Frolich v. Walbridge-Aldinger Co.

210 N.W. 488, 236 Mich. 425, 1926 Mich. LEXIS 860
CourtMichigan Supreme Court
DecidedOctober 22, 1926
DocketDocket No. 13.
StatusPublished
Cited by12 cases

This text of 210 N.W. 488 (Frolich v. Walbridge-Aldinger Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frolich v. Walbridge-Aldinger Co., 210 N.W. 488, 236 Mich. 425, 1926 Mich. LEXIS 860 (Mich. 1926).

Opinion

Steere, J.

On April 8, 1916, defendant contracted to construct a large building on Washington boulevard in the city of Detroit, known as the Book building. On May 10, 1916, it let a subcontract toi plaintiff, Frolich, for furnishing glass and doing the glazing in said building, “except paragraph No. 377 — Dome *427 Light,” according to plans and specifications of the architect as they appeared in the original contract, the agreed price therefor being $17,500. The contract is in writing, elaborately drawn, with numerous detailed provisions and references to the original contract. As the work progressed alterations, were directed by defendant from time to time and extras ordered as authorized by the contract. Many of them are unquestioned by the contractor. Under the original contract the building was to be completed by January 1, 1917, but it was not and the record shows work being done upon it for nearly a year thereafter. After the building was completed attempts were made by the parties to this contract to reach a settlement as to the various alterations, extras, delays, etc., which intervened during its performance. Many of the items which had been questioned were agreed upon, but protracted differences arose as to others which ultimately became the subject-matter of this litigation.

Plaintiff commenced this suit by declaration in assumpsit filed February 28, 1922, declaring in a special count on its contract for full performance, and extra work done, alterations made, material furnished at the instance of defendant, etc.,' stated with considerable detail, also declaring upon the common counts. A bill of particulars was demanded and furnished stating the contract price, and showing in detail items for alterations, temporarily installed glass, overtime, breakage, differences in sizes of glass and other extras amounting to $4,824.08. An amendment to the bill of particulars also appears in the record, without date, adding an item of $667.62 for polished plate glass furnished defendant, making the amount for extras claimed under plaintiff’s declaration $5,491.65, which, added to the contract price, would make plaintiff’s total charge, under and in connection with the contract, *428 $22,991.65. Payments amounting to $19,700 were credited on this in the bill of particulars, the amount claimed yet due being $3,291.65 with interest. On November 22, 1922, defendant filed its plea of the general issue with special notice of counterclaims, including work done for plaintiff, damages done by plaintiff to sill, cost of replacing stops, glass and other claimed credits amounting to $2,347.45, alleging that such claims would be urged by way of recoupment against the demand of the said plaintiff. On November 28,1924, defendant, under its plea of general issue, filed a further notice that it would give in evidence and insist in its defense that no proper effort had been made by plaintiff to have its claims submitted to arbitration as required by the contract, which was a condition precedent to the commencement of suit. That point was pressed for defendant during the trial as the controlling question in the case, and conceded to be so if defendant’s contention that fact stood undisputed was tenable. The court was requested to dispose of it as a matter of law under the testimony, but submitted it to the jury as a question of fact. Error is assigned upon such ruling and prominently argued in briefs of counsel.

Possible deviations from the strict provisions of the contract are anticipated in several of its articles and damages to one or the other of the parties in such event are authorized to be computed and determined by the architect or agreement of the parties, but in case of the architect’s failure to act or disagreement of the parties the matter “shall be referred to arbitration as hereinafter mentioned.” The material provisions thereafter mentioned upon that subject are as follows:

“Article XV. Any arbitration herein provided for shall be as follows: The subcontractor and contractor shall each appoint one arbitrator and such arbitrators shall appoint a’ third. The decision of any two of the *429 three arbitrators shall be final and binding. * * * A party who has not appointed an arbitrator after the other party has appointed one shall do so within two days after being notified in writing by such other party to do so. If the arbitrator of either party shall fail to proceed with the consideration of the matters within three days after being requested in writing by the other party’s arbitrator so to do, such other party’s arbitrator shall, if a third has not been appointed, be at liberty to act as sole arbitrator and his decision shall be final and binding, or the other two arbitrators, if a third has been appointed, may forthwith appoint an arbitrator in lieu of the one who has failed to proceed as aforesaid, and the decision of two of such three arbitrators shall be final and binding. If either party has done all in his power to comply with the provisions herein contained as to securing an arbitration, but by reason of the default of the other party or of the said architects or of the arbitrator appointed by such other party or by reason of the architects failing to certify in respect of any matter or thing upon which he should under the terms hereof adjudicate or render certificate * * * such party may take such action as would be permissible in the courts in the same way as if no reference of the-matter in question either to the said architects or to arbitration had been herein provided for and the other party shall not be at liberty to object that the adjudication of the architects or a certificate from them is prerequisite or that the remedy is only by arbitration or that arbitration is a prerequisite to such action being taken. * * * An award under the provisions of this article may be made a rule or judgment of any proper court in the State of Michigan.”

This article is not in conformity with our statutory requirements (3 Comp. Laws 1915, § 13646 et seq.) and makes no reference to the act, but in any event it is an agreement for a common-law arbitration.

When tenacious differences arose in their attempts to settle, arbitration was proposed by plaintiff and tentatively consented to by both parties, but defendant failed to name an arbitrator. Frolich testified *430 that he talked with defendant’s officers about arbitrating and named as his arbitrator, to both its vice-president, Walbridge, and secretary, Lewitt, a Mr. Morgan who was then doing some work for defendant, telling them that as Morgan was familiar with the building and the glass business plaintiff was willing to have him act as his arbitrator, and he then prepared data for the purpose of an arbitration which he submitted to defendant. On his counsel’s showing him a writing just received from defendant’s counsel, he was asked, “whether or not that is the notice you gave to them?” and answered, “It is.” Its admission in ■evidence was objected to as “a self-serving declaration” ■ and the objection sustained. Walbridge was asked '■on direct-examination if he ever received from plaintiff any request or demand for an arbitration, to which he answered, “There was something mentioned in a letter I received a long time ago. I have forgotten what it is, though.” On cross-examination he was asked and answered:

“Q.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wold Architects and Engineers v. Strat
713 N.W.2d 750 (Michigan Supreme Court, 2006)
Hetrick v. Friedman
602 N.W.2d 603 (Michigan Court of Appeals, 1999)
BRUCKER v. McKINLAY TRANSPORT, INC
557 N.W.2d 536 (Michigan Supreme Court, 1997)
Whitaker v. Seth E Giem & Associates, Inc
271 N.W.2d 296 (Michigan Court of Appeals, 1978)
F J Siller & Co. v. City of Hart
255 N.W.2d 347 (Michigan Supreme Court, 1977)
E. E. Tripp Excavating Contractor, Inc. v. Jackson County
230 N.W.2d 556 (Michigan Court of Appeals, 1975)
Stadel v. Granger Brothers, Inc.
144 N.W.2d 609 (Michigan Court of Appeals, 1966)
Ripley v. Lucas
255 N.W. 356 (Michigan Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
210 N.W. 488, 236 Mich. 425, 1926 Mich. LEXIS 860, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frolich-v-walbridge-aldinger-co-mich-1926.