Gary Hibbeln v. Ken Jordan
Opinion
RENDERED: JULY 9, 2021; 10:00 A.M.
NOT TO BE PUBLISHED
Commonwealth of Kentucky
Court of Appeals
NO. 2020-CA-0991-MR
GARY HIBBELN APPELLANT
APPEAL FROM JEFFERSON CIRCUIT COURT v. HONORABLE OLU A. STEVENS, JUDGE ACTION NO. 13-CI-04376
KEN JORDAN; AND KEN JORDAN CONTRACTING, LLC APPELLEES
OPINION AFFIRMING
** ** ** ** **
BEFORE: MAZE, TAYLOR, AND K. THOMPSON, JUDGES.
MAZE, JUDGE: Gary Hibbeln (Hibbeln) appeals from a judgment of the
Jefferson Circuit Court dismissing his claims against Ken Jordan and Ken Jordan
Contractors, LLC (collectively, “Jordan”). This is the third appeal of this case,
following two prior remands by this Court. We conclude that the “law of the case”
doctrine precludes Hibbeln from raising issues which were not presented in the
first appeal. We further conclude that the trial court properly applied the mandate
of this Court on remand and did not err by denying Hibbeln’s motion to re-open
the proof for new evidence. Hence, we affirm.
The relevant facts of this matter were set forth in a prior appeal as
follows:
The property at issue is a historic residence located at 1308 Highland Avenue, Louisville, Kentucky. Prior to Ken Jordan’s involvement, the residence was ordered to be demolished; however, the property was spared. Hibbeln and his partner on the Highland Avenue project, Stayce McCracken, met Jordan who was performing insurance claim work at the property to repair a collapsed chimney. Based on Jordan’s work, Hibbeln and McCracken hired Jordan as the general contractor for additional renovations on the residence.
In June 2010, Jordan submitted a proposal to Hibbeln listing several repairs to be made. The cost of the individual repairs was not listed, but the total amount for all repairs was estimated to be $87,290.00. The proposal further provided that payments for the work were to be made on a weekly schedule, in accordance with the proposal. Hibbeln signed the proposal, and payments were made, more or less, according to schedule. Hibbeln paid Ken Jordan Contractors a total of $85,764.00 under the June 2010 proposal.
A second proposal was submitted by Jordan to Hibbeln in October 2010. The proposal listed ten repairs to be completed and a total estimated cost of $5,100.00. Hibbeln paid $4,590.00 under the second proposal. In all, Hibbeln paid $90,354.00 to Ken Jordan Contractors for reconstruction services.
On August 10, 2013, Hibbeln filed a complaint against Jordan claiming breach of contract, conversion, and bad faith. He sought compensatory and consequential damages, attorney fees, and punitive damages.
The matter was set for trial on February 18, 2016. . . .
...
At trial, several witnesses testified, including Gary Hibbeln, Stayce McCracken, home renovation expert John Klienholter, architect Mark Bailey, all in addition to Ken Jordan.
The renovation work was initially performed without incident. However, according to Hibbeln and McCracken, progress slowed considerably, and Jordan was no longer coming to the job site to supervise his workers. Mark Bailey was hired as the architect on the project, but he was terminated when Hibbeln and McCracken decided his services were no longer needed. As Jordan’s work continued, Hibbeln and McCracken became less satisfied. Nevertheless, payments to Jordan continued based upon the payment schedule called for in the first proposal, without presenting any quality or progress complaints to Jordan. Hibbeln and McCracken further contended they gave Jordan additional projects in the fall of 2010 with hopes to motivate his performance on the residence.
After some attempt to work through the issues with Jordan, Hibbeln and McCracken decided to terminate his services in early 2011. Another contractor was hired to take over the project to fix and complete Jordan’s work. Hibbeln testified that he paid $87,239.51 to this other contractor to fix Jordan’s work on the residence.
John Klienholter testified as Hibbeln’s expert witness. He had twenty-five years’ experience as a contractor. He went to the residence and performed an inspection. He examined photographs provided by Hibbeln of Jordan’s work. Klienholter provided estimates for the costs of various line items contained in Jordan’s first proposal for a home similar to the subject of this litigation.
At the conclusion of Hibbeln’s case, Jordan moved to dismiss his claim for conversion, punitive damages, and attorney fees. The court granted Jordan’s motion. Jordan followed with his proof, the trial concluded, and the case was submitted.
The Jefferson Circuit Court found the following:
The Court finds the parties had an agreement and that a written contract signed by both parties is unnecessary under the circumstances. The Court determines that the Defendant was paid in accordance with the schedule of payments, regardless of whether the work was actually performed. There is a conflict in testimony, but the Court further determines that the Defendant did not complete the work as contemplated by the parties’ agreement. The testimony established that the following work was completed: Pull building back and straighten building, remove existing footer, pour new footer/foundation wall, removal of existing footer along left side and a portion of the sheathing installation. The Court finds that the remaining work was not completed or was completed in an unsatisfactory manner. Neither party was able to testify as to the specific amount charged for each task listed on Plaintiff’s exhibits one and two, but Plaintiff’s expert, John Klienholter, testified as to the costs for each item listed on Plaintiff’s exhibit one (1). He acknowledged those figures were “ballpark”
estimates. In all, Plaintiff claims he paid Defendant about $66,000 for work that was not completed or completed in an unsatisfactory manner. Based on the testimony, the Court determines approximately 50% of the total contemplated repairs were either not completed or not completed in a satisfactory manner. Accordingly, judgment shall be entered for the Plaintiff in the amount of $45,000 plus court costs. Post-judgment interest shall accrue at 12% per annum.
Jordan v. Hibbeln [Jordan I], No. 2016-CA-000406-MR, 2018 WL 3090442, at
*1–2 (Ky. App. Jun. 22, 2018).
In the first appeal, this Court reversed the judgment for Hibbeln,
concluding that “Hibbeln failed to provide the court with sufficient evidence to
determine calculable, non-speculative damages. The lack of evidence renders the
circuit court’s award of $45,000 in damages erroneous.” Id. at *5. Consequently,
this Court vacated the judgment and remanded, giving the circuit court explicit
direction to enter a new judgment explaining the non-speculative method used for
calculating damages and the evidence supporting the award. Specifically, the
panel directed the circuit court to determine either: “(1) that Hibbeln failed to
carry his burden of presenting non-speculative proof of his damages, or (2) that
Hibbeln did carry his burden of presenting non-speculative damages, but that the
judgment failed to articulate that proof in a way that would facilitate rather than
frustrate appellate review.” Id. at *6.
On remand, the trial court entered a new judgment for Hibbeln for
$45,000. In a subsequent appeal, this Court again reversed, finding that the trial
court failed to comply with the Court’s mandate from the prior appeal. Ken Jordan
& Ken Jordan Contractors, LLC v. Hibbeln [Jordan II], No. 2019-CA-000310-
MR, 2019 WL 6248320, at *3 (Ky. App. Nov. 22, 2019). Consequently, the Court
again remanded the matter for the findings required by Jordan I. Id.
On the second remand, the trial court entered new findings and a
judgment. In pertinent part, the trial court found as follows:
Free access — add to your briefcase to read the full text and ask questions with AI
Gary Hibbeln v. Ken Jordan (Gary Hibbeln v. Ken Jordan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.