Gary Spivey, Owner of America's Choice Roofing and AmChoice, LLC Dba America's Choice Roofing v. Joann Goodwin

CourtCourt of Appeals of Texas
DecidedJune 7, 2017
Docket10-16-00178-CV
StatusPublished

This text of Gary Spivey, Owner of America's Choice Roofing and AmChoice, LLC Dba America's Choice Roofing v. Joann Goodwin (Gary Spivey, Owner of America's Choice Roofing and AmChoice, LLC Dba America's Choice Roofing v. Joann Goodwin) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gary Spivey, Owner of America's Choice Roofing and AmChoice, LLC Dba America's Choice Roofing v. Joann Goodwin, (Tex. Ct. App. 2017).

Opinion

IN THE TENTH COURT OF APPEALS

No. 10-16-00178-CV

GARY SPIVEY, OWNER OF AMERICA'S CHOICE ROOFING AND AMCHOICE, LLC DBA AMERICA'S CHOICE ROOFING, Appellants v.

JOANN GOODWIN, Appellee

From the County Court Robertson County, Texas Trial Court No. 15-17-CV

MEMORANDUM OPINION

In four issues, appellants, Gary Spivey, owner of America’s Choice Roofing, and

AmChoice, LLC, challenge the trial court’s judgment. Specifically, appellants contend

that the trial court erred by: (1) failing to award judgment for appellants under a written

contract with appellee, Jo Ann Goodwin; (2) granting relief on a theory of breach of

implied warranty that was not pleaded or supported; (3) failing to award interest at the rate established in the contract; and (4) denying any award of attorney’s fees. Because

we conclude that the trial court erred, we modify the judgment to reflect a $2,900 damage

award in favor of appellants and to include awards of attorney’s fees and interest

provided by the underlying contract. We affirm as modified.1

I. BACKGROUND

This dispute arises out of a written contract for the replacement of a residential

roof. On March 17, 2015, Goodwin entered into a contractual agreement with appellants

for the installation of a roof on a property owned by Goodwin in Calvert, Texas. Pursuant

to the agreement, Goodwin would pay $33,236.03 in exchange for appellants installing a

new roof, decking, drip edges, valleys, ventilation, insulation, shingles and related

materials, and labor, including the removal and installation of such roof materials. The

charges under the contract were to be paid in two installments—$16,168.01 on the

delivery of the materials and $16,168.02 on the final walk-through. Furthermore, at no

additional cost, appellants agreed to install 150 feet of gutters on the home.

Later, on May 1, 2015, Goodwin and appellant entered into a written change order

that modified the work to be completed under the contract. For an additional $900 from

Goodwin, appellants agreed “to include remaining 35 Linear Feet of gutters for flat

portion of roof above and beyond original contract, dated March 17, 2015.”

1We note that Goodwin is pro se on appeal and was pro se in the trial court. She has not filed an appellee’s brief in this matter. Instead, she has filed a collection of documents that appear to be similar to the evidence she relied upon in the trial court.

Spivey v. Goodwin Page 2 The record reflects that Goodwin made two payments under the contract. She

paid the first installment of $16,168.01 on April 28, 2015. However, as work commenced

on the roof, Goodwin became dissatisfied. As noted at trial, Spivey met with Goodwin

because she was upset about the job. When conducting a walk-through of the work,

Goodwin identified a number of changes she wanted, including rebuilding two finials

that she alleged had been damaged during the work. Appellants repaired the finials.

Goodwin also requested patching of a flat section of the roof, although that section of the

roof was not within the scope of the original contract. Spivey testified that he tried to

make Goodwin happy by putting “a coating over the flat roof.” Further, Goodwin

requested that appellants paint the chimney flashing because “something about the paint

didn’t look right.” Appellants repainted all of the chimneys.

At the conclusion of her meeting with Spivey, Goodwin provided a second check

in the amount of $14,168.02. In the memo portion of the check, Goodwin handwrote

“balance due $2,900.” Goodwin withheld the remaining balance of $2,900 because she

did not believe that the work was completed. In any event, in June 2015, appellant sent

a final invoice to Goodwin requesting the remaining $2,900. Goodwin argued that the

work was not complete and refused to pay, thus prompting a second invoice from

appellants for the $2,900. Goodwin once again complained about the work on the flat

section of the roof, refused to pay the remaining balance, and threatened suit.

Spivey v. Goodwin Page 3 On November 10, 2015, Goodwin filed suit in justice court in Robertson County

against “Gary Spivey, Owner of America’s Choice Roofing,” asserting damages in the

amount of $2,900 because “3 flat roofs are . . . leaking” and some of her gutters are rusted.

Spivey filed an answer denying Goodwin’s allegations. Thereafter, AmChoice

intervened asserting counterclaims of breach of contract and quantum meruit against

Goodwin. AmChoice also pled for the recovery of attorney’s fees, as well as pre- and

post-judgment interest.

After a bench trial, the justice court rendered two separate judgments—a take-

nothing judgment on Goodwin’s claims against Spivey and a judgment against Goodwin

on the breach-of-contract counterclaim. Appellants were awarded $3,841 in damages,

which was comprised of $2,000 in damages under the contract, $1,800 in attorney’s fees,

and $41 in court costs. Goodwin appealed the justice court’s judgment to the County

Court. Appellants refiled their pleadings in the County Court.

On January 28, 2016, this matter was tried in the Robertson County Court.

Goodwin represented herself, and the record reflects that she did not call any witnesses,

though she did submit numerous documents to support her contentions. Goodwin

contended that the work on the flat-roof sections was part of the original contract and

that she had to pay Lopez Construction $1,300 to correct the work of appellants on the

flat-roof sections. Spivey, as well as AmChoice employee Chuck Allen, testified at trial.

At the conclusion of the trial, the trial court awarded appellants $1,600 in damages, which

Spivey v. Goodwin Page 4 constituted a $1,300 reduction of the $2,900 Goodwin allegedly owed under the contract.

This reduction corresponded with the amount Goodwin paid to Lopez Construction. The

trial court also declined to award costs, interest, or attorney’s fees to either party. At the

request of appellants, the trial court entered findings of fact and conclusions of law.

Subsequently, appellants filed their joint notice of appeal.

II. ANALYSIS

In their first and second issues, appellants contend that the trial court erred by

failing to award judgment for appellants under the written contract and by granting relief

to Goodwin on a theory of breach of implied warranty that was not pleaded, nor

supported by evidence.

As noted earlier, appellants asserted counterclaims of breach of contract and

quantum meruit. A breach of contract occurs when a party fails to perform an act that it

has explicitly or impliedly promised to perform. Esty v. Beal Bank S.S.B., 298 S.W.3d 280,

299 (Tex. App.—Dallas 2009, no pet.). The elements of a breach-of-contract claim are: (1)

the existence of a valid contract between the plaintiff and defendant; (2) the plaintiff’s

performance or tender of performance; (3) the defendant’s breach of the contract; and (4)

the plaintiff’s damages as a result of that breach. Id. In arguing that Goodwin breached

the original contract, appellants challenge several findings of fact made by the trial court.

Findings of fact entered in a non-jury case have the same force and dignity as a

jury’s answers to jury questions. Anderson v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Farm Life Insurance Co. v. Martinez
216 S.W.3d 799 (Texas Supreme Court, 2007)
Ingram v. Deere
288 S.W.3d 886 (Texas Supreme Court, 2009)
Smith v. Patrick W.Y. Tam Trust
296 S.W.3d 545 (Texas Supreme Court, 2009)
Cooke County Tax Appraisal District v. Teel
129 S.W.3d 724 (Court of Appeals of Texas, 2004)
San Antonio Villa Del Sol Homeowners Ass'n v. Miller
761 S.W.2d 460 (Court of Appeals of Texas, 1988)
Anderson v. City of Seven Points
806 S.W.2d 791 (Texas Supreme Court, 1991)
Ragsdale v. Progressive Voters League
801 S.W.2d 880 (Texas Supreme Court, 1990)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
State Farm Life Insurance Co. v. Martinez
174 S.W.3d 772 (Court of Appeals of Texas, 2005)
Westchester Fire Insurance Co. v. Nuckols
666 S.W.2d 372 (Court of Appeals of Texas, 1984)
Melody Home Manufacturing Co. v. Barnes
741 S.W.2d 349 (Texas Supreme Court, 1987)
Goudeau v. Marquez
830 S.W.2d 681 (Court of Appeals of Texas, 1992)
Esty v. Beal Bank S.S.B.
298 S.W.3d 280 (Court of Appeals of Texas, 2009)
World Help v. Leisure Lifestyles, Inc.
977 S.W.2d 662 (Court of Appeals of Texas, 1998)
Hassell Const. Co., Inc. v. Stature Commercial Co.
162 S.W.3d 664 (Court of Appeals of Texas, 2005)
New Amsterdam Casualty Co. v. Texas Industries, Inc.
414 S.W.2d 914 (Texas Supreme Court, 1967)
Walker v. Packer
827 S.W.2d 833 (Texas Supreme Court, 1992)
Bocquet v. Herring
972 S.W.2d 19 (Texas Supreme Court, 1998)
Tony Gullo Motors I, L.P. and Brien Garcia v. Nury Chapa
212 S.W.3d 299 (Texas Supreme Court, 2006)
DeGroot v. DeGroot
369 S.W.3d 918 (Court of Appeals of Texas, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Gary Spivey, Owner of America's Choice Roofing and AmChoice, LLC Dba America's Choice Roofing v. Joann Goodwin, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gary-spivey-owner-of-americas-choice-roofing-and-amchoice-llc-dba-texapp-2017.