Gale v. Dixon

267 P. 342, 91 Cal. App. 529, 1928 Cal. App. LEXIS 965
CourtCalifornia Court of Appeal
DecidedMay 2, 1928
DocketDocket No. 4897.
StatusPublished
Cited by5 cases

This text of 267 P. 342 (Gale v. Dixon) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gale v. Dixon, 267 P. 342, 91 Cal. App. 529, 1928 Cal. App. LEXIS 965 (Cal. Ct. App. 1928).

Opinion

CRAIG, J.

The parties to this action entered into a contract in writing whereby appellant agreed to construct for respondent at the city of Riverside two bungalows and a *531 garage according to plans and specifications, and respondent agreed to pay therefor the sum of $6,900, as the work progressed, in three equal installments of $2,300 each. The buildings were completed, respondent paid the first two installments, and took possession, but declined to make the final payment on account of various alleged wilful or negligent violations of the contract through failure to comply with the specifications. This action was instituted for the recovery of the sum last mentioned.

The case was tried before the superior court, without a jury, and the trial court made findings from the evidence, enumerating 24 technical specifications, designated by letter from “a” to “x,” inclusive. Twelve of these it found had not been complied with, and also that the defendant had been damaged thereby in the sum of $1,213; it further found that $140.90 had been paid in addition to the $4,600 admitted by the complaint, and that the amount remaining unpaid was $946.10. Conclusions of law were signed and filed, reciting that the plaintiff was entitled to judgment for this latter amount, and judgment was rendered accordingly.

Finding numbered IV recites: “That said defects were caused by the want of proper care and attention of the plaintiff and the workmanship was not first class, and the material used in the construction of said houses and garage is not first class, and defects, omissions and changes from the plans and specifications pervade the whole of said structures, and the plaintiff has not performed his contract as agreed, and he did not substantially perform same, or attempt honestly and in good faith to perform the same; the defendant did not accept said houses as being constructed in compliance with said contract.”

The plaintiff made a motion for new trial on August 7, 1923, and on August 11th the defendant moved that the judgment be vacated, that judgment for costs be entered in his favor, that the plaintiff be denied any relief, and that the conclusions of law be amended to conform thereto. The latter motion was argued and submitted, and the trial court granted the same, striking out its former conclusions of law, “and substituting in lieu thereof the following: As a conclusion of law from the foregoing facts the court finds that the defendant is entitled to judgment, that the plaintiff *532 take nothing by his action, and that the defendant is entitled to recover of and from the plaintiff his costs of defense herein.” Judgment was then entered in accordance with this latter ruling and conclusion.

The plaintiff appealed from the first judgment upon the ground, among others, that he should have been awarded the full amount demanded, less $140, and that the judgment was not supported by the evidence. He also appealed from the judgment last entered upon the ground that the trial court was without power to alter its conclusions of law and judgment, or to do more than grant a new trial, which the defendant did not request. It is insisted by appellant that the substituted judgment is void for the reason that conclusions of law may under such circumstances be modified or amended only to conform to the findings of fact, whereas, as amended, the conclusion above quoted is contrary to the findings.

It is the theory of respondent, and was stated by the trial court in granting the motion to vacate the original judgment, that a builder acting in good faith may recover the contract price, notwithstanding slight and trivial defects or deviations from the specifications, and is not held to a strict and literal compliance therewith; but that there is no legal basis for one acting in bad faith to recover either a reasonable value of the services or the contract price less the damages.

The Code of Civil Procedure, in section 663 thereof, provides that a judgment of the superior court may be vacated and another and different judgment entered when the conclusions of law are incorrect or inconsistent with the findings of fact, and that in such event the conclusions of law shall be corrected and amended. It has been held that such a matter is properly reviewable in the trial court under said section, rather than by motion for new trial. (Elizalde v. Murphy, 11 Cal. App. 32, 39 [103 Pac. 904].)

Therefore, we proceed to inquire, first, as to whether or not the plaintiff, under the finding that he failed to attempt honestly and in good faith to perform his contract substantially in accordance with agreed plans and specifications, but having received about two-thirds of the contract price, is entitled to judgment for the balance; and, second, as to whether or not under the facts presented such finding is warranted by the evidence.

*533 We think that if the finding in question be sustained, the trial court properly vacated the original judgment, and that the one which was substituted therefor, and the amended conclusions of law, must be upheld. It seems to be the established rule in this and many other jurisdictions that where a builder wilfully and without justification fails substantially to perform, though the owner cannot avoid availing himself of the benefit of partial performance because the labor and material are attached to his freehold, the contractor is not entitled to compensation, even though the owner may take possession of the incomplete structure. (9 C. J., p. 819, and cases there cited. Our supreme court, in Connell v. Higgins, 170 Cal. 541, 556 [150 Pac. 769, 775], quotes from 2 Elliott on Contracts, section 1607, as follows: “A substantial performance must be established, in order to entitle the party claiming the benefit of the contract to recover; but this does not mean a literal compliance as to the details that are unimportant. There must be no willful or intentional departure, and the defects of performance must not pervade the whole or be so essential as substantially to defeat the object which the parties intend to accomplish. Whether, in any ease, such defects or omissions are substantial, or merely unimportant mistakes that have been or may be corrected, is generally a question of fact.”

The court found in the instant case that through want of proper care and attention the plaintiff failed to furnish first-class materials or workmanship; that he did not substantially perform or attempt to perform his contract honestly or in good faith, and that the defects complained of pervaded the whole of said structures. The rule above stated was followed, and a judgment for an alleged balance, after partial payment, was likewise denied in each of the following cases: Laidlaw v. Marye, 133 Cal. 170 [65 Pac. 391]; Merchant v. Hayes, 117 Cal. 669 [49 Pac. 840]; Lynip v. Alturas School District, 24 Cal. App. 426 [141 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pioneer Title Insurance v. Guttman
345 P.2d 577 (California Court of Appeal, 1959)
Murphy v. Sheftel
9 P.2d 568 (California Court of Appeal, 1932)
Sun Oil Co. of California v. Union Drilling & Petroleum Co.
280 P. 535 (California Supreme Court, 1929)
Abney v. Belmont Country Club Properties, Inc.
279 P. 829 (California Court of Appeal, 1929)
Irer v. Gawn
277 P. 1053 (California Court of Appeal, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
267 P. 342, 91 Cal. App. 529, 1928 Cal. App. LEXIS 965, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gale-v-dixon-calctapp-1928.