Gallun v. Seymour

45 N.W. 115, 76 Wis. 251, 1890 Wisc. LEXIS 107
Wisconsin Supreme Court·Decided March 18, 1890·Published·Cited by 3 cases

Opinion

TayloR, J.

It will be seen from the facts stated that the learned circuit judge, in getting at the plaintiffs’ damages, applied the 162-f cords delivered in September, and after the time for the delivery of the last instalment of the barb, upon the deficiency of the delivery in June under the contract. The learned counsel for the defendant contends that the 162$ cords delivered in September should have been applied, first, to extinguish the deficiency of bark delivered in August, and the balance to the deficiency delivered in July. The learned counsel for the plaintiffs contend that all the bark delivered should be applied, first, to make up the 300 cords agreed to be delivered in June, and the 350 cords agreed to be delivered in July, so that the whole deficiency would be in the August delivery, and consequently the damages should be estimated as upon the failure to deliver the 350 cords in August. Under the theory of the application of the 162-f cords of bark as claimed by the [255] defendant, and upon the theory, which seems to have been acquiesced in by all the parties and the court, that the plaintiffs were entitled to recover as damages the difference in value of the bark as fixed by the contract and the actual value on the last day of the month in which the deficit occurred, the damages would have been very much less than found by the court. The shortage in July was 118$ cords; in August, 81$ cords. Under defendant’s theory, the 1621-cords delivered in September would have covered all the shortage in July and August, except 37$ cords, and left a shortage of 225 6-8 cords in June; and the damages would have been reduced to 50 cents per cord oft the 225 6-8 cords, and to $1.50 per cord on the 37$ cords, short in July, — in all, the sum of $168.93.

Upon the theory of the plaintiffs’ counsel, by applying all the bark delivered, first to make up the 300 cords to be delivered in June, then to make up the 350 cords in July, and the balance to make up the deficienc}7, as far as it would, in August, there would be a deficiency in August of 263$ cords; and the damages on that deficiency, according to the rule adopted by the parties and the court, would be $1.50 per cord, or $394.68, instead of $331.30, as allowed by the court. The learned counsel for the plaintiffs contend that, in the first place, the contract was an entire contract, and there could be no breach until the 31st of August, 1887. If that contention be correct, then the rule of damages claimed by them would be as they contend. We cannot, however, agree with the learned counsel in this construction of the contract. It seems to us very clear that it was a material part of the contract that 300 cords should be delivered in June, 350 in July, and 350 in August, and that, upon a failure to deliver the 300 cords in June, the contract was broken, and plaintiffs could have maintained an action for any damages they had sustained by a failure to make such delivery; and it is the same as to the failure to deliver in [256] July and August. There wore three breaches of the contract shown on the trial. It is a stronger case than the cases of Hill v. Chipman, 59 Wis. 211; Missouri Furnace Co. v. Cochran, 8 Fed. Rep. 463. It is to us a clear case of an agreement to deliver 1,000 cords of bark in three instal-ments,— one to be delivered in June, another in July, and another in August; and a failure to deliver any part of either instalment within the time mentioned for its delivery is a breach of the contract, as much so as if the agreement had been to pay $1,000,— $300 in June, $350 in July, and $350 in August.

The counsel for plaintiffs further contend that, admitting that the failure to deliver any instalment within the time specified would be a breach of the contract, still the bark received in July should be applied to make up the deficiency in June, and the amount received in August should be applied to make up the deficiency in July. We do not think the plaintiffs, in the absence of any agreement to that effect, would have the right to make such application of the bark delivered in the months of July and August. When the month of July commenced, the plaintiffs had a cause of action against the defendant for the breach of the contract to deliver in June, and when the defendant delivered the bark in July the presumption is that he delivered it on his contract to deliver 350 cords in that month, and not that he delivered it to make up any deficiency in June. The rights of the parties as to the June delivery were fixed on the expiration of the month, and the plaintiffs were not bound to receive any more bark to apply on that part of the contract, nor was the .defendant bound to deliver anjr more thereon. We think the just rule is to apply what was delivered in each month upon the contract for that month, in the absence of any agreement to apply it differently. Excluding these views of the construction of the contract and the application of the deliveries of the bark, the judgment is sufficiently favorable to the plaintiffs.

Free access — add to your briefcase to read the full text and ask questions with AI

Gallun v. Seymour, 45 N.W. 115, 76 Wis. 251, 1890 Wisc. LEXIS 107 (Wis. 1890).

45 N.W. 115 (Gallun v. Seymour) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Corn Planter Refining Co. v. George R. Jenkins & Co.
217 Ill. App. 139 (Appellate Court of Illinois, 1920)
Laycock v. Parker
79 N.W. 327 (Wisconsin Supreme Court, 1899)
Northern National Bank v. Lewis
47 N.W. 834 (Wisconsin Supreme Court, 1891)