Bart Construction Co. v. Bailey

125 So. 2d 51, 1960 La. App. LEXIS 1241
CourtLouisiana Court of Appeal
DecidedNovember 15, 1960
DocketNo. 5112
StatusPublished

This text of 125 So. 2d 51 (Bart Construction Co. v. Bailey) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bart Construction Co. v. Bailey, 125 So. 2d 51, 1960 La. App. LEXIS 1241 (La. Ct. App. 1960).

Opinions

LANDRY, Judge.

Plaintiff, Bart Construction Company, Inc., prime contractor for the construction of a residence for one Edwin Newchurch, Baton Rouge, Louisiana, instituted this action against defendant W. L. Bailey, subcontractor, for the alleged breach of Bailey’s sub-contract to perform all carpenter work required in the completion of the Newchurch home. Plaintiff seeks to recover the cost of completing the work undertaken by defendant after defendant’s alleged abandonment of the project without cause.

The trial court adjudged defendant to be in default and rendered judgment in favor of plaintiff in the sum of $2,144.57, which was found to be the cost of completing the work called for in defendant’s contract. From said adverse judgment, defendant has appealed.

The contract between plaintiff and defendant (a copy of which appears in the record) provides that in consideration of the payment by plaintiff of the sum of $4,200, defendant undertook to perform the work therein specified (being all carpenter work required in the construction of the Newchurch home) within 90 days of the contract date of February 10, 1955. On or about March 31, 1955 (the project then being 30% to 45% complete) all construction thereon was stopped by the supervising architect for alleged defective workmanship and imperfections set forth in a letter from the architect to plaintiff contractor bearing date of March 31, 1955. The letter in question (the original of which appears in the record) lists numerous items which the architect demanded be corrected prior to resumption of further work. Several of the items in question related to carpenter work performed by defendant including, inter alia, straightening of all fascia boards, straightening bowed studs, replacement of defective wood molding covering screen vents, leveling living room windows, correcting fire stops to make them set flush with wall studs and flattening soffits around the carport.

The first issue to be resolved is' the liability vel non of defendant for the cost of completing the work undertaken.

In this connection, plaintiff relies upon the terms of LSA-C.C. art. 2769 which provides that the undertaker who fails to perform work he has contracted to do, or who neglects to execute the work in the manner and at the time agreed to, is liable in damages for losses ensuing from such breach or nonperformance. Defendant maintains the defects listed by the architect were due to inferior material and not substandard craftsmanship. In addition, defendant contends he was justified in leaving the job because plaintiff failed to keep him supplied with sufficient material with which to work. Finally, defendant Bailey avers he did not leave or abandon the job as alleged by plaintiff but that work was halted by the architect Hughes because the plumbing sub-contractor had cut from 12 to 20 studs in the kitchen wall in the process of roughing in the plumbing.

We believe the evidence supports the conclusion of the learned trial judge who found that defendant did, in fact, leave without legitimate cause. On this important issue, Mr. Kreppein, a construction superintendent for plaintiff, testified the studs in the kitchen wall were cut by the plumber subsequent to defendant’s leaving the job. The evidence further shows the architect on the job was most exacting and demanded superior workmanship throughout the entire project. The architect’s letter of March 31, 1955, stopping all progress of the work until correction was made of the defects listed therein, does not mention defective studs in the kitchen wall, an item so obvious it could hardly have been overlooked by an architect as particular as Hughes proved to be. In addition, Hughes’ letter expressly states that all of the defects required to be corrected appeared to [54]*54be due to poor workmanship and inability to read or interpret plans and specifications. Moreover, in testifying at the trial, Hughes stated the matter of the kitchen studs did not come to his attention until after he had written his letter of March 31, 1955.

Defendant’s claim that the defects alluded to by the architect were due to inferior material and not inferior carpenter work is not sustained by the evidence of record. As previously mentioned, the architect’s letter, as well as his testimony during the trial, clearly demonstrates that the matters about which he complained were the result of inferior carpentry and not poor or improper material. To cite one example given by the architect, he testified the roof sagged and the fascia boards were “wavy” and uneven because the rafters had been improperly cut or notched and were unevenly seated, a condition which could only be corrected by leveling each rafter individually. In this regard, Hughes’ testimony is corroborated by that of plaintiff’s foreman Kreppein to the effect the bowed .studs resulted from defendant’s failure to properly brace the wall studs before superimposing the roof thereon. It is significant to note that throughout his testimony, Kreppein referred to the fact that the architect Hughes was most particular and exacting and would accept nothing less than perfection. He also stated that some of the work rejected by the architect would have been acceptable to him and that in an effort to help defendant he had, in fact, approved some of the work subsequently rejected by Hughes. Defendant’s claim he was not provided with sufficient material to keep the job in progress is not substantiated in the record. Kreppein’s testimony is to the effect there was no shortage of material and that if there had been it would have been defendant’s own fault since all defendant had to do was to make known at the end of each day the materials he needed and Kreppein would have ordered it delivered on the job the next morning. Although there is testimony contradictory to that of Kreppein on the matter of availability of material, the trial court resolved this issue adversely to defendant and we find no manifest error therein. Moreover, we are convinced defendant deserted the project with no intention of returning. We are further convinced the record justifies the conclusion defendant left because of the exactitude of the architect, hardly a legitimate cause for defendant to decline performance of his agreement. The evidence also shows Krep-pein requested Bailey to return to the job but Bailey refused on the ground he had undertaken construction of two additional houses which projects he could not leave' for a period of approximately 10 days and also because of his inability to employ other carpenters for the Newchurch job.

Defendant having defaulted on his contract is therefore liable for the cost of correcting the defective workmanship for which he was responsible as well as completing the terms of the .agreement. Pelican Signs, Inc. v. D’Aquin, La.App. Orl., 107 So.2d 722; Spicuzza v. Ranzino, La.App. Orl., 73 So.2d 208; Home Services v. Marvin, La.App. Orl., 37 So.2d 413; LSA-Civil Code, Article 2769.

Learned counsel for defendant complains of the action of the trial court in permitting recovery for wages for unskilled laborers employed by plaintiff after defendant left the work. The record indicates that plaintiff did, in fact, employ unskilled labor to remove some of the defective work, which laborers were paid wages less than skilled carpenters. Piad plaintiff employed expert carpenters to tear out the defective workmanship, the cost to defendant would undoubtedly have been greater and defendant may not be heard to complain of measures taken by plaintiff and redounding to defendant’s benefit

The paramount issue to be resolved herein is whether defendant Bailey should [55]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spicuzza v. Ranzino
73 So. 2d 208 (Louisiana Court of Appeal, 1954)
Home Services v. Marvin
37 So. 2d 413 (Louisiana Court of Appeal, 1948)
Pelican Signs, Inc. v. L.A. D'Aguin
107 So. 2d 722 (Louisiana Court of Appeal, 1958)
Frees & Laine v. C. W. Vollmer & Co.
78 So. 2d 187 (Louisiana Court of Appeal, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
125 So. 2d 51, 1960 La. App. LEXIS 1241, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bart-construction-co-v-bailey-lactapp-1960.