Frank L. Ciminelli Construction Co. v. New York State Thruway Authority

157 Misc. 2d 188, 596 N.Y.S.2d 291, 1992 N.Y. Misc. LEXIS 650
New York Court of Claims·Decided December 17, 1992·No. Claim No. 74655·Published

Opinion

OPINION OF THE COURT

Louis C. Benza, J.

Claimant and the New York State Thruway Authority (hereinafter defendant) entered into a contract for the rehabilitation of two bridges in the defendant’s Buffalo Division. Claimant contends the defendant misrepresented the work to be performed, which misrepresentation, compounded by the active interference of defendant, required claimant to perform the work in a manner not contemplated by claimant resulting in claimant performing extra work at additional expense. Claimant also contends additional payments were due to it under the value engineering and incentive bonus provisions of the contract and for defendant failing to properly credit claimant for work deleted from the contract.

[That portion of the decision dealing with the first, second, third and sixth causes of action which the court decided can be found in the slip decision filed with the court on December 18, 1992.]

CAUSE OF ACTION FOR REIMBURSEMENT IN CONNECTION WITH THE VALUE ENGINEERING PROVISION OF THE CONTRACT

Detailed instructions are given in the proposal on what materials and information were to be submitted with each VECP application.

By letter dated June 13, 1985, claimant, with respect to the Buffalo Avenue Bridge, southbound, wrote to defendant requesting its approval to place the reconstruction slab concrete and the overlay concrete as one operation detailing the savings to be made and credit to be received by defendant. Defendant eventually approved the operation for both the southbound and northbound portions of the Buffalo Avenue [190] Bridges. On November 15, 1985, claimant again wrote to defendant and, in that letter, for the first time, requested that the change which had been proposed in the June 13 letter be considered VECP and that claimant be awarded half of all savings resulting from the changes. Ultimately, not only was VECP consideration not given to claimant’s proposal, but defendant took a credit against the contract price for deleting work as suggested by claimant in its June 13 letter. In its letter of June 13, 1985, claimant suggested that a 100% credit for the savings be taken by defendant, a factor which does not weigh in favor of claimant’s position for VECP treatment (see, exhibit 44 [where claimant proposes "a credit of $.92 per sq. ft. of slab reconstruction concrete paid under Item 578.01 * * * for the Southbound Buffalo Avenue Bridge”]).

Straw’s testimony that the placement of slab reconstruction concrete as part of the monolithic pour resulted in a cost savings to claimant, costs which it would otherwise have been required to expend under the contract, gives credence to defendant’s position that said savings should, therefore, be credited to defendant for deleted work. It should also be noted that the contract plans gave claimant an option to use monolithic pours of latex modified concrete overlay in place of class D concrete for partial depths repairs. The option, although not applicable for all slab reconstruction, was certainly not innovative and was excluded from VECP consideration because it was recognized as an optional operation permitted under the contract.

The court finds that claimant has failed to follow the prescribed procedures in the proposal for qualifying for VECP consideration and to prove that the placement of the slab concrete and the overlay concrete as one operation meet the specified requirements for VECP approval. Therefore, this cause of action is dismissed.

CAUSE OF ACTION IN CONNECTION WITH THE REDUNDANCY SYSTEMS

The contract required the construction and installation of redundancy systems for a lump-sum price of $100,000 at both ends of the North Grand Island Bridge, northbound. As a result of existing field conditions, the redundancy system called for in the contract for location U146 was deleted from the contract. The contract required bidders to allow for com[191] pensation for what claimant calls general expenses in the bid under recognized pay items.

Free access — add to your briefcase to read the full text and ask questions with AI

Frank L. Ciminelli Construction Co. v. New York State Thruway Authority, 157 Misc. 2d 188, 596 N.Y.S.2d 291, 1992 N.Y. Misc. LEXIS 650 (N.Y. Super. Ct. 1992).

157 Misc. 2d 188 (Frank L. Ciminelli Construction Co. v. New York State Thruway Authority) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Del Balso Construction Corp. v. City of New York
15 N.E.2d 559 (New York Court of Appeals, 1938)