Frey v. Snyder

6 Pa. D. & C. 581, 1924 Pa. Dist. & Cnty. Dec. LEXIS 348
CourtPennsylvania Court of Common Pleas, Lehigh County
DecidedDecember 8, 1924
DocketNo. 44, M. L. D
StatusPublished

This text of 6 Pa. D. & C. 581 (Frey v. Snyder) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Lehigh County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frey v. Snyder, 6 Pa. D. & C. 581, 1924 Pa. Dist. & Cnty. Dec. LEXIS 348 (Pa. Super. Ct. 1924).

Opinion

Reno, P. J.,

Claimants entéred into a written contract with the contractor to furnish and install plumbing fixtures in the owners’ dwelling for $406.35. The contract specifies the kind, number and quality of the several fixtures to be installed in the house itself, as well as the connections to be made from them to the main pipes at the curb-line. After performing a part of the work required by the terms of the contract, that is, after installing what is called the “rough plumbing,” the claimants ceased work, alleging that the contractor had not made the payments called for by the contract. (It should be here stated that a time for payment does not appear in the contract.) Because of this cessation of work, claimants were not obliged to install certain fixtures called for by the contract. These fixtures, claimants aver, were worth $116. Accordingly, from the total amount of the contract ($406.35) there is deducted the value of the fixtures not furnished ($116), and the resultant ($290.35) is said to be the cost of the “rough plumbing” furnished for which the lien is filed. A credit of $150, representing a payment made by the contractor, is allowed and the net amount for which the lien is filed is $140.35. The sum of $290.35 must be taken to represent either labor or material, or both, actually furnished to owners’ building, and if the claim sets forth “the nature or kind of work done or the kind and amount of materials furnished, or both, and the time when the materials were furnished or the work done, or both, as the case may be” (Act of April 17, 1905, § 1, P. L. 172), the lien is sustainable.

To support the lien, claimants have attached an exhibit entitled “itemized statement of rough plumbing installed at . . . between Sept. 6, 1923, and Sept. 14, 1923.” Then follow forty-four separate items. Of these, forty state the quantity and kind of pipes, ells, plugs, lead, nipples, etc., but not stating the specific dates when they were installed nor the prices charged therefor. A typical item is: “85 feet, 4 inch X H Soil Pipe.” One item is for “Carfare, $6.92,” and three items are for labor, of which the following is typical: “Hess, plumber, 461 hours.”

This statement, the owners contend in support of their motion to strike off the lien, constitutes a lumping charge, and rely upon Burrows v. Carson, 244 Pa. 6. In that case, a sub-contractor for furnishing and erecting stairs in a dwelling-house averred that labor and material were furnished “between the dates of April 4, 1911, and Nov. 20, 1911,” and supported this by an itemized [582]*582statement showing the specific dates on which each item of material was installed, its nature and quantity and the price for each. He also claimed for labor, and this was set forth in one item as follows: “1911, April 4, to Nov. 20, 137 hours’ labor at 60 cents per hour, $82.20.” The claim also averred that “the work was done and the materials furnished under a contract consisting of a written bid submitted by claimant to contractor to furnish and erect the stairs in sixteen houses according to three sets of plans, designated as Nos. 1, 2 and 3, and the stairs in three single houses according to another set of plans, or nineteen houses in all, for the sum of $3750, and that the said bid was accepted by the contractor.” It did not appear that work had been done upon the other houses, and since the amount was greater than one-nineteenth of $3750, it could not be considered as an apportioned claim. No objection was made to the items for materials, but it was contended that the labor item was defective. The owner’s motion to strike out this item was overruled below. Upon appeal to the Superior Court, the judgment was reversed. (See 53 Pa. Superior Ct. 488.) Referring to this item, Judge Porter, speaking for the Superior Court, said: “This plaintiff was a subcontractor, as disclosed by his claim; he contracted, not with the owner, but with Rogers, the contractor. When, therefore, he filed his claim for work done upon this building, he was required to disclose the nature or kind of that work and when it was done. The claim states that the first materials were furnished on April 4th and the last item of materials was on Oct. 17th, and, as to the material, the exact date at which each item was furnished is stated in the claim. Now, stating when the work was done, it is said that it began on April 4th, the day when the first materials were furnished, and it was not completed until Nov. 20th, more than a month after the last materials were furnished. This covered a period of seven months and a-half, and yet the work was done in 137 hours of actual time. This would give less than an hour of time for each working day, and it is manifest that the work was not continuous. No one man was employed in this work from April 4th to Nov. 20th, nor any considerable portion of that time. This claim simply indicates that 137 hours of work were put upon the building, or in the preparation of materials to go into the building, sometime between April 4th and Nov. 20, 1911, but it absolutely fails to sufficiently indicate at what time during that period the work was done. The claim also fails to indicate the nature of the work, whether it was done in preparation of the materials at the shop of the plaintiff, or in incorporating them into the building, by carpenters, cabinet-makers, assistants or laborers. The objection of the appellant is that this is a lumping charge, and the objection seems to be well taken: Chapman v. Faith, 18 Pa. Superior Ct. 578. If this item of the claim be sustained, it extended the time within which the plaintiff might have filed his lien by more than a month, for the limit claimed for the work was Nov. 20th, yet the claim does not mention a specific day upon which any work was done. This case bears a striking similarity to McFarland v. Schultz, 168 Pa. 634, the claim in which was for work and labor done, to wit, ‘grading and digging lots and carting away dirt from the same. . . . The said work and labor having been done and performed for and about the erection and construction of the said building between Aug. 29, 1892, and Oct. 22, 1892.’ The Supreme Court said in that case with regard to this statement of the claim: ‘It did not adequately set forth the nature and kind of the work done nor when it was done. The claimant was a sub-contractor and bound to strict compliance with the provisions of the statute on which he relied for his lien.’ The statement in that case was that the work had been done between certain dates, and it was held [583]*583that this was not a sufficient statement of when it was done. The statement in the present case is that the work was done between certain dates, and we have here the additional element that it appears from the face of the claim that the labor was not continuous.”

Upon appeal to the Supreme Court, the judgment of the Superior Court was affirmed, and from the opinion there rendered we extract the following: “The claim as filed shows that the material and labor ‘substantially consisted of furnishing and erecting stairs in said house,’ and that they ‘were furnished between the dates of April 4, 1911, and Nov. 20, 1911.’ This was not a compliance with the statutory requirement as to the nature or kind of work or when it was done. The items of materials and the dates when they were furnished are stated in the claim, but, as suggested by the Superior Court, it fails to show the nature of the work, whether it was done in preparation of the materials at the shop of the plaintiff, or in incorporating them into the building by carpenters, cabinet-makers, assistants or laborers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McFarland v. Schultz
32 A. 94 (Supreme Court of Pennsylvania, 1895)
American Car & Foundry Co. v. Alexandria Water Co.
64 A. 683 (Supreme Court of Pennsylvania, 1906)
Willson v. Canevin
75 A. 666 (Supreme Court of Pennsylvania, 1910)
Burrows v. Carson
90 A. 549 (Supreme Court of Pennsylvania, 1914)
Ott v. DuPlan Silk Corp.
114 A. 630 (Supreme Court of Pennsylvania, 1921)
Chapman v. Faith
18 Pa. Super. 578 (Superior Court of Pennsylvania, 1902)
Burrows v. Carson
53 Pa. Super. 488 (Superior Court of Pennsylvania, 1913)
Brant v. Hartrick
60 Pa. Super. 507 (Superior Court of Pennsylvania, 1915)
Bennett Lumber & Manufacturing Co. v. Hartrick
61 Pa. Super. 456 (Superior Court of Pennsylvania, 1915)
Benton v. David Berg Distilling Co.
63 Pa. Super. 412 (Superior Court of Pennsylvania, 1916)
Barker Painting Co. v. General Carbonic Co.
78 Pa. Super. 493 (Superior Court of Pennsylvania, 1922)
A. G. Breitwieser Lumber Co. v. Wyss-Thalman
51 Pa. Super. 83 (Superior Court of Pennsylvania, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
6 Pa. D. & C. 581, 1924 Pa. Dist. & Cnty. Dec. LEXIS 348, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frey-v-snyder-pactcompllehigh-1924.