Gallagher v. St. Patrick's Church

63 N.W. 864, 45 Neb. 535, 1895 Neb. LEXIS 238
CourtNebraska Supreme Court
DecidedJune 19, 1895
DocketNo. 5907
StatusPublished
Cited by5 cases

This text of 63 N.W. 864 (Gallagher v. St. Patrick's Church) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gallagher v. St. Patrick's Church, 63 N.W. 864, 45 Neb. 535, 1895 Neb. LEXIS 238 (Neb. 1895).

Opinion

Ragan, C.

St. Patrick’s Church is a religious corporation organized under the laws of the state and situate at O’Neill, Ne[538]*538braska. Meals & Me Vea, in August, 1890, were contractors and builders, and will hereinafter be referred to as the contractors. In the said month of August said contractors entered into a written agreement with said church, in and by the terms of which they agreed to furnish all the material and erect an academy or school building for said church at said city of O’Neill, according to certain plans and specifications. The contract price for this building was $16,160.94. The contract contained the following provisions: (a) The architect was required to make estimates on the last days of August, September, October, and November, of the value of the material furnished and labor performed by the contractors towards the erection of the building, and thereupon the church was to pay to the contractors at said date three-fourths of the amount of such estimates; (6) the building was to be completed by December 31, 1890, at which time the church was to pay to the contractors the balance of the contract price; (c) that if the contractors “shall neglect and refuse to carry on the work at any time for two days in the manner required by the architect, or shall neglect or refuse to comply with any of the articles of this agreement,” then the church “is hereby empowered to enter upon and take possession of the premises, with the materials and apparatus thereon, after giving three days’ notice in writing,” and complete said building, charging the costs thereof to the contractors; (d) that if the contaactors should fail to complete the building by the time agreed they should forfeit and pay to the church the sum of $10 a day for every day that the building remained unfinished; (e) that “the owner, the church, shall protect by insurance to cover its interest when payments have been made to contractor.” To secure their performance of this contract the contractors gave a bond to the church, signed by themselves and a number of other persons, hereinafter denominated the sureties. Immediately after the execution of this contract the [539]*539contractors began the erection of the building and continued working upon the same until February 18, 1891, when the building, almost completed, was wholly destroyed by fire. Prior to December 31,1890, the church had paid to the contractors for labor and material furnished by them towards the erection of said building the sum of $12,440. Prior to the time of the destruction of the building the church had paid to the contractors the sum of $14,489.59. The church took out insurance to protect its interest in the building being constructed to the extent of $10,000, and no more. The church brought this suit in the district court of Holt county against the contractors and sureties on their bond, and in its original petition claimed a judgment for the sum of $14,489.59, the total amount paid by the church to the contractors prior to the destruction of the building, but by an amended petition, on which the action was tried, the church claimed a judgment for the sum of $12,440, the amount paid by it on the contract prior to December 31,1890. The contractors were not served with process in the action and made no appearance therein. The church had a verdict and judgment against the sureties, to reverse which they have prosecuted to this court a joint petition in error.

There are numerous assignments of error here that the district court erred in giving all of certain named instructions and that it erred in refusing to give all of certain named instructions. We have examined these instructions so far as to discover that some oí the instructions given by the court were properly given, ; n 1 that some of the instructions refused by the district court were properly refused. The assignments of error, then, as to the giving and refusing of instructions are overruled.

Certain assignments oí error relate to the action of the district court in the admission and rejection of evidence, but in view of the conclusion reached by us these assignments will not be noticed.

[540]*540One of the defenses interposed to the action was that the church had failed and neglected to insure the building to the extent of its interest therein according to the terms of the contract, and that such failure and neglect on the part of the church had released and discharged the sureties. The church met this defense by replying that it had no insurable interest in the building being constructed, and that the amount of insurance which it had taken out on the building was as large a sum as was practicable, or as any responsible insurance company would carry. It is not disputed that the church never had over $10,000 of insurance on this property. The allegations in the church’s reply that it had no insurable interest in the building being constructed is not urged by its. counsel here. Is the failure and neglect of the church to insure the building to the extent of its interest therein a defense to these sureties? In Watts v. Shuttleworth, 7 Hurl. & N. [Eng.], 253, a contractor had agreed to furnish the material and to “ execute the fittings of the first and second floors of a warehouse for the owner” by a certain date, and for a certain sum, payable in installments of not less than twenty per cent as the work progressed. The contractor further agreed that he would provide a store-room for the express purpose of the reception of the fittings from time to time as they were completed and until they were ready to be used in the warehouse; and the contract further provided that the owner should insure these fittings from risk or accident by fire. The contractor entered upon the performance of his contract, and, it appears, had a large number of fittings completed and stored; and while thus in store, and before they were placed in the warehouse, the fittings were destroyed by fire. The owner had neglected to take out any insurance on the fittings. The contractor failed to perform his contract, became insolvent, and the owner brought this suit on the bond to recover the amount of money which he had paid the contractor on the contract. The surety on the con[541]*541tractor’s bond interposed the defense that the owner had failed and neglected to insure the fittings as he had agreed. The court, in discussing.this defense, said: “The substantial question in the case is, whether the omission to insure discharges the defendant, the surety. The rule upon the subject seems to be that if the person guarantied does not act injurious to the surety, or inconsistent with his rights, or if he omits to do any act which his duty enjoins him to do, and the omission proves injurious to the surety, the latter will be discharged.” Judgment was entered for the surety. This judgment was affirmed on appeal, the court holding that the owner was bound to insure the fittings, and that his omission to do so discharged the defendant’s liability, not merely to the extent of the benefit he would have derived from the insurance if effected, but in toto. (See Watts v. Shuttleworth, 7 Hurl. & N. [Eng.], 253.) Applying the rule announced by these cases to the facts of the case at bar we conclude that the failure of the church to insure its interest in the building being constructed is a complete defense for the sureties on the bond of the contractors. To overthrow this defense counsel for the church make several arguments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Fidelity & Guaranty Co. v. Parsons
112 So. 469 (Mississippi Supreme Court, 1927)
Hagan Lumber Co. v. Duryea School District
121 A. 107 (Supreme Court of Pennsylvania, 1923)
Burt County v. Lewis
141 N.W. 1032 (Nebraska Supreme Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
63 N.W. 864, 45 Neb. 535, 1895 Neb. LEXIS 238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gallagher-v-st-patricks-church-neb-1895.