Frank T. Wike v. Grandview Solar Project LLC

CourtIndiana Supreme Court
DecidedJune 24, 2026
Docket26S-PL-00192
StatusPublished
AuthorJustice Massa

This text of Frank T. Wike v. Grandview Solar Project LLC (Frank T. Wike v. Grandview Solar Project LLC) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frank T. Wike v. Grandview Solar Project LLC, (Ind. 2026).

Opinion

Pursuant to Indiana Appellate Rule 65(E), the trial court and parties shall not take any action in reliance upon this opinion until it is certified.

IN THE

Indiana Supreme Court Supreme Court Case No. 26S-PL-192 FILED Franklin T. Wike, et al., Jun 24 2026, 11:03 am

CLERK Appellants Indiana Supreme Court Court of Appeals and Tax Court

–v–

Grandview Solar Project, LLC; Town of Grandview, Indiana Board of Zoning Appeals; Town of Grandview, Indiana Town Council; and Town of Grandview, Indiana Zoning Administrator, Appellees

Argued: October 30, 2025 | Decided: June 24, 2026

Appeal from the Spencer Circuit Court No. 74C01-2402-PL-55

The Honorable Nathan A. Verkamp, Special Judge

On Petition to Transfer from the Indiana Court of Appeals Case No. 24A-PL-1867

Opinion by Justice Massa Justices Slaughter and Molter concur. Justice Goff dissents with separate opinion, in which Chief Justice Rush joins.

Indiana Supreme Court | Case No. 26S-PL-192 | June 24, 2026 Page 2 of 22 Massa, Justice.

Normally, challenges to a board of zoning appeals’ decision need to be brought within 30 days of the decision. But Indiana recognizes the ultra vires doctrine, which, applied here, says some board of zoning appeals’ actions might be void, meaning vulnerable to a lawsuit at any time, even long after the normal window for review has closed. This case causes us to ask: which board of zoning appeals’ actions are void, and which are merely voidable and subject to the window closing?

Here, the Town of Grandview issued a special exception approval to a developer planning a large commercial solar project. Wike and seventy- eight others (“Landowners”) who own or live in the area adjacent to the proposed project filed a lawsuit challenging the Town’s awarding of the approval, which covered land in the two-mile fringe directly outside the Town’s corporate limits. Although the Town could have provided for extraterritorial jurisdiction in its comprehensive plan and local ordinance, it failed to do so before issuing the special exception approval.

Landowners argue that that failure makes the special exception approval void. Meanwhile, the Town and the solar project argue that failure to follow statutory pre-requisites made the decision merely voidable, and Landowners waived their objection by failing to bring it within 30 days. We agree with the Town and project owners. In doing so, we take stock of our precedents surrounding ultra vires zoning board decisions and ultimately affirm the trial court.

Indiana Supreme Court | Case No. 26S-PL-192 | June 24, 2026 Page 3 of 22 Facts and Procedural History Grandview Solar Project, LLC sought to develop a large solar farm in Spencer County, Indiana. Part of the solar farm would be within the Town of Grandview, part within the Town’s two-mile fringe, and part beyond the two-mile fringe in the County. 1

Typically, a town can extend its zoning authority into the two-mile fringe by following certain requirements, including allowing for extraterritorial jurisdiction (ETJ) in its comprehensive plan. Ind. Code § 36-7-4-205(d)-(e). However, here the Town had a comprehensive plan establishing development objectives and land use guidelines; it only applies to “all territory located within the corporate limits of the Town.” Joint Appellees’ App. Vol. II. at 90. The Town’s zoning ordinance has regulations “in accordance with [the] comprehensive master plan.” Id. at 96. The ordinance defines jurisdiction as “the incorporated area of the Town of Grandview.” Id. at 102.

Grandview Solar first approached the County for zoning approval in the ETJ, but following advice from the County, Grandview Solar went to the Town for approval. 2 The Town and the County confirmed the Town (1) had an ETJ and (2) was the right entity to decide zoning matters within the ETJ. 3 In November 2019, Grandview Solar applied to the Town Board of Zoning Authority for a special exception approval. After public

1Unless otherwise specified, “the Town” refers to any official representative, entity, or administrative body of the Town of Grandview, including the Board of Zoning Appeals. The County refers to any official representative, entity, or administrative body of Spencer County. 2The solar project was previously owned by a different entity, and it was that owner who approached the County. For simplicity, we refer to the owner of the solar project as Grandview Solar throughout these events. 3In November of 2019, one of Grandview Solar’s attorneys followed up with Spencer County’s Plan Commission Administrator: “As you may recall, we’re working with the Town of Grandview regarding a BZA approval procedure (special exception) for a solar project within their 2-mile fringe boundary. However, do you know if your office would be responsible for any permitting [. . .] assuming the zoning approval is granted?” Joint Appellees’ App. Vol. II at 76. And in response, the County said “Since it is in Grandview’s buffer zone they would issue the Improvement Location Permits.” Id.

Indiana Supreme Court | Case No. 26S-PL-192 | June 24, 2026 Page 4 of 22 hearing, the Town unanimously approved the special exception approval, which authorized construction of the solar farm within the two-mile fringe. At the public hearing, Grandview Solar had presented information on the impact of the solar project; including that its “solar energy would be used to help power the Town of Grandview, with Grandview netting approximately $1,000,000 in tax revenue over the life of the project.” Id. at 34. 4 No one objected during the 30-day review period or for the next several years. Special exception approval in hand, the development moved forward.

In 2020, Grandview Solar applied to the County for a contingent use permit for parcels located within the County. After confirming this area was outside the Town’s two-mile fringe (and therefore, Town authority) the County granted the permit. At that point, Grandview Solar had obtained its critical, discretionary zoning approvals. The only remaining zoning permits it needed were non-discretionary approvals such as building permits and improvement location permits.

In 2022, the solar farm development was acquired by a new owner who purchased it for millions of dollars. Prior to purchase, the attorney representing both the Town and the County confirmed the Town’s ETJ authority and the validity of the two zoning approvals. Also in 2022, the Town and the County once again confirmed “Grandview Solar has all local zoning approvals that are required from the Town of Grandview and from Spencer County, and Grandview Solar is authorized to commence with the [improvement location permit], building permit or other construction-related permit application process.” Appellants’ App. Vol. II at 74. In the three years since the Town had issued the special exception approval, Grandview Solar says it spent approximately 30 million dollars developing the project.

4Extensive information was provided about the environmental impact of the solar project, including that, at the end of the “Project’s useful life,” the land would be restored to its current use and continue to function as agricultural, that the solar project would provide landowners with stable land payments, as well as a plan for soil preservation and rehabilitation. Joint Appellees’ App. Vol. II at 36-39.

Indiana Supreme Court | Case No. 26S-PL-192 | June 24, 2026 Page 5 of 22 In June 2023, Grandview Solar applied to the Town for an improvement location permit so it could begin construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Metropolitan Development Commission v. Hair
505 N.E.2d 116 (Indiana Court of Appeals, 1987)
Georgetown Board of Zoning Appeals v. Keele
743 N.E.2d 301 (Indiana Court of Appeals, 2001)
Robert Lynn Co. v. Town of Clarksville Board of Zoning Appeals
867 N.E.2d 660 (Indiana Court of Appeals, 2007)
Schlehuser v. City of Seymour
674 N.E.2d 1009 (Indiana Court of Appeals, 1996)
BOARD OF TRUSTEES, ETC. v. City of Fort Wayne
375 N.E.2d 1112 (Indiana Supreme Court, 1978)
Mishler v. County of Elkhart
544 N.E.2d 149 (Indiana Supreme Court, 1989)
Mies v. Steuben County Board of Zoning Appeals
970 N.E.2d 251 (Indiana Court of Appeals, 2012)
Kranz v. Meyers Subdivision Property Owners Ass'n
969 N.E.2d 1068 (Indiana Court of Appeals, 2012)
In re Complaint of Pilkington N. Am., Inc. (Slip Opinion)
2015 Ohio 4797 (Ohio Supreme Court, 2015)
Anderson Lumber & Supply Co. v. Fletcher
89 N.E.2d 449 (Indiana Supreme Court, 1950)
Fidelity Trust Co. v. Downing
68 N.E.2d 789 (Indiana Supreme Court, 1946)
Samuel W. Koonce v. Kim M. Finney
68 N.E.3d 1086 (Indiana Court of Appeals, 2017)
Elkhart County Board of Zoning Appeals v. Earthmovers, Inc.
631 N.E.2d 927 (Indiana Court of Appeals, 1994)
K.S. v. State
849 N.E.2d 538 (Indiana Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Frank T. Wike v. Grandview Solar Project LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frank-t-wike-v-grandview-solar-project-llc-ind-2026.