Frank Garvey v. Oliver Building Contractors, LLC

New Jersey Superior Court Appellate Division·Decided March 22, 2024·No. A-0038-23·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-0038-23

FRANK GARVEY and ELEANOR GARVEY,

Plaintiffs-Respondents/

Cross-Appellants,

v.

OLIVER BUILDING CONTRACTORS, LLC,

Defendant-Appellant/ Cross-Respondent.

Argued March 11, 2024 – Decided March 22, 2024 Before Judges Sabatino, Mawla, and Marczyk.

On appeal from the Superior Court of New Jersey, Law Division, Cape May County, Docket No. L-0228-23.

Frederick A. Jacob argued the cause for appellant/cross-respondent (Jacob Law Group, LLC, attorneys; Frederick A. Jacob, on the briefs).

Paul M. Stanton argued the cause for respondents/cross-appellants (McCrosson & Stanton, PC, attorneys; Paul M. Stanton, on the briefs).

PER CURIAM Defendant Oliver Building Contractors, LLC appeals from an August 3, 2023 order vacating an arbitration award entered in its favor against plaintiffs Frank and Eleanor Garvey, and a September 1, 2023 order denying defendant's motion for reconsideration. Plaintiffs have also cross-appealed from the August order. We affirm both orders, rejecting the arguments raised on the appeal, and do not reach the arguments raised on the cross-appeal for the reasons expressed in this opinion.

Plaintiffs hired defendant to renovate their Strathmere home in late summer of 2021. They and a representative of defendant met with an architectural planner several times to discuss the scope of the project prior to signing a contract. The planner presented project plans and drawings resulting in a one-page plan for the project, which was produced on July 29, 2021. The architectural plans were prepared on August 11, 2021. On September 2, 2021, an engineering firm prepared a draft foundation plan and draft structural notes and details, which totaled eleven pages. On September 17, 2021, defendant's secretary emailed plaintiffs a contract, which included an estimate of $389,796 as the total cost of the project. The email stated defendant "wanted to make sure [it] included everything from the architect's August drawings."

A-0038-23

The parties disputed whether defendant had the full set of plans, including the September 2021 foundation and structural plans, prior to its transmittal of the contract estimate to plaintiffs. Defendant claimed it did not receive any other plans or drawings, aside from the July 2021 drawing, until October 2021, and plaintiffs and the planner testified a full set of plans were delivered to defendant prior to it bidding on the contract. Regardless, defendant's estimate was based on the July 2021 drawing and plaintiffs signed the contract on September 24, 2021.

Defendant began work on plaintiffs' home in November 2021. As the construction became delayed, plaintiffs emailed defendant to inquire when it received the plans from the architectural planner. Defendant responded that plaintiffs could find that information at the municipal construction office; it did not wish to give plaintiffs the information because it had "to work with the many architects around the area and [its] reputation is an essential part of that."

By May 2022, the project was only thirty percent complete, and plaintiffs had paid almost the entire contract price. In June 2022, defendant invoiced plaintiffs an additional $176,377.52.

Plaintiffs retained an attorney because defendant increased the price without their knowledge and performed work that was not in the original

A-0038-23

contract without their authorization, a change order, or an explanation for the price increase. Plaintiffs paid the June 2022 invoice amount into their attorney's trust account, and the parties agreed to have a walk-through to review the work completed and the cost of the work yet to be completed. However, defendant and its attorney did not attend the walk-through.

Defendant abandoned the job on June 11, 2022. It claimed the reasons for the increased costs were that it discovered the floor joists ran in the opposite direction than indicated on the architectural plans. The prices also increased due to a delay, which defendant blamed on the planner's failure to submit the plans to the municipality in a timely manner to issue the construction permits. As a result, permits were not issued until February 2022, and construction was delayed because of the winter weather. In the meantime, the cost of the construction materials increased.

In September 2022, plaintiffs retained a different contractor to correct the work performed by defendant and complete the project. The new contractor estimated its work would cost $548,999. Plaintiffs ultimately paid the new contractor a total of $716,300.08.

Pursuant to the parties' contract, defendant filed a demand for arbitration alleging a breach of contract. Plaintiffs counterclaimed, alleging violations of

A-0038-23

the New Jersey Consumer Fraud Act (CFA), N.J.S.A. 56:8-1 to -227, and common law fraud. The counterclaim pointed out the uncontested fact defendant "was in the business of making home improvements as defined by [the Home Improvement Practice Regulations (HIPR),] N.J.A.C. 13:45A-16.1."1 The arbitrator conducted a six day hearing, and found "there was no actual fraud by either . . . [party], other than the violations of the . . . []CFA[] and the . . . []HIPR[]." Rather,

because [plaintiffs] did not engage a contract administration professional there were informal and confused communications concerning the scope, changes, payments and other matters permeated the parties' relationships on this project and that created a culture and environment in which CFA and HIPR violations took place, which in turn, resulted in disputes and hostilities between the parties.

The arbitrator then calculated that defendant incurred costs totaling $365,167.52, which he reduced by: $6,550 of work defendant performed that was not in a workmanlike manner; $186,925 representing sums plaintiffs had already paid; $103,658.40, which was the trebled amount of $34,552.80 the

1 The HIPR were adopted pursuant to the Attorney General's statutory authority under the CFA, which provides "the Attorney General, in addition to other powers conferred upon him by this act, may . . . promulgate such rules and regulations, . . . which shall have the force of law." N.J.S.A. 56:8-4. See Allen v. V & A Bros., Inc., 208 N.J. 114, 128-29 (2011).

A-0038-23

arbitrator found constituted plaintiffs' ascertainable damages under the CFA and HIPR; and $19,637.68 representing counsel fees and costs awarded to plaintiffs. The arbitrator ordered plaintiffs to pay defendant $48,396.44.

Plaintiffs filed a complaint and order to show cause in the Law Division to vacate the arbitration award, alleging the award was procured by undue means. They claimed the arbitrator: interrupted their witnesses; criticized them for not hiring a professional to review the contract; questioned whether the CFA and HIPR applied; prevented them from fully testifying about the defects in defendant's work; fell asleep during plaintiffs' case and then criticized plaintiffs' counsel for pointing it out; ignored the CFA and HIPR; coached defendant's attorney; inquired about and commented on the religious affiliations of the parties and their counsel; suggested plaintiffs should hire someone "to watch [the new contractor's] work"; admonished plaintiffs to "be delicate" in questioning the architectural planner because "architects do not like being questioned"; commented the architect was "not trustworthy"; and complimented defendant's representative for being a hard worker.

The Law Division judge rejected plaintiffs' claims the arbitrator was biased, disregarded evidence, or prevented them from presenting evidence. However, the judge found the award was procured by undue means under

A-0038-23

Free access — add to your briefcase to read the full text and ask questions with AI

Frank Garvey v. Oliver Building Contractors, LLC, (N.J. Ct. App. 2024).

Frank Garvey v. Oliver Building Contractors, LLC (Frank Garvey v. Oliver Building Contractors, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

D'Atria v. D'Atria
576 A.2d 957 (New Jersey Superior Court App Division, 1990)
Middletown Township PBA Local 124 v. Township of Middletown
935 A.2d 516 (Supreme Court of New Jersey, 2007)
Kearny PBA Local 21 v. Town of Kearny
405 A.2d 393 (Supreme Court of New Jersey, 1979)
Roberts v. Cowgill
719 A.2d 668 (New Jersey Superior Court App Division, 1998)
Thiedemann v. Mercedes-Benz USA, LLC
872 A.2d 783 (Supreme Court of New Jersey, 2005)
Linden Board of Education v. Linden Education Ass'n
997 A.2d 185 (Supreme Court of New Jersey, 2010)
New Jersey Turnpike Authority v. Local 196, I.F.P.T.E.
920 A.2d 88 (Supreme Court of New Jersey, 2007)
Dabush v. MERCEDES BENZ USA, LLC
874 A.2d 1110 (New Jersey Superior Court App Division, 2005)
State, Office of Employee Rel. v. Communications Workers
711 A.2d 300 (Supreme Court of New Jersey, 1998)
Cummings v. Bahr
685 A.2d 60 (New Jersey Superior Court App Division, 1996)
Allen v. v. AND a BROS., INC.
26 A.3d 430 (Supreme Court of New Jersey, 2011)
Weiss v. Carpenter, Bennett & Morrissey
672 A.2d 1132 (Supreme Court of New Jersey, 1996)
Manger v. Manger
9 A.3d 1081 (New Jersey Superior Court App Division, 2010)
Bound Brook Board of Education v. Glenn Ciripompa (076905)
153 A.3d 931 (Supreme Court of New Jersey, 2017)
Minkowitz v. Israeli
77 A.3d 1189 (New Jersey Superior Court App Division, 2013)
Borough of East Rutherford v. East Rutherford PBA Local 275
61 A.3d 941 (Supreme Court of New Jersey, 2013)