Frontera Eastern Georgia, Ltd. v. Arar, Incorporat

483 F. App'x 896
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 16, 2012
Docket11-20661
StatusUnpublished

This text of 483 F. App'x 896 (Frontera Eastern Georgia, Ltd. v. Arar, Incorporat) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frontera Eastern Georgia, Ltd. v. Arar, Incorporat, 483 F. App'x 896 (5th Cir. 2012).

Opinion

PER CURIAM: *

ARAR, Incorporated (“ARAR”) appeals from the district court’s confirmation of an arbitration award in favor of Frontera Eastern Georgia, Limited (“Frontera”) and dismissal of its counterclaim for money had and received. Having heard the parties’ arguments and studied their briefs and the relevant case law, we affirm the judgment of the district court.

I.

Frontera initiated arbitration after a dispute arose between the parties related to their drilling contract. The parties selected and confirmed a three-member arbitral panel (the “panel”), and a merits hearing was scheduled for December 2008. Mere days before the hearing, the parties negotiated and executed a Settlement Agreement, 1 the terms of which called for ARAR to make an immediate $300,000 payment, followed by $950,000 (plus interest) in in *898 stallment payments over a period of twelve months beginning in January 2009. ARAR also was required to obtain a $500,000 irrevocable letter of credit in favor of Frontera by January 15, 2009. Its failure to do so entitled Frontera, under Section 5(i) of the Settlement Agreement, to submit a Final Award by Consent (“Final Award”) in the amount of $1.25 million, plus certain expenses, which the panel “shall issue,” if requested, in the form attached to the Settlement Agreement as Exhibit B.

ARAR timely made the $300,000 payment. It failed, however, to obtain the letter of credit by January 15, 2009, or at any point thereafter. Although Frontera warned ARAR that its noncompliance entitled Frontera to seek entry of the Final Award, Frontera accepted ARAR’s installment payments through July 2009. By that point, ARAR had made payments totaling approximately $900,000. ARAR missed the August and September 2009 installment payments, prompting Frontera to request entry of the Final Award from the panel under the terms of Section 5(i), despite the fact that the unpaid installments only totaled approximately $400,000.

ARAR objected to the panel’s entry of the Final Award, arguing, inter alia, that the panel lacked jurisdiction to enter the Final Award because the parties had failed to comply with a mediation provision in the Settlement Agreement and that ARAR should be awarded an offset in the amount of the Final Award for payments it had made to Frontera. The panel, at ARAR’s urging, convened a hearing on March 25, 2010 to hear the parties’ arguments on the disputed issues.

On April 19, 2010, the panel issued the Final Award, in which it ordered ARAR to pay Frontera $1.25 million, plus certain expenses. 2 The panel overruled ARAR’s jurisdictional objection and determined that neither the language of the Settlement Agreement nor Texas law required that an offset in the amount of the Final Award be given for ARAR’s payments to Frontera.

Frontera filed suit in federal district court on April 29, 2010 to confirm and enforce the Final Award under 9 U.S.C. § 9. 3 ARAR answered and counterclaimed for, inter alia, vacatur of the award under 9 U.S.C. § 10, 4 and money had and received. The district court confirmed the panel’s Final Award in its entirety and dismissed ARAR’s counterclaims and affirmative defenses. The district court held that the panel did not exceed its authority in deciding: (1) that it had jurisdiction to enter the Final Award; (2) that the language of the Settlement Agreement did not require an offset; and (3) that Texas law concerning unenforceable contractual penalties did not apply to the Final Award. The district court dismissed ARAR’s money had and received counterclaim on the ground that it was an impermissible collateral attack on the panel’s Final Award.

*899 II.

Although we review a district court’s confirmation of an arbitration award de novo, our “ ‘review of the underlying award is exceedingly deferential.’ ” Rain CII Carbon, LLC v. ConocoPhillips Co., 674 F.3d 469, 472 (5th Cir.2012) (quoting Apache Bohai Corp. LDC v. Texaco China BV, 480 F.3d 397, 401 (5th Cir.2007)). “An award may not be set aside for a mere mistake of fact or law.” Apache, 480 F.3d at 401.

III.

The district court correctly concluded that the panel did not exceed its authority in determining that it had jurisdiction to interpret the Settlement Agreement and enter the Final Award because the parties’ Settlement Agreement incorporated the International Arbitration Rules of the International Centre for Dispute Resolution (“ICDR Rules”). Article 15(1) of the ICDR Rules states that “[t]he tribunal shall have the power to rule on its own jurisdiction, including any objections with respect to the existence, scope or validity of the arbitration agreement.” The parties’ incorporation of the ICDR Rules constitutes clear and unmistakable evidence of the parties’ intent to arbitrate questions of arbitrability, Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 83, 123 S.Ct. 588, 154 L.Ed.2d 491 (2002), and we will not disturb the panel’s jurisdictional decision even if we disagree with it, T.Co Metals, LLC v. Dempsey Pipe & Supply, Inc., 592 F.3d 329, 344-45 (2d Cir.2010). In rejecting ARAR’s argument that the parties were required to mediate under Section 12 of the Settlement Agreement before the panel could interpret the agreement and enter the Final Award, the panel determined that Section 12 must be reconciled with Sections 4 and 5, which clearly subjected the parties to the panel’s jurisdiction to enter a Final Award pursuant to Exhibit B. We agree with the district court that the panel’s interpretation of these sections is rationally inferable from the language of the Settlement Agreement, Reed v. Florida Metro. Univ., Inc., 681 F.3d 630, 637 & n. 8 (5th Cir.2012), and a decision that, consistent with Texas contract law, “harmonize[d] and [gave] effect to all the provisions of the contract so that none will be rendered meaningless,” Seagull Energy E & P, Inc. v. Eland Energy, Inc., 207 S.W.3d 342, 345 (Tex.2006) (internal quotation marks and emphasis omitted).

The district court did not err, moreover, in determining that the panel did not exceed its authority in issuing the Final Award in the amount of $1.25 million with no offset for the payments ARAR had made to Frontera through July 2009.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Apache Bohai Corp. LDC v. Texaco China BV
480 F.3d 397 (Fifth Circuit, 2007)
Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
RAIN CII CARBON, LLC v. ConocoPhillips Co.
674 F.3d 469 (Fifth Circuit, 2012)
Jeffrey Reed v. Florida Metro University, Inc., et
681 F.3d 630 (Fifth Circuit, 2012)
Seagull Energy E & P, Inc. v. Eland Energy, Inc.
207 S.W.3d 342 (Texas Supreme Court, 2006)
T. CO METALS, LLC v. Dempsey Pipe & Supply, Inc.
592 F.3d 329 (Second Circuit, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
483 F. App'x 896, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frontera-eastern-georgia-ltd-v-arar-incorporat-ca5-2012.