Frank Powell Lumber Co. v. Federal Insurance Co.

817 S.W.2d 648, 1991 Mo. App. LEXIS 1591, 1991 WL 210338
CourtMissouri Court of Appeals
DecidedOctober 21, 1991
Docket17298
StatusPublished
Cited by9 cases

This text of 817 S.W.2d 648 (Frank Powell Lumber Co. v. Federal Insurance Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frank Powell Lumber Co. v. Federal Insurance Co., 817 S.W.2d 648, 1991 Mo. App. LEXIS 1591, 1991 WL 210338 (Mo. Ct. App. 1991).

Opinions

PARRISH, Judge.

Appellant brought an action for damages on a surety bond issued by respondent. Appellant sought payment for the value of goods and merchandise sold and used in the construction of improvements on the property of First Methodist Church of Rol-la, Missouri (Owner). The contractor for the construction project was Brockmiller Construction, Inc. (Contractor). The goods and merchandise for which appellant seeks payment were sold to a subcontractor. The trial court found for respondent. This court affirms.

Contractor entered into an agreement with Owner to construct an addition to a building on Owner’s property. Pursuant to the terms of the agreement, Contractor provided a surety bond “to pay for labor, materials and equipment furnished for use in the performance of the Construction Contract.” The surety bond was issued by respondent.

The subcontractor that incurred the indebtedness for which appellant seeks recovery from respondent was J.B. McCarty Plumbing & Heating Co. (McCarty). The value of the goods and merchandise that were purchased by McCarty from appellant — $381.39—is uncontested. The last date on which the appellant sold materials to McCarty was November 22, 1988. Thereafter, McCarty refused to pay for the goods and merchandise it had purchased from appellant and filed for bankruptcy.

Appellant gave notice to Owner by letter dated February 10, 1989, of its claim against McCarty. In that letter, appellant stated, “It is my understanding that you will turn these invoices over to your attorney who will seek relief from Brockmiller Construction Co. under their performance bond.” Appellant’s attorney first notified Contractor’s attorney of appellant’s claim by letter dated March 1, 1989.

The terms and conditions of the surety bond that respondent issued, and upon which appellant seeks recovery, include:

4. The Surety shall have no obligation to Claimants under this bond until:
[[Image here]]
4.2 Claimants who do not have a direct contract with the Contractor:
.1 Have furnished written notice to the Contractor and sent a copy, or notice thereof, to the Owner, within 90 days after having last performed labor or last furnished materials or equipment included in the claim stating, with substantial accuracy, the amount of the claim and the name of the party to whom the materials were furnished or supplied or for whom the labor was done or performed; and
.2 Have either received a rejection in whole or in part from the Contractor, or not received within 30 days of furnishing the above notice any communication from the Contractor by which the Contractor has indicated the claim will be paid directly or indirectly; and
.3 Not having been paid within the above 30 days, have sent a written notice to the Surety (at the address described in Paragraph 12) and sent a copy, or notice thereof, to the Owner, stating that a claim is being made under this Bond and enclosing a copy of the previous written notice furnished to the Contractor.
5. If a notice required by Paragraph 4 is given by the Owner to the Contractor or to the Surety, that is sufficient compliance.

The date of the letter appellant sent to Owner, February 10, 1989, was within 90 [650]*650days next following November 22, 1988, the date of the last sale of goods and merchandise to McCarty. The date of the letter from appellant’s attorney to Contractor’s attorney, March 1, 1989, is more than 90 days after the last sale of goods and merchandise by appellant to McCarty.

Appellant presents one point on appeal. It is directed to the 90-day notice requirement in the surety bond. Appellant contends that the trial court erred in not finding that the requirement for a subcontractor to give a 90-day written notice to Contractor with a copy to Owner was void as violating public policy. Appellant claims that the notice provision “attempts to create a private statute of limitations,” and, therefore, that judgment should have been entered for appellant in the amount of appellant’s claim.

Appellant takes two approaches in its challenge to the enforceability of the notice requirement. One is directed to the purpose for having such a bond. The second is directed to the policy of this state as codified by § 431.030.1

Appellant argues that the “sole purpose” of a surety bond is to protect third-party beneficiaries. Appellant concludes, therefore, that:

A contractor or materialman may rely on a six month mechanic’s lien right, about which they are deemed to know, or a ten year statute of limitation for suit on account, about which they are also deemed to know, only to find all their rights destroyed because the owner secretly went and purchased a payment bond with a ninety day notice provision.

Appellant’s premise that “[t]he sole purpose of the Payment Bond is to protect third party beneficiaries” is not sound. Further, the fact that the type of debt appellant seeks to collect by this action is protected by mechanics’ and materialmen’s lien statutes is irrelevant. The fact that an owner obtained, secretly or otherwise, a payment bond with a 90-day notice provision does not destroy or in any way affect a contractor’s or materialman’s rights under the mechanics’ and materialmen’s lien statutes.2

Appellant mischaracterizes the purpose of the surety bond that was provided. Its purpose was to protect the owner of the property where the construction was performed. Any benefits that materialmen or other third-party beneficiaries received as a result of the surety bond were incidental and were available only in accordance with its terms. The purpose of a surety bond such as the one in this case was discussed in National Gypsum Co. v. Travelers Indemnity Co., 417 So.2d 254 (Fla.1982). The Florida court upheld a 90-day notice requirement (“within 90 days of the last delivery”) in a surety bond similar to this one. In upholding the notice requirement, the court stated, at l.c. 256, “Pavarini [the contractor] secured the bond for the benefit of the owner; protecting materialmen, such as National Gypsum, was not the main purpose.”

The Supreme Court of this state has also alluded to the incidental nature of a third-party beneficiary’s rights arising- from a surety bond. In La Salle Iron Works, Inc. v. Largen, 410 S.W.2d 87 (Mo. banc 1966), a material supplier sought recovery against both the principal contractor and his surety for the value of material furnished in the building of a church school. The court discussed the effect that express terms of a surety bond had on the third-party beneficiary. At l.c. 91, quoting from Corbin on [651]*651Contracts, Vol. 4, Ch. 43, § 798, pp. 163-164, the court stated:

“ * * * the third party has an enforceable right if the surety promises in the bond, either in express words or by reasonable implication, to pay money to him. If there is such a promissory expression as this, there need be no discussion of ‘intention to benefit.’ We need not speculate for whose benefit the contract was made, or wonder whether the promisee was buying the promise for his own selfish interest or for philanthropic purposes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
817 S.W.2d 648, 1991 Mo. App. LEXIS 1591, 1991 WL 210338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frank-powell-lumber-co-v-federal-insurance-co-moctapp-1991.