Atlas Plastering, Inc. v. Superior Court

72 Cal. App. 3d 63, 140 Cal. Rptr. 59, 1977 Cal. App. LEXIS 1690
CourtCalifornia Court of Appeal
DecidedJuly 28, 1977
DocketDocket Nos. 41001, 41025
StatusPublished
Cited by42 cases

This text of 72 Cal. App. 3d 63 (Atlas Plastering, Inc. v. Superior Court) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlas Plastering, Inc. v. Superior Court, 72 Cal. App. 3d 63, 140 Cal. Rptr. 59, 1977 Cal. App. LEXIS 1690 (Cal. Ct. App. 1977).

Opinion

Opinion

SCOTT, J.

Jasper Construction, Inc., general contractor and real party in interest, contracted with the County of Alameda for construction of a courthouse and government center in Hayward.

Petitioners here and respondents below are Atlas Plastering, Inc., University Mechanical & Engineering Contractors, Inc., Feiler Bros. Corp., and Rosendin Electric, Inc. as subcontractors, and Insurance Company of North America (INA) as surety on behalf of Atlas. Atlas had INA execute a performance bond with Jasper as obligee. That bond incorporated the Jasper/Atlas subcontract by reference.

The issue presented here is whether subcontractors not in contractual privity with each other, but whose contracts with the general contractor contain identical procedures for individual arbitration of disputes relating to construction delay, can be compelled to participate in a consolidated arbitration proceeding resulting in a change in the agreed upon method of selecting arbitrators. We conclude that such consolidat *67 ed arbitration cannot be compelled, and therefore the order of the superior court must be reversed.

All parties agree that disputes including but not limited to project completion delays arose, and that construction has not been completed or accepted by the owner.

Jasper made a demand upon petitioners to hold consolidated arbitration, asserting that a dispute had arisen as to damages claimed by reason of construction delays in which each petitioner was involved, making all parties indispensable. Joint arbitration was refused by petitioners. Jasper’s suit to compel consolidated arbitration followed. Jasper contends that the subcontractors’ respective work was “interrelated and interdependent” so that apportionment of delay damages was extremely difficult; that each subcontractor blames some or all the other subcontractors; that there were consequently common questions of law and fact, and that consolidation “is necessary in order to promote justice between the parties, to avoid duplication of testimony and proceedings, and to provide a single forum for the resolution of the interrelated disputes.”

The subcontractors contend in part that consolidated arbitration may not be ordered in the absence of a multiparty contractual arbitration agreement, and that consolidation would change the size and method of selection of the arbitration panel.

The court below ordered consolidated arbitration and a manner of selection of arbitrators at variance with the agreement of the parties.

I. Propriety of review by mandate or prohibition of the lower court’s order

An order directing parties to arbitrate is nonappealable. (Maddy v. Castle (1976) 58 Cal.App.3d 716, 719 [130 Cal.Rptr. 160].) The order is reviewable on appeal from a judgment confirming the award. (Code Civ. Proc., §§ 1294, 1294.2; Lesser Towers, Inc. v. Roscoe-Ajax Constr. Co. (1969) 271 Cal.App.2d 675, 692 [77 Cal.Rptr. 100].) The preferred procedure is to proceed by arbitration and attack confirmation on appeal. (Maddy v. Castle, supra, at p. 719; Code Civ. Proc., § 1294, subd. (d); see also Titan Enterprises, Inc. v. Armo Construction, Inc. (1973) 32 Cal.App.3d 828, 831 [108 Cal.Rptr. 456]; Spence v. Omnibus Industries (1975) 44 Cal.App.3d 970, 976 [119 Cal.Rptr. 171].)

*68 Mandate or prohibition, however, is available to review such orders if the matters ordered arbitrated fall clearly outside the scope of the arbitration agreement, or if the arbitration would appear to be unduly time consuming or expensive. (Lesser Towers, Inc. v. Roscoe-Ajax Constr. Co., supra, at pp. 692-693; Bertero v. Superior Court (1963) 216 Cal.App.2d 213, 222 [30 Cal.Rptr. 719]; Unimart v. Superior Court (1969) 1 Cal.App.3d 1039, 1041 [82 Cal.Rptr. 249].) In the instant case, if the court’s order was in excess of its jurisdiction, the expense to the parties in participating in and seeking review of the arbitration is apparent. This court determined the issue as to adequacy of relief by another remedy when it granted the alternative writ. (City of Los Angeles v. Superior Court (1959) 51 Cal.2d 423, 429 [333 P.2d 745]; Rosemont v. Superior Court (1964) 60 Cal.2d 709, 712 [36 Cal.Rptr. 439, 388 P.2d 671]; 5 Witkin, Cal. Procedure (2d ed. 1971) § 44, pp. 3817-3819.)

II. Effect of failure to file timely responses to petition for arbitration

Jasper contends that all of the allegations contained in its petition to compel consolidated arbitration must be deemed admitted because petitioners failed to respond, submitted untimely briefs, and said briefs did not conform to the pleading statutes.

The responses by Atlas, Rosendin and INA were both served and filed beyond the 10-day period required by Code of Civil Procedure section 1290.6, and no extensions of time were granted or stipulations entered. However, there is no indication that the respondent court here did not treat the responses as timely. Jasper could have submitted a transcript of the hearing to contradict such assumption, but did not. (Travelers Indemnity Co. v. Bell (1963) 213 Cal.App.2d 541, 544-545 [29 Cal.Rptr. 67].) Even if the court deemed the allegations of the petition admitted by the failure of the subcontractors to file timely responses, no prejudice appears to Jasper in that the issue of applicability of sister state precedent regarding consolidated arbitration is purely a question of law raised in the court below by Jasper and is the sole issue on appeal. (See Travelers Indemnity Co. v. Bell, supra, at p. 545.)

III. Power of the court to vaiy the method of selecting arbitrators

Petitioners do not at this stage allege the instant dispute was not within the arbitration clauses. Here, the issue is simply whether a California court may change the agreed method of selecting arbitrators and compel consolidation of what might otherwise be a costly, duplicative and time *69 consuming series of arbitrations which might well lead to disparate results.

Each subcontract contains the following clause: “K. Arbitration—If at any time any controversy should arise between the Contractor and the Subcontractor regarding anything pertaining to this Agreement and which the parties hereto do not promptly adjust and determine, then the written orders of the Contractor to the Subcontractor shall be followed. The controversy existing between the parties shall be submitted to and determined by arbitration. Each of the parties hereto shall select an arbitrator and the arbitrator so selected by them shall select a third person to serve as arbitrator with them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Novoa v. Superior Court CA2/5
California Court of Appeal, 2024
Herzog v. Super. Ct.
California Court of Appeal, 2024
Saenz v. Superior Court CA4/2
California Court of Appeal, 2023
Ocean Cities Pizza v. Superior Court CA1/4
California Court of Appeal, 2022
Neil Wallace v. Mt. Poso Cogeneration Company, LLC
Court of Chancery of Delaware, 2021
Felisilda v. FCA US LLC
California Court of Appeal, 2020
Khorsand v. Liberty Mutual Fire Ins. Co.
California Court of Appeal, 2018
Khorsand v. Liberty Mut. Fire Ins. Co.
230 Cal. Rptr. 3d 89 (California Court of Appeals, 5th District, 2018)
Ruiz v. Moss Bros. Auto Group
232 Cal. App. 4th 836 (California Court of Appeal, 2014)
Arroyo v. Riverside Auto Holdings, Inc. CA4/2
California Court of Appeal, 2013
Frog Creek Partners, LLC v. Vance Brown, Inc.
206 Cal. App. 4th 515 (California Court of Appeal, 2012)
Medeiros v. Superior Court
53 Cal. Rptr. 3d 307 (California Court of Appeal, 2007)
ZEMBSCH v. Superior Court
53 Cal. Rptr. 3d 69 (California Court of Appeal, 2007)
Patchett v. Bergamont Station, LTD.
49 Cal. Rptr. 3d 941 (California Court of Appeal, 2006)
Independent Ass'n of Mailbox Center Owners, Inc. v. Superior Court
34 Cal. Rptr. 3d 659 (California Court of Appeal, 2005)
Titan/Value Equities Grp., Inc. v. Superior Court of San Diego Cty.
29 Cal. App. 4th 482 (California Court of Appeal, 1994)
Brock v. Kaiser Foundation Hospitals
10 Cal. App. 4th 1790 (California Court of Appeal, 1992)
American Home Assurance Co. v. Benowitz
234 Cal. App. 3d 192 (California Court of Appeal, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
72 Cal. App. 3d 63, 140 Cal. Rptr. 59, 1977 Cal. App. LEXIS 1690, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlas-plastering-inc-v-superior-court-calctapp-1977.