Garden Grove Galleria v. Cathay Bank CA4/3

CourtCalifornia Court of Appeal
DecidedNovember 6, 2015
DocketG050394
StatusUnpublished

This text of Garden Grove Galleria v. Cathay Bank CA4/3 (Garden Grove Galleria v. Cathay Bank CA4/3) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garden Grove Galleria v. Cathay Bank CA4/3, (Cal. Ct. App. 2015).

Opinion

Filed 11/6/15 Garden Grove Galleria v. Cathay Bank CA4/3

NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FOURTH APPELLATE DISTRICT

DIVISION THREE

GARDEN GROVE GALLERIA, LLC,

Plaintiff, Cross-defendant and G050394 (Consol. with G051021) Appellant, (Super. Ct. No. 30-2010-00342212) v. OPINION CATHAY BANK,

Defendant, Cross-complainant and Appellant;

THEODORE C. YOON et al.,

Cross-defendants and Respondents.

Appeals from a judgment and a postjudgment order of the Superior Court of Orange County, Ronald L. Bauer, Judge. Judgment and postjudgment order affirmed. Miller Barondess, Louis R. Miller, Daniel S. Miller and Mira Hashmall; Frandzel Robins Bloom & Csato, Thomas M. Robins and Steven N. Bloom for Defendant, Cross-complainant and Appellant Cathay Bank. Lowe & Baik, Jeffre T. Lowe and John A.S. Baik for Plaintiff, Cross- defendant, and Appellant Garden Grove Galleria, LLC, and Cross-defendants and Respondents Theodore C. Yoon, Julie Yoon, Charles H. Kim and Mok Kim.

* * *

This case involves two appeals consolidated for decision. In case No. G050394 Cathay Bank (Cathay) appeals from a judgment in favor of Garden Grove Galleria, LLC (GGG) on the latter’s complaint for breach of contract and in favor of GGG, Theodore C. Yoon, Julie Yoon, Charles H. Kim, and Mok Kim on Cathay’s cross- complaint for breach of personal guaranties and judicial foreclosure. In case No. G051021, GGG appeals from a postjudgment order denying its motion for attorney fees and granting Cathay’s request to strike costs. We find the contentions asserted by each appellant lack merit and affirm both the judgment and the postjudgment order.

CASE No. G050394

1. Facts and Procedural Background The Yoons and the Kims created GGG to build a multi-story mixed use development on vacant land owned by a third party. In 2003, Theodore C. Yoon and Charles H. Kim acquired possession of the land under a long-term lease. Over the next several years, they obtained plans for the development, hired a contractor, and acquired the city permits necessary to proceed with the proposed development. In late 2007, GGG and Cathay entered into a $42.5 million construction loan agreement (CLA) to build the proposed development. To obtain the loan, GGG made a required “Minimum Equity” deposit of $10,625,000 that consisted of $7,164,330 in prior development expenditures plus an additional payment of $3,460,670. GGG also

2 signed a promissory note secured by a deed of trust recorded on its leasehold interest in the parcel. Theodore C. Yoon, Julie Yoon, Charles H. Kim, and Mok Kim signed personal guaranties for the CLA. Due to delays in obtaining approval from participating lenders, East West Bank and Wing Lung Bank, the loan was not funded until December 2007. GGG presented evidence that both parties understood construction of the development would take two years. But the CLA specified the construction’s completion date as December 12, 2008, and a loan maturity of May 1, 2009, with the option of three 90-day extensions. Section 3.13 of the CLA listed several conditions that had to be met to trigger Cathay’s obligation to disburse construction funds. These conditions included requirements that GGG submit and document written applications for payment through Chuck Hasz Enterprises, Inc. (Hasz), Cathay’s fund control manager. In part, section 3.13.24 stated: “Lender or Fund Control may, at any time and from time to time, cause an inspection to be made of the progress of the construction. If any such inspection shows that the construction has reached a stage consistent with the work and materials represented in the Application for Payment to have been incorporated into the work of improvement, and upon the occurrence of all other conditions set forth in this Section 3.13, Lender will make Disbursements in accordance with this Agreement.” In addition, section 3.13.18 declared “the total amount of the Project Funds on hand shall be sufficient, in the sole opinion and judgment of Lender, to complete the Improvements.” It also required GGG (1) to “immediately pay any and all cost overruns in excess of the Contingency Reserve,” plus (2) on written notice, “Deposit . . . an amount equal to [any] deficiency” if Cathay determines “the total of Project Funds shall be insufficient . . . to complete the Project, or be less than the Project Costs . . . .” According to plaintiffs’ testimony the development’s construction proceeded smoothly for the first several months. In December 2008, Cathay informed GGG that East West Bank, one of the participating lenders, had begun “aggressively

3 managing its [real estate] loans . . . to reduce its exposure.” The same month payment of disbursement request No. 15 was delayed until January 2009. Cathay claimed East West Bank caused the delay because it erroneously believed GGG had not paid real property taxes. Due to the delay in payment, work on the project ceased. GGG presented evidence of further delays in the payment of subsequent disbursement requests, which caused further work stoppages. Cathay denied there were disbursement delays and any lag in payment resulted from GGG’s and its general contractor’s failure to properly document their funding requests. In March 2009, Cathay demanded GGG make an additional $1 million deposit, declaring it would not continue funding the project without more funds. The demand resulted from Cathay’s insistence on maintaining a relative balance between the estimated costs Hasz had budgeted for each category of labor, service, or construction materials needed to complete the development and the sums actually disbursed for these line items. Cathay also claimed the percentage of disbursements from the CLA’s contingency reserve needed to match the project’s estimated completion status. To satisfy Cathay’s demand, GGG provided it with a $1 million stand-by letter of credit. In early April 2009, the parties began discussing the necessity of extending the CLA. On the morning of May 29, 2009, Cathay sent GGG an e-mail with two attached documents: (1) a 3-page amendment to the CLA declaring the project’s completion date was December 1, 2009; and (2) a 9-page loan extension agreement that specified the loan maturity date would be February 1, 2010. The e-mail also demanded GGG pay renewal fees of $202,100. Both of the documents were dated April 27, 2009. The e-mail insisted GGG’s principals and guarantors sign the documents and return them to Cathay by 1:00 p.m. the same day. Theodore C. Yoon spoke to a Cathay vice- president by telephone asking for additional time to review the documents. But he was told that without the signed documents, “this deal is gone.” GGG’s principals and guarantors signed the documents and sent them to Cathay.

4 The loan extension agreement contained a clause whereby GGG and its guarantors relieved Cathay “from any and all claims . . . which Borrower and Guarantor . . . now own or hold . . . by reason of any acts, facts, transactions or any circumstances whatsoever occurring or existing through the date of this Extension, including . . . those based upon, arising out of, appertaining to, or in connection with . . . the Loan, the Loan Documents, [or] the facts pertaining to this Extension.” In late May, GGG also submitted disbursement request No. 20.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ellis v. Toshiba America Information Systems., Inc.
218 Cal. App. 4th 853 (California Court of Appeal, 2013)
Waller v. Truck Insurance Exchange, Inc.
900 P.2d 619 (California Supreme Court, 1995)
Foreman & Clark Corp. v. Fallon
479 P.2d 362 (California Supreme Court, 1971)
Serrano v. Unruh
652 P.2d 985 (California Supreme Court, 1982)
PLCM Group, Inc. v. Drexler
997 P.2d 511 (California Supreme Court, 2000)
Soule v. General Motors Corp.
882 P.2d 298 (California Supreme Court, 1994)
Gordon v. Aztec Brewing Co.
203 P.2d 522 (California Supreme Court, 1949)
Cucamonga County Water District v. Southwest Water Co.
22 Cal. App. 3d 245 (California Court of Appeal, 1971)
Johnson v. Cayman Development Co.
108 Cal. App. 3d 977 (California Court of Appeal, 1980)
Parlour Enterprises, Inc. v. Kirin Group, Inc.
61 Cal. Rptr. 3d 243 (California Court of Appeal, 2007)
Myers v. Trendwest Resorts, Inc.
178 Cal. App. 4th 735 (California Court of Appeal, 2009)
Thrifty Payless, Inc. v. MARINERS MILE GATEWAY, LLC.
185 Cal. App. 4th 1050 (California Court of Appeal, 2010)
Christian Research Institute v. Alnor
165 Cal. App. 4th 1315 (California Court of Appeal, 2008)
Hoopes v. Dolan
168 Cal. App. 4th 146 (California Court of Appeal, 2008)
In Re Marriage of Arceneaux
800 P.2d 1227 (California Supreme Court, 1990)
Buxbom v. Smith
145 P.2d 305 (California Supreme Court, 1944)
Ketchum v. Moses
17 P.3d 735 (California Supreme Court, 2001)
Chavez v. City of Los Angeles
224 P.3d 41 (California Supreme Court, 2010)
Concepcion v. Amscan Holdings, Inc.
223 Cal. App. 4th 1309 (California Court of Appeal, 2014)
Holguin v. Dish Network LLC
229 Cal. App. 4th 1310 (California Court of Appeal, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Garden Grove Galleria v. Cathay Bank CA4/3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garden-grove-galleria-v-cathay-bank-ca43-calctapp-2015.