Garden City Wire Spring Co. v. Boecher

94 Ill. App. 96, 1899 Ill. App. LEXIS 827
CourtAppellate Court of Illinois
DecidedDecember 4, 1900
StatusPublished

This text of 94 Ill. App. 96 (Garden City Wire Spring Co. v. Boecher) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garden City Wire Spring Co. v. Boecher, 94 Ill. App. 96, 1899 Ill. App. LEXIS 827 (Ill. Ct. App. 1900).

Opinion

JN£e. Justice Hoeton

delivered the opinion of the court.

This is an appeal from a judgment for §6,708.33, entered in the Circuit Court of Cook County in favor of appellee and against appellant in an action for personal injury.

The original declaration consisted of three counts. Afterward and by leave of court three additional counts were filed. Briefly stated, the charges of negligence in the declaration are (as stated in his brief by counsel for appellee):

1st. Ordering appellee to do work. which was outside the line of his employment.

2d. Failing to provide a sufficient number of men to safely do the work in the performance of which appellee was injured.

3d. Providing an unsafe and insecure scaffold used in the performance of said work.

Appellee was in the employ of appellant in the capacity of a blacksmith. Upon the occasion in question he was directed by the foreman in the employ of appellant to assist in raising an iron shaft weighing 400 pounds from the floor into “ hangers” projecting down from the ceiling. A scaffold or platform about eighteen feet long and three and a half or four feet high was put in place for the men to stand upon in raising the shaft and putting it in the hangers. Several men were called to assist in thus putting the shaft in place. All the employes except the foreman and the appellee were dismissed by the foreman after the shaft was safely in the hangers. The shaft was then resting in three hangers, one near the middle and one near to each end. The foreman told appellee to go to one end of the shaft and lift it up two inches so that he, the foreman, could adjust the box or bearing in one of the other hangers. (The middle hanger, as we understand from the testimony.) That would require that appellee, standing upon the scaffold with his shoulder under the shaft, should thus lift about 200 pounds. The hangers were fastened to the ceiling and at the lower end of each was what may be called a hook. Above the hook was a horizontal part of the hanger, the space between the hook and such horizontal part of the hanger being more than the diameter of the shaft. To remove the shaft so that it would not receive the support of the hanger, it must be lifted up and out at1 the open side. The shaft must have been so lifted out by appellee or it could not have fallen.

The platform or scaffold was constructed by putting wooden “ horses ” on the floor and placing on them planks upon which the men stood. It is claimed that this scaffold was so negligently constructed that it was unsteady and shook under the feet of appellee when he had lifted the end of the shaft, thus causing him to lift or throw it out at the open side of the hanger and away from its bearings, and that that was the proximate cause of the injury to appellee.

First. Was there any negligence in “ ordering appellee to do work which was outside the line of his employment? ”

The place where appellee was working as a blacksmith, was on the same floor and forty or fifty feet from the place where he 'was injured. Appellee testified that he knew that what the foreman requested him to do was not blacksmith work; that he made no objection to doing it and that he had been doing other work which was not blacksmith work. Also that “ when the foreman said, come on, blacksmith, and took me to where the scaffold stood, I didn’t tell him I didn’t want to go. I went right along.” Appellee was an experienced blacksmith about fifty-six years of age.

When an employe of mature years and ordinary intelligence is directed to do a temporary work outside of the line of his employment, and proceeds to do such work without "an)r objection whatever, negligence of the employer can not be predicated upon that state of facts alone. Cole v. C. & N. W. Ry. Co.; 71 Wis. 114; Leary v. B. & A. R. R. Co., 139 Mass. 580; 2 Thomp. on Neg., p. 976, Sec. 9; Hogan v. N. P. R. R. Co., 53 Fed. Rep. 519.

We understand the same principles to be recognized and approved by our Supreme Court in Gall v. Beckstein, 173 Ill. 187, where it is said (p. 190):

“ The plaintiff’s ordinary work in the factory was making sausage casings, but when called upon to unload the salt he voluntarily, without anjr objection whatever, undertook the performance of that labor, and such labor may therefore be regarded within the scope of his employment.”

Counsel for appellee cites as in conflict with this case the following cases: Offut v. Columbian Exposition, 175 Ill. 472; Ill. Steel Co. v. Schymanowski, 162 Ill. 447, and Anderson Pressed Brick Co. v. Sobkowiak, 148 Ill. 573. It will be noticed that in point of time two of these cases are prior and one subsequent to the Gall case. One, and we apprehend a sufficient distinction between these cases and the Gall case is, that in the latter, the party injured made no objection, but went voluntarily to the performance of the service, while in each of the three cases cited the employe informed his superior of the supposed danger and went to the performance of the service by reason of peremptory orders so to do.

In the case at bar, when the foreman said to appellee, “ Come on, blacksmith,” and took him to where the scaffold stood, and appellee, as he says, made no objection whatever, but “ went right along,” and if there was any danger, there was none which was not just as apparent to the appellee as it was to the foreman, the labor in which appellee" was called to assist will be regarded as being “ within the scope of his employment.” There is nothing to support the charge that appellee was ordered “ to do work which was outside the line of his employment.” There was no negligence in this, whether considered by itself or in connection with the other facts and circumstances shown in this record for which appellant can be held to respond in damages.

Second. Was there negligence on the part of appellant in failing to provide a sufficient number of men 'to safely do the work in the performance of which appellee was injured \

The appellee was a man of experience. He was present and assisted in putting the shaft in place. He knew that the other man who were assisting had been dismissed and were not then present. The absence of other men to assist in lifting the shaft is not alone sufficient ground for a recovery. This is clearly stated in Swift & Co. v. Rutkowski, 167 Ill. 156, where the court says (p. 159):

.“ We are not aware of any well considered case, where it has been held that the servant who is in the 'exercise of" reasonable care and caution, may recover from the master upon the ground alone that the master has failed to furnish a sufficient supply of help.”

But there is no testimony to support the charge that there was not sufficient help. Appellee does not testify that he was not able to readily lift the end of the shaft as directed by the foreman. He says he did lift it, but that it fell because the scaffold shook under his feet. He does not state that he was injured because there was not sufficient help, but says it was because the scaffold shook. The foreman testified that any man of good strength could lift fl.11 that appellee had to lift and much more with the advantage he had. Also that he had the hanger to hold onto and the foreman thought he was holding onto it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leary v. Boston & Albany Railroad
2 N.E. 115 (Massachusetts Supreme Judicial Court, 1885)
Cole v. Chicago & Northwestern Railway Co.
37 N.W. 84 (Wisconsin Supreme Court, 1888)
Joliet Steel Co. v. Shields
146 Ill. 603 (Illinois Supreme Court, 1893)
Chicago Anderson Pressed Brick Co. v. Sobkowiak
36 N.E. 572 (Illinois Supreme Court, 1894)
Goldie v. Werner
38 N.E. 95 (Illinois Supreme Court, 1894)
Illinois Steel Co. v. Schymanowski
44 N.E. 876 (Illinois Supreme Court, 1896)
Swift & Co. v. Rutkowski
47 N.E. 362 (Illinois Supreme Court, 1897)
Gall v. Beckstein
50 N.E. 711 (Illinois Supreme Court, 1898)
Offutt v. World's Columbian Exposition
51 N.E. 651 (Illinois Supreme Court, 1898)
Kuhns v. Wisconsin, Iowa & Nebraska Railway Co.
31 N.W. 868 (Supreme Court of Iowa, 1887)
Baltimore Elevator Co. v. Neal
5 A. 338 (Court of Appeals of Maryland, 1886)

Cite This Page — Counsel Stack

Bluebook (online)
94 Ill. App. 96, 1899 Ill. App. LEXIS 827, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garden-city-wire-spring-co-v-boecher-illappct-1900.