FS, Inc. v. Jefferson County Conservation Board

CourtCourt of Appeals of Iowa
DecidedMay 27, 2026
Docket25-0556
StatusPublished

This text of FS, Inc. v. Jefferson County Conservation Board (FS, Inc. v. Jefferson County Conservation Board) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
FS, Inc. v. Jefferson County Conservation Board, (iowactapp 2026).

Opinion

IN THE COURT OF APPEALS OF IOWA _______________

No. 25-0556 Filed May 27, 2026 _______________

FS, Inc., Plaintiff–Appellant, v. Jefferson County Conservation Board, Defendant–Appellee. _______________

Appeal from the Iowa District Court for Jefferson County, The Honorable Shawn Showers, Judge. _______________

AFFIRMED _______________

Frederic C. Hayer (argued) of Aspelmeier, Fisch, Power, Engberg & Helling, P.L.C., Burlington, attorney for appellant.

Chauncey Moulding, Jefferson County Attorney, and Edwin F. Kelly (argued), Assistant Jefferson County Attorney, Fairfield, attorneys for appellee. _______________

Heard at oral argument by Schumacher, P.J., Chicchelly, J., and Bower, S.J. Opinion by Bower, S.J.

1 BOWER, Senior Judge.

FS, Inc. (Four Seasons) appeals from an adverse breach-of-contract ruling. Following our review, we affirm.

I. Background Facts & Prior Proceedings

After the Jefferson County Conservation Board (the Board) secured funding to develop campgrounds, the Board requested bids from contractors to complete the project. The notice to bidders required bidders to put up a ten percent bid bond along with the performance bid. See Iowa Code § 26.8 (2024). The performance bid and bid bonds were to be opened at a regularly scheduled public meeting on February 28, 2024.

At the meeting, the bids were opened, including a bid submitted by Four Seasons. Four Seasons had the lowest bid. However, it was accompanied by a bid bond of five percent instead of the required ten percent. No one initially noticed that issue, and the Board indicated Four Seasons would be selected to complete the project, pending engineer review of the bid.

The engineer noticed Four Seasons’ bid bond was insufficient and deemed the bid itself to be non-responsive as a result. The Board ultimately contracted with the company that provided the next lowest bid with a ten percent bid bond.

Four Seasons then brought this action against the Board claiming breach of contract and seeking compensation for lost profits. It sent a request for admissions regarding thirty statements to the Board. But the Board failed to file a timely response to the request or move for permission to file a late response to the request for admissions. As result, Four Seasons sought summary judgment, arguing that all the requests for admissions were

2 admitted under Iowa Rule of Civil Procedure 1.510(2). The Board also sought summary judgment. The district court deemed the request for admissions admitted given the Board’s failure to file a timely response but denied the motions for summary judgment.

The matter proceeded to a bench trial, where Four Seasons objected to the Board’s presentation of any evidence contrary to the thirty admitted statements. The thirty admissions are as follows:

1. “Multiple contractors who had submitted bids relating to the Prairie Ridge Campground Project (the ‘Project’) were present at the Board meeting held on February 28, 2024.”

2. “Four Seasons’ bid was opened at the February 28, 2024 Board meeting.”

3. “After Four Seasons’ bid was opened at the February 28, 2024 Board meeting, the amount of the Four Seasons’ bid bond was readily ascertainable.”

4. “The Board has at all relevant times considered Four Seasons to be sufficiently qualified and able to perform the contract for the Project if it was awarded to Four Seasons.”

5. “At the February 28, 2024 Board meeting, the Board accepted Four Seasons’ bid.”

6. “At the February 28, 2024 Board meeting, the Board never determined that Four Seasons’ bid was non-responsive.”

3 7. “After the February 28, 2024 Board meeting, the Board refused to execute a contract for the Project with Four Seasons on the ground that Four Seasons’ bid was non-responsive.”

8. “The Board’s determination that Four Seasons’ bid was non- responsive was based solely on Four Seasons’ bid bond being five percent.”

9. “The Board has accepted the bid of Leffler Dirtworks, LLC to perform the work on the Project.”

10. “The bids of Four Seasons and Leffler Dirtworks, LLC each provide for the same exact work to be completed in constructing the Project.”

11. “After the Board’s acceptance of Four Seasons’ bid, Four Seasons did not have the right to withdraw its bid without forfeiting its bid bond.”

12. “Had the Board and Four Seasons entered into a formal contract for the completion of the Project with Four Seasons providing the proposed performance bond for the Project, any discrepancy regarding the amount of the bid bond would have been of no concern to the Board.”

13. “The Board is the only entity responsible for paying for the Project.”

14. “After the February 28, 2024 Board meeting, the Board failed to offer Four Seasons a contract for the Project.”

4 15. “After the February 28, 2024 Board meeting, the engineer completed a review of the Four Seasons’ bid.”

16. “After the February 28, 2024 Board meeting, Four Seasons acted in good faith in relation to the Board and the Project.”

17. “After the February 28, 2024 Board meeting, Four Seasons did not prevent satisfaction of any conditions relating to the Project which may have existed.”

18. “A five percent bid bond is not in violation of any Iowa statute.”

19. “The amount of the bid bond with respect to the Project would not change in any way the work was to be completed as part of the Project.”

20.“The amount of the bid for the project by Leffler Dirtworks, LLC was $890,469—which is $82,025 more than Four Seasons’ bid for $808,444.”

21. “If the Board allows Leffler Dirtworks, LLC to complete the Project, it will be obligated to pay $82,025 more than what Four Seasons bid to complete the Project.”

22.“The public would not have been prejudiced had the Board allowed Four Seasons to post a performance bond and complete the Project according to its bid.”

23. “Four Seasons’ bid conforms in all material respects to the actual construction work proposed in the Board’s Notice to Bidders for the Project.”

5 24.“The Board had full authority to award the contract for the Project and did not require the approval of any other person, individual, agency, or entity.”

25. “The submission of a lower bid bond does not give a bidder a substantial advantage or benefit not enjoyed by other bidders.”

26. “The people of Jefferson County would benefit if the Board could have the Project completed for less money.”

27. “Ben Brueck, President of Four Seasons, was present at the February 28, 2024 meeting when the Board accepted Four Seasons’ bid.”

28.“Four Seasons’s bid addressed all material terms relating to the construction of the Project.”

29. “No further material terms relating to the construction of the Project beyond the terms contained in Four Seasons’ bid remained to be negotiated after February 28, 2024.”

30. “On February 28, 2024, the Board assented to the material terms relating to the construction of the Project as contained in Four Seasons’ bid.”

The district court agreed that these statements were deemed admitted as the law of the case under the prior summary judgment ruling. However, the court allowed the Board to present evidence, some of which conflicted with the admissions. The district court found the Board’s acceptance of Four Seasons’ bid was conditioned on approval by an engineer. And it ultimately concluded the parties never entered an enforceable contract, noting that even

6 if the Board breached an enforceable contract, Four Seasons’ evidence of damages was too speculative.

Four Seasons appeals.

II. Standard of Review

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Molo Oil Co. v. River City Ford Truck Sales, Inc.
578 N.W.2d 222 (Supreme Court of Iowa, 1998)
Horsfield Construction, Inc. v. Dubuque County
653 N.W.2d 563 (Supreme Court of Iowa, 2002)
NevadaCare, Inc. v. Department of Human Services
783 N.W.2d 459 (Supreme Court of Iowa, 2010)
Olson v. Nieman's, Ltd.
579 N.W.2d 299 (Supreme Court of Iowa, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
FS, Inc. v. Jefferson County Conservation Board, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fs-inc-v-jefferson-county-conservation-board-iowactapp-2026.