GenConn Energy, LLC v. Public Utilities Regulatory Authority

348 Conn. 532
CourtSupreme Court of Connecticut
DecidedFebruary 27, 2024
DocketSC20716
StatusPublished
Cited by2 cases

This text of 348 Conn. 532 (GenConn Energy, LLC v. Public Utilities Regulatory Authority) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GenConn Energy, LLC v. Public Utilities Regulatory Authority, 348 Conn. 532 (Colo. 2024).

Opinion

GENCONN ENERGY, LLC v. PUBLIC UTILITIES REGULATORY AUTHORITY (SC 20716) Robinson, C. J., and McDonald, D’Auria, Mullins, Ecker, Alexander and Moll, Js.

Syllabus

Pursuant to statute (§ 16-243u), ‘‘in an annual retail generation rate contested case,’’ a peaking generation facility ‘‘shall be entitled to recover its prudently incurred costs,’’ and the Public Utilities Regulatory Authority (PURA) ‘‘shall review such recovery of costs consistent with the princi- ples set forth in sections 16-19, 16-19b and 16-19e . . . .’’ Pursuant further to statute (§ 16-19e (a) (4)), PURA shall examine and review a peaking generation facility’s recoverable costs to ensure ‘‘that the level and structure of rates be sufficient, but no more than sufficient,’’ to cover the facility’s operating costs.

The plaintiff electric supplier, G Co., appealed to the trial court from the final decision of the defendant, PURA, which reduced G Co.’s proposed return on capital with respect to two of G Co.’s peaking generation facilities that were designed to provide additional electric supply to Connecticut consumers at times of increased demand. G Co., as a peak- ing generation provider, is required to submit its Annual Fixed Revenue February 27, 2024 CONNECTICUT LAW JOURNAL Page 3

348 Conn. 532 FEBRUARY, 2024 533 GenConn Energy, LLC v. Public Utilities Regulatory Authority Requirements application (application) to PURA every year to set out the recoverable capital it seeks for the upcoming year. In determining the allowable recoverable capital, PURA first determines the peaking generation facility’s rate base, which represents the value of the property on which the facility is permitted to earn a rate of return. The rate base is then divided based on the debt-to-equity ratio to find the portion of the rate base that is attributable to each. Finally, the portion of the rate base that is attributable to debt and the portion that is attributable to equity are multiplied by the applicable rate to find the total amount the facility should be allowed to recover. For each of G Co.’s applications for 2010 through 2020, it sought and was allowed to recover, as part of the recoverable capital, its actual annual financing costs. When G Co. submitted its 2021 application, PURA concluded that G Co. was not entitled to recover the entire $8.573 million actual interest expense and determined that a reduction was warranted. PURA found that there were certain inaccuracies in both the debt-to-equity ratio and the debt rate proposed by G Co., and that G Co.’s miscalculations would lead to an overrecovery of costs. PURA’s solution was to maintain G Co.’s proposed debt-to-equity ratio but to reduce the debt rate, ultimately reducing G Co.’s recoverable capital by approximately $2.861 million. According to PURA, this result would be more in line with the recovery contemplated by § 16-19e (a) (4), in that the rates paid by consumers would be ‘‘sufficient, but no more than sufficient,’’ to cover G Co.’s capital costs. PURA therefore approved G Co.’s 2021 application but only authorized a return on interest of approximately $5.712 million rather than the $8.573 million that G Co. sought. The trial court rendered judgment dismissing G Co.’s administrative appeal, concluding that PURA was authorized to adjust G Co.’s overall recovery as it did. On appeal from the trial court’s judgment, G Co. claimed, inter alia, that § 16-243u required PURA to use the statute’s specific rate-making meth- odology applicable to peaking generation and not the general rate-mak- ing principles found in § 16-19e, and that the plain language of § 16-243u did not give PURA the authority to lower the recovery of G Co.’s actual annual financing costs. Held:

1. The trial court correctly determined that PURA had acted within its statutory authority to lower G Co.’s debt rate in its decision on G Co.’s 2021 application, PURA having acted pursuant to its authority under § 16-243u when it reviewed G Co.’s recovery of costs consistent with the general rate-making principles of § 16-19e:

Because § 16-243u incorporates § 16-19e by reference, the plain meaning of § 16-243u must be determined by considering § 16-19e alongside of it, and, when the two statutes are considered together, it is clear that § 16-243u directs PURA to review a peaking generation facility’s recover- able costs pursuant to § 16-19e (a) (4) to ensure that the rates are ‘‘suffi- Page 4 CONNECTICUT LAW JOURNAL February 27, 2024

534 FEBRUARY, 2024 348 Conn. 532 GenConn Energy, LLC v. Public Utilities Regulatory Authority cient, but no more than sufficient,’’ to allow a peaking generation facility to cover its operating costs.

Moreover, there was no merit to G Co.’s claim that § 16-243u’s reference to § 16-19e authorizes PURA only to consider the principles in § 16-19e for the recovery of costs but not for the setting of rates, as cost recovery and rate setting are interrelated in that a peaking generation facility recovers its costs only through the setting of rates.

Furthermore, G Co.’s contention that PURA must allow a full recovery of costs for any costs that were previously deemed ‘‘prudent,’’ without any additional evaluation, would render the language in § 16-243u requiring an ‘‘annual retail generation rate contested case’’ and a review by PURA of ‘‘recovery of costs consistent with the principles set forth in [§] . . . 16-19e’’ meaningless.

In addition, although it was undisputed that PURA previously determined that the interest costs that G Co. had incurred from a 2012 refinancing of its debt were prudent, PURA had the authority, under § 16-243u, to reevaluate and recharacterize costs that were previously deemed pru- dently incurred in a prior year and to determine that they nevertheless may not properly be recovered from consumers in a subsequent year.

There also was no merit to G Co.’s claim that PURA had violated the plain language of § 16-243u by preventing G Co. from recovering a reason- able rate of return on equity when it disallowed some of G Co.’s recovery of costs and thus effectively reduced the rate of return on equity to less than the amount on which the parties had previously agreed, as the reduction in G Co.’s recoverable capital resulted from a reduction in the debt rate rather than a reduction of the rate of return on equity, and, accordingly, PURA allowed a reasonable rate of return on equity pursuant to the same rate of return on equity that had previously been agreed on by the parties.

This court concluded that G Co.’s interpretation of the statutory scheme, if applied, would leave PURA powerless to fix excess recoveries, which would conflict with the plain meaning of § 16-243u and with the broad authority granted to PURA in § 16-19e to set rates.

2. PURA’s action in lowering the debt rate in its decision on G Co.’s 2021 application after not doing so for more than one decade was not arbitrary and capricious, as the administrative record contained substantial evi- dence to support PURA’s conclusion that a reduction in G Co.’s debt rate was necessary:

The evidence presented and examined by PURA provided a substantial basis from which PURA reasonably could infer that G Co. had sought an overrecovery of costs, that finding supported PURA’s conclusion that an adjustment was necessary to ensure that the rates set by G Co. were, February 27, 2024 CONNECTICUT LAW JOURNAL Page 5

348 Conn. 532 FEBRUARY, 2024 535 GenConn Energy, LLC v. Public Utilities Regulatory Authority pursuant to § 16-19e (a) (4), ‘‘no more than sufficient’’ to allow G Co. to recover its costs, and PURA provided an adequate and full explanation in both its final decision and subsequent briefs for the reasons behind the change. (One justice dissenting) Argued September 8, 2023—officially released February 27, 2024

Procedural History

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
348 Conn. 532, Counsel Stack Legal Research, https://law.counselstack.com/opinion/genconn-energy-llc-v-public-utilities-regulatory-authority-conn-2024.