Garden Grove Community Church v. Pittsburgh-Des Moines Steel Co.

140 Cal. App. 3d 251, 191 Cal. Rptr. 15, 1983 Cal. App. LEXIS 1429
CourtCalifornia Court of Appeal
DecidedFebruary 24, 1983
DocketCiv. 26228
StatusPublished
Cited by11 cases

This text of 140 Cal. App. 3d 251 (Garden Grove Community Church v. Pittsburgh-Des Moines Steel Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garden Grove Community Church v. Pittsburgh-Des Moines Steel Co., 140 Cal. App. 3d 251, 191 Cal. Rptr. 15, 1983 Cal. App. LEXIS 1429 (Cal. Ct. App. 1983).

Opinion

Opinion

WORK, J.

Pittsburgh-Des Moines Steel Company (PDM) appeals a judgment staying its pending arbitration with Garden Grove Community Church of the Reformed Church in America (Church) and denying Church’s request the PDM arbitration be judicially consolidated with its arbitrable indemnification claims against third parties which arise from the facts underlying its dispute with PDM. For the following reasons, we hold it was error to refuse to consolidate separate arbitrations between the Church and each of several parties with whom it separately contracted for work on a common project where the disputes must necessarily be resolved upon common factual determinations. In reaching this conclusion, we determine language within the various Church contracts purporting to limit the consolidation of individual arbitrations does not preclude court-ordered coordination of these separate arbitrations within a single fact finding hearing.

Factual and Procedural Background

For purposes of this opinion, we rely solely on facts developed and supported by the trial record. Where the record contains evidence to support the trial court’s findings, we accept them as true. (Denham v. Superior Court (1970) 2 Cal.3d 557, 564 [86 Cal.Rptr. 65, 468 P.2d 163]; see 6 Witkin, Cal. Procedure (2d ed. 1971) Appeal, § 235, pp. 4225-4226.)

The Church decided to build a structure now known as the “Crystal Cathedral” and hired C. L. Peck as project construction manager. The Church *257 separately contracted with Johnson/Burgee to serve as project architect. Johnson/Burgee in turn hired Severud-Perrone-Szegezdy-Sturm (Severud) as structural engineer. In yet another separate agreement, the Church contracted directly with PDM to do substantial construction work on the edifice. The Church now had separate, direct contractual relationships with Peck, Johnson/ Burgee and PDM, but no direct relationship with Severud.

The Church’s contract with PDM included the following provisions regarding arbitration: “Notwithstanding the fact that a dispute, controversy or question shall have arisen in the interpretation of any provision of this Contract, the performance of any work, the delivery of any material, the payment of any moneys to Contractor, or otherwise, the Contractor agrees that it will not directly or indirectly stop or delay the Trade Contract Work, or any part thereof, or stop or delay the delivery of any materials on its part required to be furnished hereunder, pending the determination of such dispute or controversy, regardless of whether such dispute, controversy or question is or may be subject to arbitration.

“All claims, disputes and other matters in question arising out of, or relating to, this Contract or the breach thereof shall be settled by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining, provided that any award must be based upon the terms herein and the rules of law applicable to the facts of such dispute^] . . . [pjrovided, however, that Owner shall not be obligated to arbitrate any such claim, dispute, or other matter, if Owner, in order to fully protect its interests, desires in good faith to bring in or make a party to any such claim, dispute, or other matter, the Construction Manager, the Architect, or any other third party who has not agreed to participate in and be bound by the same arbitration proceeding. ” (Italics added.) 1 We refer to the clause, italicized above, as the “escape clause.”

The contracts between the Church and Peck and between the Church and Johnson/Burgee also contained arbitration clauses. The Johnson/Burgee con *258 tract included the following limitation: “No arbitration, arising out of, or relating to this Agreement, shall include, by consolidation, joinder or in any other manner, any additional party not a party to this Agreement except by written consent containing a specific reference to this Agreement and signed by all the parties hereto.”

A number of disputes arose between the Church and PDM in which PDM claimed a right to payment for cost overruns, as well as a.balance due under the original contract. Peck, the Church’s sole agent for the purpose of enforcing its agreement with PDM, at various times during the course of the construction assured PDM its claims would be carefully reviewed in good faith and, if necessary, they would be arbitrated according to the contract. On April 2, 1980, Peck wrote PDM: “It is my opinion that arbitration is the only way to settle our differences.” In another letter dated April 17, 1980, Peck wrote to PDM: “This matter is so complex that the only useful procedure for its settlement would be arbitration which is a remedy prescribed by contract.”

When PDM’s claims were rejected, it instituted arbitration proceedings against the Church pursuant to their contract. The arbiter rejected the Church’s objection its “escape clause” precluded arbitration because it desired to resolve its potential claim for indemnity against Johnson/Burgee, Peck and Severud at the same time.

The bulk of PDM’s claim (approximately $3.5 million) involves purported conduct of Peck, Johnson/Burgee, and/or Severud allegedly causing cost overruns to PDM, including unnecessary and expensive modifications of construction plans, delays in delivering shop drawings to PDM, and mistakes in delivering shop drawings causing expensive delays in the work for PDM. 2 Assuming PDM’s allegations are correct, the Church’s liability to PDM on these claims is derivative through the acts of its contractors, Peck and Johnson/Burgee, and possibly of Severud, a subcontractor of Johnson/Burgee.

After arbitration proceedings commenced, the Church repeatedly asked Peck, Johnson/Burgee and Severud to join as parties to the PDM arbitration so its potential rights to indemnification could be simultaneously resolved. A draft agreement for consolidated arbitration was circulated; however, when Johnson/ *259 Burgee and Severud refused to join as parties, the Church sued to stay arbitration, or alternatively for an injunction requiring Johnson/Burgee and other relevant parties to join the PDM arbitration under the provisions of Code of Civil Procedure section 1281.3. 3 The court ordered the arbitration stayed, finding the Church’s “escape clause” prevented arbitration because the Church could not include third parties it believed in good faith were necessary to protect its interests. The trial court’s findings of fact and conclusions of law do not deal directly with arguments that, under federal or state law, the trial court should order the Church-Peck and the Church-Johnson/Burgee indemnification disputes consolidated. However, the court found no contractual relationship existed between the Church and Severud, and concluded: “Johnson/Burgee and Severud have no obligation to participate in or be bound by the PDM arbitration and, absent their consent, may not be compelled to participate in or be bound by the PDM arbitration.”

The Church Is Not Obligated to Arbitrate With PDM Absent Consolidation of the Church-Johnson/Burgee Arbitration

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kaufman v. Adani CA1/3
California Court of Appeal, 2024
Ehrman v. Post CA2/2
California Court of Appeal, 2022
John Murphy v. Directv, Inc.
724 F.3d 1218 (Ninth Circuit, 2013)
Bob Lewis Volkswagen v. Universal Underwriters Group
571 F. Supp. 2d 1148 (N.D. California, 2008)
Parker v. McCaw
24 Cal. Rptr. 3d 55 (California Court of Appeal, 2005)
Zakarian v. Bekov
119 Cal. Rptr. 2d 623 (California Court of Appeal, 2002)
Blue Cross of California v. Superior Court
78 Cal. Rptr. 2d 779 (California Court of Appeal, 1998)
Gordon v. G.R.O.U.P., Inc.
49 Cal. App. 4th 998 (California Court of Appeal, 1996)
Slaught v. Bencomo Roofing Co.
25 Cal. App. 4th 744 (California Court of Appeal, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
140 Cal. App. 3d 251, 191 Cal. Rptr. 15, 1983 Cal. App. LEXIS 1429, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garden-grove-community-church-v-pittsburgh-des-moines-steel-co-calctapp-1983.