Frees & Laine v. C. W. Vollmer & Co.

78 So. 2d 187, 1955 La. App. LEXIS 644
CourtLouisiana Court of Appeal
DecidedJanuary 31, 1955
DocketNo. 20384
StatusPublished
Cited by6 cases

This text of 78 So. 2d 187 (Frees & Laine v. C. W. Vollmer & Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frees & Laine v. C. W. Vollmer & Co., 78 So. 2d 187, 1955 La. App. LEXIS 644 (La. Ct. App. 1955).

Opinion

McBRIDE, Judge.

Plaintiff, a partnership, filed this suit seeking to recover from defendant thé bal-[188]*188anee due on a contract between the parties under which the plaintiff undertook to perform certain work as subcontractor on a levee construction job on which defendant was the principal contractor. The petition alleges that the contract between plaintiff and defendant was evidenced by a written instrument dated December 15, 1952; that plaintiff performed all work in accordance with the provisions of the said subcontract and is entitled to recover $2,115.97, being the difference between the contract price of $5,018.40 and $2,902.43, the amount paid on account by defendant.

Defendant alleges that the subcontract was verbally made and further alleges that the written instrument declared on by plaintiff was only a memorandum of the agreement not constituting the entire contract, and in addition to the terms mentioned therein, plaintiff agreed to complete its subcontract in fifty calendar days, subject to all of the terms and conditions of the principal contract between defendant and the Board of Levee Commissioners of the Orleans Levee District and particularly with reference to the demurrage clauses of said principal contract. Defendant then set forth that the subcontract was not completed within fifty calendar days, but, on the contrary, through the fault of plaintiff the work which plaintiff had undertaken was not finished until ninety-nine calendar days, and as a result defendant was charged de-murrage by the Board of Levee Commissioners on the principal contract at the rate of $25 per day for forty-nine days or $1,225, which amount it is entitled to charge to plaintiff. Defendant claimed by way of set-off the following items:

1. Fuel and supplies furnished for plaintiff’s use $238.35
2. Damages to power line paid for by defendant 76.76
3. Labor and materials for construction of mats used by plaintiff 313.05
4. Labor to repair slides 262.81
$890.97 Total

Defendant claimed all of the above including the demurrage totaling $2,115.97 made up the difference between the contract price and the amount paid plaintiff and-prayed for the dismissal of plaintiff’s suit.

In the alternative, defendant assumed the position of plaintiff in reconvention and claimed damages for plaintiff’s failure to timely perform its contract as follows:

Demurrage as outlined above $1,225.00-Wages of foreman kept on job for demurrage period 735.00
Social Security, etc. on foreman’s wages 75.95
$2,035.95

It itemized its claim in the alternative as follows:

Gross balance' due plaintiff on contract $2,115.97
Less items 1, 2, 3 and 4 described above 890.97
Net balance due plaintiff on contract $1,225.00
Damages due defendant by plaintiff 2,035.95
Net balance due defendant $ 810.95

The district judge after hearing the evidence rendered judgment in favor of plaintiff for the sum of $1,225 on the main demand, and also rendered judgment in favor of defendant and against plaintiff for the sum of $2,035.95, which in effect granted the defendant a net recovery of $810.95 in accordance with the alternative prayer of the reconventional demand. Plaintiff has appealed.

At the trial below plaintiff conceded the correctness of items 1, 2 and 3 and with respect to the claimed offset the items in dispute are the claim for demurrage and the labor to repair slides.

We are told a “slide” occurs when the dirt after being put in place on the levee by the dragline fails to hold its position and [189]*189slides off the fill. There were two slides, one at the upper end when the work was first started by plaintiff and a smaller and subsequent one at the lower end. The testimony of Theriot, an employee of plaintiff, is that these slides occurred because the earth was too wet when it was put in place. Theriot states that notwithstanding that fact, Coomer, defendant’s superintendent, instructed him to put the dirt in place so that Coomer could later put it up with a bulldozer.

In the agreement no mention whatever was made of slides and we are at a loss to know under what theory plaintiff endeavors to escape the charge made by defendant for labor to remedy them. The subcontract called for putting the mud in place, and if it fell by virtue of its wetness and not because of the fault of defendant, we fail to see how any valid defense can be made to defendant’s claim, the amount of which has been adequately proven.

The defendant before submitting a bid for the contract invited plaintiff to participate in the job by subcontracting for the placement of the earth on the levee. An inspection of the site was made by McSween, plaintiff’s representative, who also examined the plans and specifications issued by the Levee Board. McSween orally agreed with defendant’s representative, Wills, that if defendant was awarded the contract, plaintiff would undertake the placing the earth on the levee in accordance with the plans and specifications at 18^ per cubic yard, the job to be completed in fifty calendar days. This agreement was reached on November 23, 1952, and no mention seems to have been made of the subsequent placing the agreement in writing.

The oral agreement thus made between the representatives of the parties was one of the predicates upon which defendant made its bid to the Levee Board for the principal contract. A time limit for performance of fifty days was stipulated in the principal contract, defendant agreeing that if it did not complete the entire work within that time, it would be obligated to pay to the Levee Board liquidated damages in the sum of $25 for each day’s delay.

Defendant upon its bid being accepted by the Levee Board so notified plaintiff which began operations on the subcontract on December 17, 1952.

The major contention of appellant is that the rights and obligations of the respective parties flow not from the , verbal contract between McSween and Wills but from a written contract which must control in this suit. Plaintiff’s counsel point out that the written agreement is silent as to any particular period of time in which plaintiff was obligated to complete the work undertaken under its subcontract, and the argument is then made that any and all testimony received by the trial judg'e touching on the matter of a time element was inadmissible and should be disregarded.

The document which plaintiff maintains constituted the written contract is in the form of a letter dated December 15, 1952, addressed to Ross Wills, C. W. Vollmer & Co., signed by Frees & Laine, E. L. Frees, Partner, the body of which reads thus:

“This will confirm our conversation agreeing on your job, with New Orleans Levee Board.
“We agree to furnish all men, machines and material necessary to raise the levee to required cross section and elevation. We will be compensated for this at the agreed price of $.18 per cubic yard. Measurement will be determined by estimate at Levee Board.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bowes v. Fox-Stanley Photo Products, Inc.
379 So. 2d 844 (Louisiana Court of Appeal, 1980)
Papania v. Aetna Casualty & Surety Company
291 So. 2d 908 (Louisiana Court of Appeal, 1974)
Bewley Furniture Co., Inc. v. Maryland Casualty Co.
285 So. 2d 216 (Supreme Court of Louisiana, 1973)
Menge Pump & Machinery Co. v. A. F. Blair Co.
270 So. 2d 320 (Louisiana Court of Appeal, 1972)
Irby Steel v. W. R. Fairchild Construction Co.
270 So. 2d 233 (Louisiana Court of Appeal, 1972)
Bart Construction Co. v. Bailey
125 So. 2d 51 (Louisiana Court of Appeal, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
78 So. 2d 187, 1955 La. App. LEXIS 644, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frees-laine-v-c-w-vollmer-co-lactapp-1955.