Galin Corp. v. MCI Telecommunications Corp.

CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 11, 1994
Docket92-02649
StatusPublished

This text of Galin Corp. v. MCI Telecommunications Corp. (Galin Corp. v. MCI Telecommunications Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Galin Corp. v. MCI Telecommunications Corp., (5th Cir. 1994).

Opinion

IN THE UNITED STATES COURT OF APPEALS

FOR THE FIFTH CIRCUIT

No. 92-2649

GALIN CORPORATION and PETROPAK, INC., Plaintiffs-Appellants,

versus

MCI TELECOMMUNICATIONS CORPORATION, Defendant-Appellee.

Appeal from the United States District Court for the Southern District of Texas

( January 14, 1994 )

Before WISDOM, HIGGINBOTHAM, and SMITH, Circuit Judges.

HIGGINBOTHAM, Circuit Judge:

This is a diversity suit for breach of a construction

contract. The district court granted judgment denying relief to

plaintiffs at the outset of trial, but without allowing the parties

to present evidence to the jury. We agree with the district court

that plaintiffs' claims are barred by the terms of the release and

notice of claim provisions of the construction contract. We also

conclude that the district court's unusual grant of judgment at the

outset of trial was effectively a grant of summary judgment that

had been argued earlier. We affirm. I

In March 1987, MCI Telecommunications Corporation invited bids

on a fiber optic cable installation route comprising eight sections

to extend through Georgia, Alabama and Tennessee. Galin

Corporation and Petropak, Inc., met with MCI personnel, made

extensive visits to various future work sites, and analyzed MCI's

plans, specifications, and bid instructions. Galin and Petropak

then submitted bids on six of the eight sections. MCI accepted no

bids on the project. In late August of the same year, MCI issued

new instructions for the installation of a shorter version of the

same fiber optic cable route. Before requesting a second set of

bids, MCI released to the prospective contractors an estimate of

the amount of subsurface rock that lay along the cable route.

Galin and Petropak again submitted a bid, this time at a lower

price, which MCI accepted. The parties executed a written

contract.

Galin and Petropak commenced work in early November. During

the project, MCI complained to Galin and Petropak of their lack of

timely progress and, on December 18, MCI gave Galin and Petropak

notice of termination by default for failure to meet the contract

schedule. On December 30, MCI eliminated the last seven miles of

the cable route from the contract.

Galin and Petropak say that they completed the installation of

the cable on or about February 21, 1988, "except for areas where

MCI had failed to obtain necessary permits or easements and where

2 MCI had misrepresented the existence of rocks"; and that they then

commenced cleaning up their work sites.

On April 22, 1988, MCI issued a proposed Final Modification of

Contract, which Galin and Petropak did not sign. As the project

had progressed, however, Galin and Petropak had signed a series of

releases in exchange for incremental payments from MCI. They

signed the last of these releases on May 13, 1988. Finally, in

July of 1988, MCI terminated the contract for non-performance.

Settlement negotiations failed and Galin and Petropak filed

this suit in a Texas court seeking compensation from MCI for breach

of contract, in quantum meruit, and in tort. MCI removed to

federal district court invoking the court's diversity jurisdiction.

MCI and Galin and Petropak then both moved for summary judgment.

The district court granted judgment to MCI on Galin and Petropak's

claim for breach of a covenant of good faith and fair dealing, but

left the remaining issues for trial.

When the case was called for trial, MCI asserted that the

district court should render judgment. The district court granted

the requested relief treating it as a motion for judgment as a

matter of law under Federal Rule of Civil Procedure 50(a).

Applying New York law, the court dismissed the case before the

first witness was called. Galin and Petropak appeal.

3 II

Galin and Petropak pursue several claims.

Galin and Petropak allege that MCI deliberately underestimated

the amount of subsurface rock that lay along the route to decrease

the cost of construction. The subcontractor who performed the rock

probes, Galin and Petropak assert, did not work long enough to

produce the results that MCI released. Galin and Petropak argue

that MCI must have fabricated either some or all of the site

information. They claim to have relied on this falsely optimistic

information in their bid.

According to Galin and Petropak, MCI engaged in other

questionable business practices. They allege that MCI's designs

for installing the cable were faulty, that MCI failed to obtain

timely permission for them work on several stretches of the route,

that MCI interfered in their operations, that MCI forced them to

meet more exacting standards during the clean up process than the

contract required, and that MCI otherwise failed to support them.

Galin and Petropak sue for recovery on the contract, in

quantum meruit for extra-contractual work performed, for

compensation for MCI's wrongful interference with their contract

performance, and for compensation for MCI's breach of its duty of

good faith and fair dealing.1 The district court decided the case

1 Galin and Petropak wish to recover the balance owed on their contract with MCI, compensation for the work they performed outside the scope of their contract with MCI, and damages which they incurred as a result of delays, acts of interference, improper administration of the contract, misrepresentations, and other reckless, grossly negligent, arbitrary and capricious acts by MCI.

4 based on provisions in the contract that protect MCI from liability

and on the releases that Galin and Petropak signed. Galin and

Petropak argue that the protective provisions and releases are

inapplicable to their claims and, further, that MCI waived

application of the provisions. The parties agree that New York law

controls.

A.

At the outset, Galin and Petropak argue that the district

court improperly invoked Federal Rule of Civil Procedure 50(a) in

dismissing their case. First, they argue that Rule 50(a) required

that MCI move for judgment as a matter of law and that when the

court ruled MCI had not done so. Second, they argue that they had

not been fully heard by the court, as required by Rule 50(a),

before it rendered judgment. We need not address these contentions

as we construe the court's order as a grant of summary judgment and

affirm on that basis.

The district court early in the case denied MCI's motion for

summary judgment, to which Galin and Petropak had fully responded.

On reconsidering, the court concluded that the case did turn on the

notice and release provisions of the contract. This interpretation

presented no issues of fact and protected MCI from liability. The

court therefore ruled in MCI's favor, albeit under Federal Rule of

Civil Procedure 50(a).

Where a case does not require the resolution of material

facts, summary judgment is appropriate. See Seneca v. Phillips

Petroleum Co., 963 F.2d 762

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seven-Up Bottling Co.(Bangkok) v. Pepsico, Inc.
686 F. Supp. 1015 (S.D. New York, 1988)
Gilbert Frank Corp. v. Federal Insurance
520 N.E.2d 512 (New York Court of Appeals, 1988)
Janos v. Peck
21 A.D.2d 529 (Appellate Division of the Supreme Court of New York, 1964)
Savin Brothers, Inc. v. State
62 A.D.2d 511 (Appellate Division of the Supreme Court of New York, 1978)
Silverstein Properties, Inc. v. Paine, Webber, Jackson & Curtis, Inc.
104 A.D.2d 769 (Appellate Division of the Supreme Court of New York, 1984)
Herman v. Malamed
110 A.D.2d 575 (Appellate Division of the Supreme Court of New York, 1985)
Gilbert Frank Corp. v. Federal Insurance
129 A.D.2d 414 (Appellate Division of the Supreme Court of New York, 1987)
Troy News Co. v. City of Troy
167 A.D.2d 730 (Appellate Division of the Supreme Court of New York, 1990)
Metz v. Metz
175 A.D.2d 938 (Appellate Division of the Supreme Court of New York, 1991)
DeCosta v. Williams
119 Misc. 2d 314 (New York Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
Galin Corp. v. MCI Telecommunications Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/galin-corp-v-mci-telecommunications-corp-ca5-1994.