Frank Adkins Robert Kean Federico Montinez John D. Johnson Jerry Kahklen, Claimants-Appellants v. Trans-Alaska Pipeline Liability Fund

101 F.3d 86, 96 Daily Journal DAR 13987, 1997 A.M.C. 536, 96 Cal. Daily Op. Serv. 8439, 1996 U.S. App. LEXIS 30114, 1996 WL 671272
CourtCourt of Appeals for the Ninth Circuit
DecidedNovember 21, 1996
Docket95-35291
StatusPublished
Cited by6 cases

This text of 101 F.3d 86 (Frank Adkins Robert Kean Federico Montinez John D. Johnson Jerry Kahklen, Claimants-Appellants v. Trans-Alaska Pipeline Liability Fund) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frank Adkins Robert Kean Federico Montinez John D. Johnson Jerry Kahklen, Claimants-Appellants v. Trans-Alaska Pipeline Liability Fund, 101 F.3d 86, 96 Daily Journal DAR 13987, 1997 A.M.C. 536, 96 Cal. Daily Op. Serv. 8439, 1996 U.S. App. LEXIS 30114, 1996 WL 671272 (9th Cir. 1996).

Opinion

SCHWARZER, Senior District Judge:

In 1989, the EXXON VALDEZ ran aground, spilling millions of gallons of oil into Prince William Sound. On this appeal, Alaska businesses and property owners claiming damage from the oil spill challenge the denial of their claims by the Trans-Alaska Pipeline Liability Fund (the “Fund”).

The Fund was established in 1973 by the Trans-Alaska Pipeline Authorization Act (the “Act”). Pub.L. No. 93-153, 87 Stat. 576 (1973) (codified at 43 U.S.C. §§ 1651-54). Section 1653(c) of the Act creates strict liability for damages caused by marine spills of Alaska crude oil transported through the Trans-Alaska pipeline and loaded onto vessels at the pipeline terminal. 43 U.S.C. § 1653(c). To provide moneys for the payment of compensation out of the Fund, the Act imposes a tax on oil moving through the pipeline. See In re Glacier Bay, 944 F.2d 577, 580-81 (9th Cir.1991).

The four claims that are the subject of this appeal are said to be representative of many others whose denial by the Fund was affirmed by the district court in the order appealed from. The claims are as follows:

*88 Kodiak Electric Cooperative, an electric utility, claims to have lost its largest customers when seafood processing companies closed or operated at low levels because of the shortage of fish for processing;
Killer Whale Cafe, a restaurant, claims to have lost much of its patronage when the oil spill idled commercial fishermen for a season;
Michael T. Tuhy d/b/a 2 E Fish Company and Alaska Sport Angling Photography (ASAP), two tourist-oriented businesses, claim cancellations and loss of customers due to cancellation of a part of the fishing season; and
Marine Welding, Inc., a boat repair company, claims a decline of business because of the decrease in fishing operations after the spill.

PROCEDURAL BACKGROUND

In September 1990, early in the massive litigation that resulted from the oil spill, the district court determined that the Fund should be utilized to provide expedited payments to the many persons and firms who suffered losses. The court urged plaintiffs in the pending actions to promptly file claims with the Fund for administrative resolution. The court later ruled that the Fund process would not be treated as exclusive and that exhaustion of Fund remedies would not be required before others could be pursued.

Beginning in 1990, plaintiffs in the oil spill litigation began to submit claims to the Fund. In 1991, the Fund’s board of trustees appointed John J. Gibbons, who had recently retired as chief judge of the Third Circuit Court of Appeals, to serve as administrator to review and decide the. claims submitted to the Fund, which ultimately numbered 29,000. See 29 C.F.R. § 29.3(c) (1992).

The claims process established by the Fund required a claimant to file a simple registration form setting out the claimant’s name and the nature and amount of the claim. The Fund would then request the claimant to furnish documents and information supporting the claim. This response was initially to be made within 30 days, but the Fund extended the deadline several times, eventually giving all claimants until September 1991, more than 28 months from the date of the spill in March 1989. Some claimants were given until December 1991.

Beginning in December 1991, the Fund issued preliminary determinations of claims. Claimants were permitted to make requests for reconsideration within 30 days. While the Fund gave extensions of time where justified, it accepted no new documents' in support of reconsideration. A claimant was then entitled to appeal the Fund’s determination to the district court. Various claimants whose claims had been denied took appeals, challenging the claims process as violative of due process.

These claimants also challenged the district court’s affirmance of the Fund’s determination that their losses were not proximately caused by the oil spill. The Fund, following the district court’s direction in a prior order to determine proximate cause on a case-by-case basis and to consider remoteness in time, place, and like factors, determined the claimants’ damages to be too remote.

The district court upheld both the validity of the Fund’s claims procedure and the propriety of its proximate cause ruling, and entered a final order disposing of the claimants’ appeals, The representative claimants appeal from that determination. We have jurisdiction under 28 U.S.C. § 1291, and now affirm.

DENIAL OF DUE PROCESS

Appellants state in their brief that “[t]he only Fund procedure at issue in this appeal is one which required claimants to submit information to the Fund within thirty days.” They complain that the Fund “would not, and generally did not accept information after that deadline,” and they argue that “such expedited procedures violated due process.”

In their argument to this.eourt, claimants ignore the fact that they had over two years to submit proof in support of their claims. Their argument is directed solely at the Fund’s rule limiting the time to file requests for reconsideration to 30 days and barring submission of new documents with such requests.

*89 While we review due process challenges de novo, National Assn, of Radiation Survivors v. Derwinski, 994 F.2d 583, 587 (9th Cir.), cert, denied, 510 U.S. 1023, 114 S.Ct. 634, 126 L.Ed.2d 592 (1998), absent constitutional constraints or extremely compelling circumstances, we defer to an administrative agency’s fashioning of procedures. Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519, 543-44, 98 S.Ct. 1197, 1211, 55 L.Ed.2d 460 (1978). The Fund is authorized to “establish uniform procedures and standards for the appraisal and settlement of claims.” 43 C.F.R. § 29.9(d)(2). The Act itself requires the Fund to “expeditiously pay claims.... ” 43 U.S.C. § 1653(c)(3). With some 29,000 claims pending, we cannot say that the procedure and deadlines adopted by the Fund for reconsideration of preliminary determinations were unreasonable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wieler v. United States
364 F. Supp. 2d 1057 (D. Alaska, 2005)
United States v. Frank F. Colacurcio, Sr.
122 F.3d 1074 (Ninth Circuit, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
101 F.3d 86, 96 Daily Journal DAR 13987, 1997 A.M.C. 536, 96 Cal. Daily Op. Serv. 8439, 1996 U.S. App. LEXIS 30114, 1996 WL 671272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frank-adkins-robert-kean-federico-montinez-john-d-johnson-jerry-kahklen-ca9-1996.