Gallivan Building Co. v. Kress Co.

113 S.E. 342, 120 S.C. 502
CourtSupreme Court of South Carolina
DecidedJuly 6, 1920
Docket10940
StatusPublished
Cited by1 cases

This text of 113 S.E. 342 (Gallivan Building Co. v. Kress Co.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gallivan Building Co. v. Kress Co., 113 S.E. 342, 120 S.C. 502 (S.C. 1920).

Opinions

The opinion of the Court was delivered by

Mr. Justice Cothran.

Action for $3,168.20 balance alleged to be due upon a contract for the remodeling of a certain storeroom in the city of Greenville.

*506 The case turns upon the construction of the contract entered into between the parties on September 4, 1920. In the contract the plaintiff is referred to as the contractor and the defendant as the owner, designations which will be followed herein.

The owner, desiring to remodel his building to a considerable extent, engaged an architect to draw up plans and specifications. He also had the form of a contract prepared, embodying with amplifications the oral agreement which had concluded the preliminary negotiations between the owner and the plaintiff. This form of contract as submitted to the contractor for execution contained in typewriting the following clause:

“It is agreed that the contractor has estimated the total cost to it of furnishing the material, labor, etc., mentioned in this contract at the sum of $20,000 and that the contractor is entitled to a profit of $1,200 upon this contract on the basis of that computation, making a total sum of $21,200.”

As a matter of fact these were the figures of the architect. When the contract was thus presented to the contractor the president, J. F. Gallivan, insisted upon the insertion of the word “about” immediately succeeding the figures $20,000, and the word “approximately” immediately succeeding the figures $21,200, and the contract with these words inserted -in handwriting was duly executed.

The work was then undertaken and completed by the contractor in strict conformity with the plans and specifications, and accepted by the owner without complaint. During the progress of the work the owner paid to the contractor upon bills submitted for material, labor, etc., including the $1,200 compensation, $22,983.96, $1,783.96 in excess of the estimated cost of the work; and at the com *507 pletion the contractor presented similar bills amounting to $3,168.20, claiming that the work had cost $24,952.16, exclusive of the $1,200.00 compensation, and making no charge for commissions on the amount of the cost in excess of the estimate, $4,952.16.

The defendant, owner, contended that the contractor had undertaken to do the entire work as called for by the plans and specifications for $21,200.00, including its compensation; that the owner had paid the contractor $22,983.96, $1,783.96 in excess of what it calls the “contract price”; that it owed the contractor nothing; and set up a counterclaim for the alleged overpayment.

The case was tried by Judge Memminger without a jury upon testimony taken in open Court. He filed a “decision and order for judgment,’’ dated October 24, 1921, in which he takes the defendant’s view that the contractor had agreed, to do the work at a “stipulated price” of “about” $20,000.00, plus the contractor’s fee of $1,200.00, total “approximately” $21,200.00. He accordingly held that $2,000.00 additional would reasonably be within the terms “about” and “approximately,” and that the contractor would be “entitled” to $23,200.00, plus $120.00 additional fee, total $23,320.00, upon which he had been paid $22,983.96, leaving a balance due the contractor of $337.04 ($336.04?), for which amount he ordered judgment.

From this decree and order for judgment both parties have appealed; the contractor contending that it was entitled to $3,168.20, with interest on $113.86 from February 15, 1921, on $2,510.52 from March 22, 1921, and on $543.82 from May 18, 1921, at 7 per cent.; and the owner contending that it was error to allow so great a sum as $2,000.00 additional in variation of the estimate, and in allowing $120.00 additional fee to the contractor. The defendant did not except to the disallowance of the counterclaim of $1,783.96.

*508 The contention of the defendant and the Circuit decree are based upon an erroneous construction of the contract entered into between the parties; that is that the contract contained an undertaking on the part of the contractor to do the work for an approximate compensation of $21,200.00; in other words, that by his estimate, if it was his estimate, of the approximate cost of the work, he guaranteed that it would not cost more than that amount, which is exactly the undertaking the contractor would have assumed if he had agreed to do the work for a certain sum of money.

By an examination of the contract, which will be reported, it will be found that the following provisions, utterly inconsistent with the idea that the contractor undertook to do the work for a fixed or an approximate compensation, occur:

(1) The contractor should in purchasing the material and supplying the labor assume the duty of “holding the cost down as low as possible.” What interest would this have been to the owner, if the contractor had assumed the obligation of completing the work within the estimate?

(2) The contractor should keep full and complete records of the cost of all material, drayage, labor, and other expenses incurred by it in connection with the carrying on of this work. What interest would this have been to the owner if the contractor had assumed the obligation of completing the work within the estimate?

(3) The contractor agrees to carefully check all invoices, pay rolls and bills to- the end that it may subsequently certify the same to the owner to be correct, and the contractor agrees to promptly pay all invoices, pay rolls and bills and all other expenses connected with this work, and to render to the owner about the first of each month, invoices, payrolls, and bills of all materials, drayage, labor and other expenses and accompanied by an affidavit of Mr. Gallivan *509 showing that said bills, invoices, etc., have been properly-checked and found correct and have been paid,' and also stating that all bills have been paid up to such date. Within a reasonable length of time after the receipt of the owner of such invoices, pay rolls, bills, etc., verified as above provided, the owner agrees to pay over to the contractor the sums of money paid by it on such invoices, pay rolls, and bills, plus fee agreed.’’ The same question may be asked as to this provision.

The contract shows that the owner eng'aged the contractor to pay for all of the material, supply all the labor, and complete the work “in strict conformity with the plans and specifications prepared” by the owner’s architect, “Which plans and specifications are a part of this contract, the same as if herein set forth in full”; to supervise the work; to make the cost as low as possible; to keep full records, to certify the bills, invoices, and pay rolls to the owner; who engaged to pay them as presented. There is not a word in the contract casting an obligation upon the contractor to do this work within certain limits, or to personally incur any obligation which the owner would not relieve him of, all for a stated compensation of $1,200.00; there is not a word in it suggesting a guaranty on the part of the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Koppers Co., Inc. v. Inland Steel Co.
498 N.E.2d 1247 (Indiana Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
113 S.E. 342, 120 S.C. 502, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gallivan-building-co-v-kress-co-sc-1920.