Gantry Construction Co. v. American Pipe & Construction Co.

49 Cal. App. 3d 186, 122 Cal. Rptr. 834, 17 U.C.C. Rep. Serv. (West) 1218, 1975 Cal. App. LEXIS 1197
CourtCalifornia Court of Appeal
DecidedJune 18, 1975
DocketCiv. 42805
StatusPublished
Cited by19 cases

This text of 49 Cal. App. 3d 186 (Gantry Construction Co. v. American Pipe & Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gantry Construction Co. v. American Pipe & Construction Co., 49 Cal. App. 3d 186, 122 Cal. Rptr. 834, 17 U.C.C. Rep. Serv. (West) 1218, 1975 Cal. App. LEXIS 1197 (Cal. Ct. App. 1975).

Opinion

Opinion

KINGSLEY, Acting P. J.

In September 1966, appellant, American Pipe and Construction Co. (Ameron) 1 contracted to sell a substantial quantity of pipe 2 to respondent, Gantry Construction Company (Gantry), for use in constructing a project for the City of Los Angeles. The contract called for delivery of the pipe in installments, for invoicing the delivered pipe, and for payment by Gantry for delivered pipe by the 25th of each month after invoice. Pursuant to the provisions of its contract with the city, Gantiy procured a performance bond from Pacific Indemnity (Pacific).

It is clear from the whole record that Gantry was underfinanced and that it depended on progress payments from one job to meet unpaid bills on a previous job. Gantry admitted at the trial that it never intended to meet the contract terms for payment, but that it intended from the first to wait from 30 to 60 days before making a required contractual payment. Pursuant to its business policy (and economic need) Gantry for several months used the progress payments made to it by the city on the contract herein involved to meet obligations arising out of an earlier contract with the city. As a result, although billings by Ameron started at the end of November 1966, no payments were made by Gantry until March 1967, *191 when it paid $26,934.26, against a total billing as of the end of February of$139,532.65.

Testimony on behalf of Ameron was to the effect that efforts to secure and expedite payments were begun by Ameron in January 1967, continuing without success until April. 3 On April 13, Gantry paid Ameron an additional $25,661.04.

On or about April 14, 1967, an official of Ameron called an official of Pacific, telling him that Gantry was seriously in default and soliciting Pacific’s aid in expediting payments. The ‘phone call was confirmed by a letter, in which the amount of Gantry’s default was stated as being $247,634.48. On April 17, 1967, Ameron and Gantry negotiated a new payment schedule, calling for Gantry to pay Ameron about 75 percent of each progress payment received by Gantry from the city. On April 18, 1967, Ameron advised Pacific of the new arrangement.

Alerted by the calls and letter from Ameron, Pacific instituted a series of inquiries into the financial condition of Gantry. As a result of those inquiries, it (and other bonding companies) refused to bond Gantry on future jobs resulting, as Gantry claims, in its failure, with loss of future profits and the value of its established business.

On these facts, Gantry sued Ameron for slander and for interference with business relations. 4 After a trial by jury, Gantry recovered judgment in the amount of $3,500,000; Ameron has appealed; we reverse for the errors hereinafter discussed in the instructions dealing with the defense of qualified privilege. Since the case must be retried, we comment on certain deficiencies in other instructions for the assistance of counsel and the trial court on such retrial.

I

Relying on the fundamental proposition that “[tjruth of the statements made is a complete defense against civil liability for defama *192 tion, regardless of bad faith or malicious purpose” (4 Witkin, Summary of Cal. Law (8th ed. 1974) Torts, § 292, p. 2564), defendant contends that its statements to Pacific were true. In support of that contention, it argues that, although admittedly the contract between Ameron and Gantry did not contain an acceleration clause, it had a right to accelerate under subdivision (1) of section 2709 of the California Commercial Code, the pertinent portions of which read as follows: “(1) When the buyer fails to pay the price as it comes due the seller may recover, together with any incidental damages under the next section, the price [H] (a) Of goods accepted. . . .” If that contention is valid, the statement that Gantry was in default over $247,000 was true; if it is not, the amount in default on April 14, was only about $87,000.

On this issue, the trial court instructed the jury as follows: “Where the agreement between two parties does not contain any provision giving the seller the right upon the buyer’s default to declare immediately due the unpaid balance of the purchase price, the seller has no right to declare immediately due the unpaid balance. The contract between plaintiff and defendant has no provision giving the seller the right upon the purchaser’s default to declare immediately due the unpaid balance.”

(1) Unless the Commercial Code changed the California law on acceleration, the trial court’s instruction was correct. We conclude that the Commercial Code did effect a change in the precode law. The comments of the draftsmen of the Uniform Comm ercial Code, as to this provision, say: “Neither the passing of title to the goods nor the appointment of a day certain for payment is now material in a price action.” Plaintiff argues that the California comments do not contain any reference to the “day certain for payment” concept. That comment reads: “Subdivision (1) liberálizes the remedy formerly given to the seller. Under former Civil Code section 1783(1) the seller could maintain an action for the price only if title had passed to the buyer and the buyer had wrongfully refused or neglected to pay for the goods. Under subdivision (1) the passage of title is immaterial to a seller’s right to bring an action for the price.” (Italics in original.)

We agree that acceptance of goods without payment does, under the Commercial Code, allow the seller to sue at once not only for past due payments but for the price of all goods then delivered and accepted. (Cal. U. Com. Code, § 2106, subd. (1).) The comment was before the Legislature when the Code was adopted; it adopted, without change, the unambiguous language of the uniform code, i.e.: that mere" acceptance *193 controls the amount of recovery in a suit for the price. We follow the plain meaning of the statute.

While we conclude that the instruction as given was erroneous, we do not agree with appellant that it was entitled to an instruction that, as a matter of law, the defense of truth had been proven. Ameron had not told Gantry that it regarded the entire $247,634 as accelerated and then due. It was for the jury to decide whether the unexpressed intent, to which Ameron’s witness testified, actually existed or whether the figure used in the Ameron communication was based on some theory other than that of the Commercial Code section. At a retrial, an instruction on truth as a defense should be given which leaves that factual issue to the jury.

(2) Alternatively, Ameron contends that, under the first sentence of subdivision (3) of section 2612 of the California Commercial Code, it was entitled to treat the entire contract as breached and sue for damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Appel v. Wolf
S.D. California, 2021
Howard Appel -v- Robert S Wolf
S.D. California, 2021
Schelske v. TMZ Productions CA2/2
California Court of Appeal, 2016
Tolsa v. Pacific Aqua Farms CA2/8
California Court of Appeal, 2016
Ringler Associates Inc. v. Maryland Casualty Co.
96 Cal. Rptr. 2d 136 (California Court of Appeal, 2000)
Smith v. Maldonado
85 Cal. Rptr. 2d 397 (California Court of Appeal, 1999)
Lundquist v. Reusser
875 P.2d 1279 (California Supreme Court, 1994)
Goehring v. Wright
858 F. Supp. 989 (N.D. California, 1994)
Seaman's Direct Buying Service, Inc. v. Standard Oil Co.
686 P.2d 1158 (California Supreme Court, 1984)
Institute of Athletic Motivation v. University of Illinois
114 Cal. App. 3d 1 (California Court of Appeal, 1980)
Lull v. Wick Construction Co.
614 P.2d 321 (Alaska Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
49 Cal. App. 3d 186, 122 Cal. Rptr. 834, 17 U.C.C. Rep. Serv. (West) 1218, 1975 Cal. App. LEXIS 1197, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gantry-construction-co-v-american-pipe-construction-co-calctapp-1975.