Freedom Roofing, Windows & Siding, L.L.C. v. Jomaa
Opinion
IN THE COURT OF APPEALS OF OHIO SIXTH APPELLATE DISTRICT
SANDUSKY COUNTY
Freedom Roofing, Windows & Siding, Court of Appeals No. S-25-044 LLC
Appellee Trial Court No. 25 CV 654 v.
Kaleb Jomaa, et al. DECISION AND JUDGMENT Appellant Decided: August 25, 2026
*****
Andrew R. Mayle, Richard R. Gillum, Benjamin G. Padanilam, and Nichole K. Papageorgiou, for appellee.
Peter A. Dewhirst, and Lacey Riley, for appellant.
*****
SULEK, J.
{¶ 1} Appellant, Kaleb Jomaa, appeals a judgment of the Sandusky County Court of Common Pleas granting appellee, Freedom Roofing, Windows & Siding, LLC’s motion for a preliminary injunction enjoining him from breaching the noncompete agreement entered into between the parties. Because the judgment granting the preliminary injunction is not a final appealable order, the appeal is dismissed.
I. Facts and Procedural History
{¶ 2} In October 2023, Freedom, a residential and commercial roofing, windows, and siding company, hired Jomaa as a project estimator. In February 2024, Freedom promoted Jomaa to Director of Sales. That Fall, looking to expand to other geographic locations Freedom’s Expansion Committee discussed implementing a noncompete agreement for top level management, including Jomaa. Jomaa was a member of the Expansion Committee and was present during discussions involving the time restriction and geographic radius of the noncompete. On October 21, 2024, Jomaa signed the agreement, which stated that its purpose was to “protect the Company’s legitimate business interests and confidential information.” The agreement precluded Jomaa from post-employment competition with Freedom for a period of nine months and within “50 miles of any operating Freedom Roofing, Windows, and Siding location[.]”
{¶ 3} In February 2025, Jomaa requested unpaid leave due to “heightened anxiety.” Returning to work after 30 days, Freedom assigned him the job title of Branch Sales Manager. The job had fewer responsibilities, though his compensation and bonus potential remained unchanged. Jomaa resigned on March 17, 2025.
{¶ 4} Approximately two weeks following his resignation, Salinas Construction and Repairs, LLC employed Jomaa in a sales position. It is undisputed that Salinas is a direct competitor of Freedom and their operations are within 50 miles of each other.
{¶ 5} Following unsuccessful cease and desist letters, on July 15, 2025, Freedom commenced this action against Jomaa, Salinas Construction, and Salinas’ “founder and proprietor” Kevin Salinas raising two claims. Against Jomaa, Freedom alleged that he breached the noncompete agreement and as to Salinas Construction and Salinas, that they tortiously interfered with the noncompete agreement by willfully ignoring its terms. Freedom requested that the trial court enjoin Jomaa from breaching the noncompete terms for nine months, minus the time between his resignation and employment with Salinas. As to Salinas Construction and Salinas, Freedom requested they be enjoined from employing Jomaa.
{¶ 6} Jomaa filed an answer and raised the counterclaims of hostile work environment and constructive discharge. In essence, Jomaa attributed his anxiety and panic disorder diagnoses to the working conditions at Freedom and claimed that he had to resign to protect his mental health. Salinas Construction and Salinas filed a separate answer generally denying the claims.
{¶ 7} Freedom moved to dismiss Jomaa’s counterclaim under Civ.R. 12(B)(6), contending that his hostile work environment claim was insufficient because he failed to allege that he was part of a protected class and that constructive discharge is not an independent cause of action. Opposing the motion, Jomaa argued that Freedom discriminated against him based on his mental health status and that he asserted his constructive discharge claim in conjunction with the hostile work environment claim. He requested leave to amend his counterclaim to set forth his protected class status.
{¶ 8} Freedom also moved for a preliminary injunction requesting that the court enforce the terms of the noncompete during the pendency of the case. Jomaa opposed the motion and the court held a hearing on October 6, 8, and 30, with the parties submitting post-hearing memoranda. On November 20, 2025, the trial court granted the preliminary injunction noting that “the terms of the non-compete provisions [are] reasonable in scope, duration, and geographical limitation” and ordered that “[b]ased on the continuous nature of the violation of the non-compete the duration shall commence upon the issuance of this Order.”
{¶ 9} This appeal followed.
II. Assignments of Error
{¶ 10} Jomaa raises three assignments of error on appeal:
I. The trial court committed reversible error when it granted Plaintiff/Appellee’s Motion for a Preliminary Injunction.
II. The trial court committed reversible error when it failed to meet the specificity requirements of Civ.R. 65(D) in its November 20, 2025, Decision, Judgment Entry.
III. The trial court committed reversible error when [it] did not require any security in its November 20, 2025, Decision, Judgment Entry.
III. Analysis
{¶ 11} Jomaa’s assignments of error relate to the trial court’s order granting Freedom’s motion for a preliminary inunction pending final determination on the merits of the appeal. Freedom first contends, however, that the appeal should be dismissed because the order was not final and appealable. We agree.
{¶ 12} Under Section 3(B)(2), Article IV of the Ohio Constitution, a trial court’s judgment can be immediately reviewed by an appellate court only if it constitutes a “final order” in the action. Taxiputinbay, LLC v. Put-in-Bay, 2021-Ohio-191, ¶ 7 (6th Dist.), citing Deyerle v. City of Perrysburg, 2004-Ohio-4273 (6th Dist.), ¶ 3. If, however, a trial court’s order is not final, then an appellate court does not have jurisdiction to review the matter, and the matter must be dismissed. Id., citing Gen. Acc. Ins. Co. v. Ins. Co. of N. Am., 44 Ohio St.3d 17, 20 (1989).
{¶ 13} A preliminary injunction is considered a provisional remedy, R.C.
2505.02(A)(3), and is generally not appealable unless it meets the following criteria under R.C. 2505.02(B)(4):
(B) An order is a final order that may be reviewed, affirmed, modified, or reversed, with or without retrial, when it is one of the following:
...
(4) An order that grants or denies a provisional remedy and to which both of the following apply:
(a) The order in effect determines the action with respect to the provisional remedy and prevents a judgment in the action in favor of the appealing party with respect to the provisional remedy.
(b) The appealing party would not be afforded a meaningful or effective remedy by an appeal following final judgment as to all proceedings, issues, claims, and parties in the action.
See Doe v. Columbus, 2026-Ohio-1095, ¶ 11-12.
{¶ 14} Under the first prong, R.C. 2505.02(B)(4)(a), an appealing party must show that “there was no further opportunity to petition the court for the remedy being sought, and there existed nothing further for the trial court to decide with respect to the provisional remedy.” (Cleaned up.) Id. at ¶ 14. The preliminary injunction granted in this case facially satisfies this prong as there is nothing further for the trial court to decide with respect to it. However, because Freedom claims that Jomaa continues to violate the terms of the noncompete, it is uncertain what additional actions may be taken by the trial court.
{¶ 15} Next, under R.C. 2505.02(B)(4)(b), an appealing party must also demonstrate that by waiting until a final judgment is issued as to all claims and parties, the party would be denied a meaningful or effective remedy. This requirement acknowledges that there are certain exceptions to the substantial interest in avoiding piecemeal litigation. Burnham v. Cleveland Clinic, 2016-Ohio-8000, ¶ 22.
Free access — add to your briefcase to read the full text and ask questions with AI
Freedom Roofing, Windows & Siding, L.L.C. v. Jomaa (Freedom Roofing, Windows & Siding, L.L.C. v. Jomaa) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.