. The MSA required Plaintiff to provide Defendant with monthly invoices, each of which Defendant had an obligation to pay within thirty days of receipt. Any undisputed items on an invoice that were not paid within thirty days accrued interest at a rate of one percent per month.

Pursuant to the Dispute Resolution clause contained in paragraph 20 of the MSA, “any dispute or controversy between the Parties arising under or in connection with the Agreement (‘Dispute’) shall be settled exclusively” 2 by means of binding arbitration to be held in Nashville, Tennessee. Paragraph 20 and Paragraph 7(b) of the MSA provide for a narrow exception to dispute resolution by arbitration if, and only if, the dispute at issue is confined to the recovery of payment on undisputed invoices. Under such circumstances, the MSA permits Plaintiff to pursue a remedy “through initiation of litigation in a court of competent jurisdiction in the Commonwealth of Massachusetts.” 3

The MSA also contains a Force Majeure/Excusable Delay Provision which temporarily excuses nonperformance in the case of an enumerated Force Majeure event or due to excusable delay “... caused by Customer or its employees, agents, suppliers or other third party contractors supporting Customer, provided that such circumstances were not reasonably foreseeable by such Party and, by the exercise of reasonable commercial due diligence, could not have been prevented by such Party.” 4 The Provision specifies that, in the face of a Force Majeure event, the affected party must promptly provide notice to the other party, at which time it may suspend performance without penalty. But if the nonperformance “exceeds thirty days from receipt of .the notice of the Force Majeure Event, either Party may terminate for convenience the affected Purchase Order.” 5 The Force Majeure/Excusable Delay Provision does not, however, specify the protocol to be followed by the parties in the case of excusable delay.

Since the Parties entered the MSA, Defendant has issued purchase orders for, and Plaintiff has subsequently provided, $1,376,000.00 in services. But as of July 2008, Defendant began to fall behind in paying the invoices in a timely manner. *214 In December 2008, Plaintiff made a formal demand for immediate payment of the $912,529.21 owed to it as of that time. On April 6, 2009, Defendant sent a letter to Plaintiff acknowledging that it owed Plaintiff such amount and stating that it was in the process of selling some assets, so as to be able to remit payment. On May 28, 2009, Defendant made a payment of $100,000 and promised to pay the balance of the outstanding debt within two weeks. On July 10, 2009, Defendant made an additional payment of only $25,000.

From May 2009 until the end of October 2009, Defendant made repeated promises to pay all outstanding amounts due Plaintiff and indicated that it planned to conduct a sale of additional assets to facilitate payment. On October 29, 2009, however, Defendant informed Plaintiff that it was invoking the Force Majeure/Excusable Delay Provision contained in paragraph 10 of the MSA because a third party had failed to provide it financing which would have enabled it to submit payment on the overdue invoices. In response, Plaintiff took the position that a failure to secure financing did not amount to either a Force Majeure event or excusable delay and, in any event, the failure to provide financing had occurred over a year prior and, thus, Defendant had failed to promptly notify Plaintiff of the alleged Force Majeure event.

Defendant still has not paid the balance of its debt due Plaintiff. As of the time of the Complaint, the amount owing was $899,002.96.

III. Discussion

Plaintiffs Complaint characterizes this action as an effort to recover payment on undisputed invoices, which is not subject to arbitration as per paragraphs 20 and 7(b) of the MSA. And, notably, Defendant has indeed never disputed the amount due on the invoices. Nonetheless, Defendant seeks an order from this court compelling the Parties to arbitrate the present dispute because the dispute is not confined to the issue of the undisputed invoices. Rather, Defendant contends that the face of the Complaint demonstrates that any recovery depends upon a threshold determination of whether the Force Majeure/Excusable Delay Provision applies to the underlying facts and how such application impacts the recovery to which Plaintiff is immediately entitled on the undisputed invoices. 6 This court agrees with Defendant and must compel arbitration.

“Arbitration is a matter of contract and a party cannot be required to submit to arbitration any dispute which [it] has not agreed to so submit....” 7 But neither may a Party avoid arbitration if it has agreed to such. Accordingly, the Federal Arbitration Act (FAA) requires courts *215 to stay judicial proceedings and compel arbitration where the parties have previously agreed to arbitration as the sole means of resolving a dispute. 8 “[Wjhether or not [a party is] bound to arbitrate, as well as what issues it must arbitrate, is a matter to be determined by the Court on the basis of the contract entered into by the parties.” 9

As a general matter, where a contract contains an arbitration clause, there is a strong presumption in favor of the arbitrability of the dispute. 10 This presumption gives way only

Free access — add to your briefcase to read the full text and ask questions with AI

Related

At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
Combined Energies v. CCI, INC.
514 F.3d 168 (First Circuit, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
714 F. Supp. 2d 211, 2010 U.S. Dist. LEXIS 51404, 2010 WL 2070279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-dynamics-information-technology-inc-v-wireless-properties-llc-mad-2010.