E. E. Tripp Excavating Contractor, Inc. v. Jackson County

230 N.W.2d 556, 60 Mich. App. 221, 1975 Mich. App. LEXIS 1435
CourtMichigan Court of Appeals
DecidedApril 8, 1975
DocketDocket 19526
StatusPublished
Cited by35 cases

This text of 230 N.W.2d 556 (E. E. Tripp Excavating Contractor, Inc. v. Jackson County) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. E. Tripp Excavating Contractor, Inc. v. Jackson County, 230 N.W.2d 556, 60 Mich. App. 221, 1975 Mich. App. LEXIS 1435 (Mich. Ct. App. 1975).

Opinion

*225 M. J. Kelly, J.

I

Facts

After competitive bidding, E. E. Tripp Excavating Contractor, Inc., Plaintiff-Appellant, was awarded the general contract for the construction of a sanitary sewer system in Blackman Township, Jackson County. The contract between plaintiff and the Jackson County Board of Public Works was in the amount of $1,330,958.24, and called for completion in one year.

The work was begun in November of 1971. In December, it was discovered that the subsoil conditions were unsatisfactory and that it would be necessary to reroute portions of the sewer. According to the contract, the project engineers Williams & Works were entitled to issue change orders and to adjust completion dates and compensation accordingly.

Attempts to negotiate price and completion date changes proved futile. Tripp claims that the county, through its engineers acting arbitrarily, refused to negotiate in good faith. The county claims that Tripp refused to proceed with certain work contrary to the contract. At any rate, cooperation between the project engineers and the general contractor dissolved in acrimony. On February 14, 1972 the project engineer notified Tripp that if it felt aggrieved it should resort to the arbitration remedy provided by the contract. On March 21, 1972, Tripp filed a demand for arbitration with the American Arbitration Association alleging numerous breaches of contract and requesting relief. On April 3rd the county filed its answer to Tripp’s demand for arbitration, denied *226 wrong-doing and requested affirmative relief. Accompanying the answer and counterclaim was the county’s list of proposed arbitrators and a request for heating dates. Some time after April 3rd and befóte May 4th, three attempts were made to agree on qualified arbitrators. On May 4th defendant county indicated its consent to what eventually became the three-man arbitration panel consisting of one contractor, one attorney, and one architect. During all this time Tripp continued to work on the various other areas of the sanitary sewer System which were not in dispute over the rerouting.

On May 11th, after the final members of the arbitration panel had been selected in accordance with the AAA’s rules, the county notified Tripp and its Surety by letter that the county was terminating the contract pursuant to § 3.13 of the General Conditions of the contract and that the contract would therefore terminate ten days after the date of the notice. The county’s express justification for termination was that Tripp was in default. This letter stopped Tripp’s activity on the project. The arbitration process however continued.

On June 2nd the Detroit office of the American Arbitration Association confirmed the three-man panel by phone and solicited acceptable dates from the parties. An hiatus of 19 days was followed by a ietter from defendant-appellee’s attorney addressed to the Regional Director of the American Arbitration Association. That letter is set forth here in its entirety:

*227 "American Arbitration Association
Mr. Harry R. Payne II
Regional Director
Room 1035, Penobscot Building
Detroit, Michigan, 48226
"Re: Case Ño. 54 10 0011 72
E.E. TRIPP EXCAVATING CONTRACTOR, INC.
and
JACKSON COUNTY BOARD OF PUBLIC WORKS
"Dear Mr. Payne:
"On June 2, 1972, We Were contacted by your office and advised orally that a three-man Arbitration panel had been selected to hear the above caption case and an inquiry was made to an acceptable date for the Arbitration hearing.
"At that time, I advised your office that on or about May 12, 1972, Jacksori County Board of Public Works had issued a notice to E. E. Tripp Excavating Contractor, Inc. pursuant to the provisions of the construction contract advising the contractor of his default and of the coúnty’s intent to terminate the contract ten (10) days after issuance of the notice. I further indicated that in view of the issuance of the default and termination of the contract upon the expiration of the ten (10) day period, it was the position of the Jackson County Board of Public Works that the claimant, E. E. Tripp Excavating Contractor, Inc. were not entitled to proceed with the Arbitration and that as far as the Jackson County Board of Public Works was concerned, any further proceeding by the American Arbitration Association in the above caption case should be stayed.
"The purpose of this letter is to officially confirm the position of the Jackson County Board of Public Works. As previously indicated; it is the position of the Jackson County Board of Public Works that the claimant, E. E. Tripp Excavating Contractor, Inc. has no right to proceed with the Arbitration and that the American Arbitration Association should cease and desist from any further proceedings in this matter for the following reasons:
*228 "1. On May 12, 1972, the Jackson County Board of Public Works issued a notice of default to the contractor indicating its intention to terminate the contract ten (10) days after issuance of the notice of default because of the contractor’s breach of the terms and conditions thereof. The ten (10) day notice period has expired and at this time, the county considers the contract terminated. Having breached the contract, it is the county’s position that the contractor has no right to have Arbitration over the objection of the county at this time.
"2. In the Claimant’s Demand for Arbitration, the claimant alledged [sic] that the county had breached the contract. As previously indicated, the county’s answer to the Demand for Arbitration, it is the county’s position that the question of breach of contract is not a matter within the jurisdiction of the American Arbitration Association to decide, but rather a decision that is properly determined by court of proper jurisdiction. There is ample case authority to support the county’s position in this regard.
"3. It should be pointed out that even where an issue in dispute is subject to Arbitration pursuant to the provisions of the contract between the parties, under the provisions of Section 3.04 of the general conditions to the contract it is stated, 'The Contractor shall not delay the work because Arbitration proceedings are pending unless he shall have written permission from the engineer to do so and such delay shall not extend beyond the time when the Arbitrators shall have opportunity to determine whether the work shall continue to be suspended pending decision by the Arbitrator to such a dispute.’ The county wishes to point out that with regard to the items in dispute, the contractor has failed to proceed with the work in accordance with the provisions of Section 3.04.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wold Architects and Engineers v. Strat
713 N.W.2d 750 (Michigan Supreme Court, 2006)
City of Ferndale v. Florence Cement Co.
712 N.W.2d 522 (Michigan Court of Appeals, 2006)
Hetrick v. Friedman
602 N.W.2d 603 (Michigan Court of Appeals, 1999)
Michigan Municipal Liability & Property Pool v. Muskegon County Board
597 N.W.2d 187 (Michigan Court of Appeals, 1999)
Rembert v. Ryan’s Family Steak Houses, Inc
596 N.W.2d 208 (Michigan Court of Appeals, 1999)
Tellkamp v. Wolverine Mutual Insurance
556 N.W.2d 504 (Michigan Court of Appeals, 1996)
Beattie v. Autostyle Plastics, Inc
552 N.W.2d 181 (Michigan Court of Appeals, 1996)
Tony Andreski, Inc v. Ski Brule, Inc
475 N.W.2d 469 (Michigan Court of Appeals, 1991)
City of Atlanta v. Brinderson Corporation
799 F.2d 1541 (Eleventh Circuit, 1986)
Nemzin v. Sinai Hospital
372 N.W.2d 667 (Michigan Court of Appeals, 1985)
Redford Township v. Redford Township Civil Service Commission
356 N.W.2d 270 (Michigan Court of Appeals, 1984)
Northern Michigan Education Ass'n v. Board of Education
126 Mich. App. 781 (Michigan Court of Appeals, 1983)
Nmea v. Bd. of Educ., Cheboygan Area Schools
337 N.W.2d 923 (Michigan Court of Appeals, 1983)
Risman v. Granader
309 N.W.2d 562 (Michigan Court of Appeals, 1981)
Union Lake Associates, Inc. v. Commerce & Industry Insurance
280 N.W.2d 469 (Michigan Court of Appeals, 1979)
Lanzo Construction Co. v. City of Port Huron
276 N.W.2d 613 (Michigan Court of Appeals, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
230 N.W.2d 556, 60 Mich. App. 221, 1975 Mich. App. LEXIS 1435, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-e-tripp-excavating-contractor-inc-v-jackson-county-michctapp-1975.