Frickel v. Lancaster County

213 N.W. 826, 115 Neb. 506, 1927 Neb. LEXIS 66
CourtNebraska Supreme Court
DecidedApril 26, 1927
DocketNo. 24804
StatusPublished
Cited by20 cases

This text of 213 N.W. 826 (Frickel v. Lancaster County) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frickel v. Lancaster County, 213 N.W. 826, 115 Neb. 506, 1927 Neb. LEXIS 66 (Neb. 1927).

Opinions

Goss, C. J.

Plaintiff had a verdict and judgment against Lancaster county and Central Contractors for $12,000 for personal injuries. Both defendants appealed.

On July 26,1924, the county was constructing a state and federal-aid road on the state highway west of Lincoln between Emerald and the west county line. Central Contractors, a copartnership, was doing the work under a written contract in which the county and the state by its department of public works were the parties of the first part and the contractors were the parties of the second part. The evidence shows that the grading had been completed, at least at the place involved here, and the contractors were hauling and depositing the gravel in piles, as dumped by trucks, on the north side, or shoulder, of the graded portion in the usual manner ready to be spread mechanically over the rest of the grade. They had first begun at the east end of the project, and had dumped gravel on the grade [508]*508from the end of pavement to the railroad viaduct. Then they began at the west end on the Seward county line and were dumping the gravel eastward to meet the point where they had left off on the eastern section. There was thus a gap of a mile or more between the west end of gravel at the viaduct and the east end of gravel on the part of the project where the accident occurred. On the roadway at this point there was left ample space for vehicles proceeding with ordinary care to meet and pass going east and west. Before daylight on the morning of the day named, the plaintiff, aged 21, and her husband, aged 22, having a vacation of two weeks, started from Lincoln by motorcycle on a trip to a point 207 miles distant in Kansas to visit relatives. They left Lincoln on West 0 street. Plaintiff was in a side-car at the right of the motorcycle and her husband was operating the vehicle. When they had gone about nine miles, the car ran into the piles of gravel and overturned. In some way plaintiff’s hand was caught and injured and later two of her fingers were amputated.' There was evidence that she was in a comparatively early stage of pregnancy and suffered a miscarriage the next night after the accident. Evidence was admitted showing that eight weeks later she was operated on for appendicitis.

Numerous errors are assigned and argued by the county and by the contractors separately, many of them applicable alike to both defendants, but we do not find it desirable nor necessary to list them all. They have to do chiefly with instructions to the jury, and refusal to give instructions requested, and with alleged error in the admission of evidence.

The county complains because the court overruled its demurrer and because it refused both at the end of plaintiff’s evidence and at the end of all the evidence to instruct the jury to return a directed verdict in its favor. Section 2746, Comp. St. 1922, makes a county liable for any special damages happening to any person by means of insufficiency or want of repairs of a highway which the county is liable to keep in repair. Under section 8336 (the state highway [509]*509act) the county was required to maintain the road adequately, and under section 8342 it had authority to close temporarily to traffic any portion of the highway and give notice to the public by placing at the roadside signs stating that the road is closed to travel by order of the county board. The county is bound to use reasonable and ordinary care in maintaining and in repairing its highways. Its duty will not be extended by construction beyond the words and fail-implications of this statutory liability. However, the county contends that, since1 it entrusted the work of grading and graveling to skilled and experienced contractors selected with reasonable care and judgment, the county is not liable for the negligent acts of the contractors in failing to keep the road sufficiently in repair or to maintain sufficient barriers or warnings to protect those' allowed to use the highway while the work is going on. In Sharp v. Chicago, B. & Q. R. Co., 110 Neb. 34, this court, in a discussion and application of section 2746, held that a county cannot evade statutory liability for damages by the plea that the repair and upkeep of the highway had been delegated to another. The same principle was involved in Saltzgaber v. Morrill County, 111 Neb. 392, and in King v. Douglas County, 114 Neb. 477, and was decided adversely to the respective counties involved. We find nothing in the facts here to warrant a departure from the rule announced in those cases.

The defendant contractors also insist that they are exonerated from liability because the county had assumed, by arrangement between the defendants, the responsibility of spreading the gravel and that the duty of the contractors ended when the gravel was deposited. The written proposal which ripened into the written contract and by the latter was expressly referred to and made a part of the contract was for “56,300 square yards gravel surfacing, in place, 3 inches deep, 26 cents, $14,638.” The specifications which likewise were expressly made a part of the written contract contained provisions from which we excerpt: “The contractor shall provide and maintain proper guards, suitable [510]*510and efficient lights, and take all necessary precautions for the prevention of accidents;” and “The contractor shall assume all responsibility in the event of accidents, either personal injuries or property damage, sustained by persons or property due to the carrying on of his work.” Under the specifications made part of the contract, it was the engagement between the county and state and the contractors that the county should spread the gravel for the contractors and be paid by the contractors for that work the sum of one and a half cents per square yard. In this specification the parties agreed that the contract should be considered fulfilled and final acceptance should be given by the ■state within 15 days after the spreading of the gravel. So it appears, first, that the contractors’ duty did not end with the depositing of the gravel, and, second, that as to t) spreading of the gravel the county was acting for and paid by the contractors.

The defendants severally offer strong arguments why the case presented by plaintiff on the merits of the evidence should not have been submitted to the jury. While we might think that the general knowledge that roads in Nebraska are under repair in the summer-time, that the fact that plaintiff had already on the morning in question passed over a part of this very project, that if the lights on the motorcycle were reflecting as the law requires and she was not keeping a lookout as ordinary care would dictate, that one driving or riding in the darkness is more liable to meet disaster than in the daylight, and such things might induce us if we were jurors not to have found for plaintiff, yet that was the. province of the trial jury, as selected, and we cannot say that they should have been directed to return a verdict for the defendants or for either of them.

The defendants allege error as to several of the instructions given by the court, and because of the refusal to give instructions requested. The most serious complaint refers to the fifth instruction given by the court on its own mo[511]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parrish v. Omaha Public Power District
496 N.W.2d 902 (Nebraska Supreme Court, 1993)
Seward County Board of Commissioners v. City of Seward
242 N.W.2d 849 (Nebraska Supreme Court, 1976)
Stadler v. Curtis Gas, Inc.
151 N.W.2d 915 (Nebraska Supreme Court, 1967)
Olson v. County of Wayne
59 N.W.2d 400 (Nebraska Supreme Court, 1953)
Buresh v. George
31 N.W.2d 106 (Nebraska Supreme Court, 1948)
Dickenson v. County of Cheyenne
18 N.W.2d 559 (Nebraska Supreme Court, 1945)
Miller v. Abel Construction Co.
300 N.W. 405 (Nebraska Supreme Court, 1941)
Porter v. Lancaster County
266 N.W. 584 (Nebraska Supreme Court, 1936)
Fireman's Fund Insurance v. Leftwich
90 S.W.2d 497 (Supreme Court of Arkansas, 1936)
Franek v. Butler County
254 N.W. 489 (Nebraska Supreme Court, 1934)
Brooks v. Thayer County
254 N.W. 413 (Nebraska Supreme Court, 1934)
Cotten v. Stolley
248 N.W. 384 (Nebraska Supreme Court, 1933)
Benton v. State
247 N.W. 21 (Nebraska Supreme Court, 1933)
May Department Stores Co. v. Bell
61 F.2d 830 (Eighth Circuit, 1932)
Nichols v. Owens Motor Co.
236 N.W. 169 (Nebraska Supreme Court, 1931)
Sloan v. Harrington
223 N.W. 663 (Nebraska Supreme Court, 1929)
Roth v. Blomquist
220 N.W. 572 (Nebraska Supreme Court, 1928)
Boomer v. Lancaster County
218 N.W. 751 (Nebraska Supreme Court, 1928)
Pratt v. Western Bridge & Construction Co.
218 N.W. 397 (Nebraska Supreme Court, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
213 N.W. 826, 115 Neb. 506, 1927 Neb. LEXIS 66, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frickel-v-lancaster-county-neb-1927.