G. S. F. Corp. v. Sandell Manufacturing Co. (In Re G. S. F. Corp.)

6 B.R. 894, 31 U.C.C. Rep. Serv. (West) 919, 1980 Bankr. LEXIS 4134
CourtUnited States Bankruptcy Court, D. Massachusetts
DecidedNovember 10, 1980
Docket19-30142
StatusPublished
Cited by3 cases

This text of 6 B.R. 894 (G. S. F. Corp. v. Sandell Manufacturing Co. (In Re G. S. F. Corp.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G. S. F. Corp. v. Sandell Manufacturing Co. (In Re G. S. F. Corp.), 6 B.R. 894, 31 U.C.C. Rep. Serv. (West) 919, 1980 Bankr. LEXIS 4134 (Mass. 1980).

Opinion

FINDINGS OF FACT, RULINGS OF LAW

HAROLD LAVIEN, Bankruptcy Judge.

This is an action brought by the Plaintiff, G. S. F. Corp., Debtor-in-Possession under Chapter 11, against the defendant, Sandell Manufacturing Company, Inc. for goods sold and delivered, but not paid for. Defendant counterclaims for damages due to allegedly defective goods sold to it by the Plaintiff.

Specifically, G. S. F. delivered a shipment of polyurethane foam to Sandell in February of 1980, for which Sandell has, admittedly, not paid. Sandell defends and counterclaims against G. S. F. alleging that the foam was defective and that it did not perform according to specifications. San-dell seeks damages for the alleged defects.

G. S. F. Corp. is engaged in the manufacture of polyurethane foam, primarily for use in bedding, furniture and packaging. The parties have been dealing with each other since 1975, when Sandell placed its first order for foam with G. S. F. Although Sandell’s counsel talked of a specific formula which Sandell submitted, there was no actual evidence of any such formula, and I find that all orders for Sandell were filled from a G. S. F. stock formula which was changed at Sandell’s request for the shipment in question to reduce the cost by eliminating the fire resistant component.

Sandell treated the polyurethane foam with polymers in a manufacturing process that yielded a waterproof sealant, called Polytite, for use in construction joints. This process required the foam to be open-celled to enable it to absorb the polymers in the Sandell treatment. I note at the outset, however, that G. S. F. foam, like all polyurethane foam, is not in and of itself a natural waterproof material. Quite the contrary, it is a water absorbent material. It was only Sandell’s treatment of the foam which made it a waterproof sealant. The cellular structure of G. S. F.’s product, however, ultimately affected the effectiveness of Sandell’s treatment. Interestingly, the less perfect the cell formation, the better, since the success of the treatment required the filling of the cells with polymer and, therefore, the more broken walls between cells, the more readily the polymer flowed between cells.

The evidence indicated that the parties were dealing with each other on satisfactory terms since 1975 until the last shipment of foam was delivered by G. S. F. to Sandell in February, 1980. This shipment was of standard 3000 molecular weight foam but manufactured according to a formula which left out what was considered to be an unnecessary fire retardant. There was no evidence to indicate that the lack of the fire retardant rendered the foam unfit for the Sandell polymer treatment.

On February 15, Sandell picked up the first batch of the February shipment. Max Wasserman, the general manager of San-dell and the inventor of Polytite, testified that the foam looked so bad to him that within a week, he had run his in house tests and was aware of the problem. He then called in Joe Hartigan, the G. S. F. salesman who handled the Sandell account, to demonstrate the inability of this foam to absorb the polymer and become waterproof. He also complained that the material looked different and was not cut to uniform widths and was torn at the ends. Wasserman even *896 performed a test for Hartigan in which he simulated the Sandell treatment on the foam. Two pieces of foam were placed in liquid, one of the pieces absorbed the liquid, the other did not. It was Wasserman’s claim that the piece which did not absorb the liquid was a piece of the G. S. F. foam from the February shipment. 1 Hartigan relayed Wasserman’s complaint to Frank Ippollito, sales manager of G. S. F. who, according to Wasserman, visited him between February 20th and 25th and, in any event, before the letters of March 5 and 6, and I so find. Both Hartigan and Ippollito suggested the return of the foam. However, Wasserman said that although Sandell still had the majority of the foam in its possession, that as a result of their testing, they were satisfied that they could make the foam watertight by increasing the amount of polymer. Wasserman indicated that Sandell was going to fill some of its overseas orders by using the foam and, instead of returning the foam, insisted on a 20% credit.

The meetings were followed up by a letter, dated March 5, from Wasserman to G. S. F., in which Wasserman indicated that the February order contained a minimum of 20% wastage, which he was deducting from the bill, that if Sandell were not in a rush for the foam, they would have sent the entire load back, and that this was the worst material Wasserman had ever seen from any manufacturer. This letter was followed by another one, dated March 6, from the treasurer of Sandell to G. S. F., adjusting the charges for the February shipment to reflect a 20% credit for waste. Neither letter rejected the material or offered its return, or refused payment but, in fact, agreed that after taking the 20% credit, $5,839.47 was due.

Sandell delivered a batch of Polytite which was manufactured from the February, 1980 delivery of G. S. F. foam to the E. B. Jones Construction Company on March 4, 1980. Because of complaints from E. B. Jones, Sandell took back all the material it had shipped and issued a credit to E. B. Jones for $1,800.00.

Starting May 20, 1980, and continuing through July, despite its knowledge of the problems and its ability to purchase and, in fact, its actual purchases of substitute foam, during this period, from Rogers, another supplier, Sandell delivered Polytite to a construction job at the Baltimore Stadium. Because of complaints about the Poly-tite, Sandell took back the defective material at no charge and issued credits, spending in total, approximately $14,000.00. In addition, Sandell claims to have approximately $3,000.00 of G. S. F. foam on hand which it cannot use because of a defect in its cell structure which does not allow the foam to be successfully treated by Sandell.

No evidence was offered by Sandell as to its ability or inability to buy substitute foam from Rogers or any other supplier at any specific period of time nor at what price it was making the purchases when it, in fact, in the late Spring, started to purchase foam from Rogers. No invoice or other specific evidence was offered as to the first Rogers purchase, nor was any evidence offered as to how long it took Sandell to process the foam.

Prior to the debtor bringing suit and San-dell answering by counterclaim, Sandell offered no evidence of any notice of revocation of acceptance or claim of breach of warranty, other than its claim of credit in the letters of March 5 and 6.

There was no evidence offered of negligence or other cause for the February foam not being suitable other than the alleged unaccounted for difference in cell structure.

These were the only two orders on which credit was given because of complaints of *897 unsatisfactory performance, although San-dell used the foam and its modified process to fill an undetermined number of orders. Sandell’s argument is that the defects in the February shipment of foam caused a breach of contract by G. S. F., thereby entitling Sandell to damages. This claim is without merit under the applicable law and under the facts as I have found them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
6 B.R. 894, 31 U.C.C. Rep. Serv. (West) 919, 1980 Bankr. LEXIS 4134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-s-f-corp-v-sandell-manufacturing-co-in-re-g-s-f-corp-mab-1980.