Francis J. Palo Inc v. Secretary United States Depart

CourtCourt of Appeals for the Third Circuit
DecidedJuly 5, 2019
Docket17-3748
StatusUnpublished

This text of Francis J. Palo Inc v. Secretary United States Depart (Francis J. Palo Inc v. Secretary United States Depart) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Francis J. Palo Inc v. Secretary United States Depart, (3d Cir. 2019).

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT _________________

No. 17-3748 _________________

FRANCIS J. PALO, INC., Petitioner

v.

SECRETARY UNITED STATES DEPARTMENT OF LABOR, Respondent _________________

Petition for Review of an Order of the Occupational Safety and Health Review Commission (OSHRC No. 15-2239) Administrative Law Judge: Carol A. Baumerich _________________

Submitted Under Third Circuit L.A.R. 34.1(a) September 25, 2018

Before: MCKEE, RESTREPO, FUENTES, Circuit Judges

(Filed: July 5, 2019)

_________________

OPINION** _________________

** This disposition is not an opinion of the full Court and pursuant to I.O.P. 5.7 does not constitute binding precedent. FUENTES, Circuit Judge.

Francis J. Palo, Inc. has filed a petition with this Court to review the Occupational

Safety and Health Review Commission’s1 determination that Palo violated its workplace

safety guidelines. Because we find that substantial evidence supports the Commission’s

finding, we will deny the petition for review.

I.

Palo is in the business of demolishing and constructing bridges. It held a contract

from the Pennsylvania Department of Transportation to demolish and reconstruct a bridge

in Ridgeway, Pennsylvania. This bridge had an arched shape, and Palo’s proposed

reconstruction plan—reviewed and approved by the Department of Transportation—called

for Palo to demolish and rebuild the bridge in halves, allowing traffic access to one half

while Palo rebuilt the other. Palo’s plan included a statement that “[a]t no time during the

demolition process will men or equipment work on or from the component being

demolished.” It did not specify what equipment it intended to use.

Palo’s strategy proceeded by first cutting the bridge in half longways, then cutting

the first half of the bridge away from the abutments on either end of the bridge. While

doing this, Palo parked a Caterpillar excavator on the half of the bridge being demolished.

The excavator weighed over 90,000 pounds.2

1 The Commission, an agency within the Department of Labor, is represented by the Secretary of the Department of Labor. For consistency with the administrative proceedings, the Court here will refer to the Respondent as the “Commission.” 2 The administrative law judge found that the excavator weighed over 90,000 pounds but did not make a finding as to the specific weight. Parties assert that it weighs approximately 101,800 pounds. 2 When Palo had finished both the horizontal and vertical cuts on one end of the

bridge, and had almost completed the cuts on the other side, that first half of the bridge

collapsed from its center. The excavator and two workers fell with the collapsing half.

Two workers below the bridge also sustained injuries.

The Commission began an investigation after the accident. It concluded that Palo

had violated Commission guidelines by parking the excavator on the bridge without

ensuring the bridge had sufficient strength to support it.

Palo contested the citation, and an administrative law judge held a hearing on the

issue. Palo contended that it had lacked the requisite knowledge of the violation.

At the hearing, the administrative law judge heard evidence from the Commission’s

expert, Mohammad Ayub. Ayub testified that, because the bridge was arched, its structure

directed its load to its supporting abutments. When the bridge half was cut free from the

abutments on either end, the half could no longer bear as much weight as it could before.

The bridge was no longer strong enough to support the heavy excavator and collapsed

under its weight. Ayub further testified that a reasonably experienced contractor should

have known that the bridge’s structural behavior would change when it was cut free of its

abutments, and that a reasonably diligent contractor would have conducted an analysis to

determine whether the bridge could sustain the excavator’s weight before parking it.

Palo executives at the hearing testified that Palo had not requested any inspection

reports or documentary information from the Pennsylvania Department of Transportation

prior to developing its demolition plan. Executives also testified that they had not

undertaken an external engineering analysis in preparing the demolition plan and had not

3 analyzed whether the bridge could hold the excavator. They testified that they reasonably

relied on their experience in concluding the partially-demolished bridge could support the

excavator. However, the Palo employee responsible for developing the demolition plan

had only limited experience with arch-shaped bridges, and had thought the bridge’s arch

was decorative, not structural. That employee also testified that he had reasonably assumed

that the bridge was reinforced with industry-standard rebar, and only after the bridge

collapsed discovered that the bridge, built in 1912, had less rebar than expected. Ayub

testified in response that, even if the bridge had rebar conforming to current engineering

standards, its load-bearing capacity would still have been compromised when Palo cut the

bridge from its abutments.

After hearing testimony, the administrative law judge concluded that Palo failed to

engage in reasonably diligent efforts to assess the strength of the bridge. The judge found

that “an experienced demolition and construction contractor should not have placed

mechanical equipment like the [excavator] on the bridge without conducting an

engineering analysis to ascertain whether the bridge could take the load after the abutments

were cut.”3 The administrative law judge found that the information Palo possessed from

the Pennsylvania Department of Transportation did not support Palo’s decision to park the

excavator on the bridge, and Palo’s reliance on its pre-site survey and employee experience

did not overcome its failure to obtain sufficient information.

3 App. 36. 4 Palo appealed the administrative law judge’s ruling to the full Commission, which

declined to undertake a discretionary review, and the administrative law judge’s order

became final. Palo appealed that final order to this Court.4

II.

The Court reviews the Commission’s findings of fact for substantial evidence.5

Substantial evidence is “more than a mere scintilla” and “means such relevant evidence as

a reasonable mind might accept as adequate to support a conclusion.”6 If such substantial

evidence exists, then the Court must affirm the Commission’s interpretation of the evidence

even if the Court “might have interpreted the evidence differently in the first instance.”7

The Court reviews questions of law under an arbitrary and capricious standard. It

reverses the Commissions legal conclusions only when they are “arbitrary, capricious, and

an abuse of discretion or otherwise not in accordance with the law.”8

To establish the violation of a standard, the Commission must show by a

preponderance of the evidence that (1) the standard applied; (2) the employer failed to

comply with it; (3) employees had access to the violative condition; and (4) the employer

knew or should have known of the condition through the exercise of reasonable diligence.9

Here, the Secretary found that Palo violated the regulation found at 29 C.F.R § 1926.856(a),

4 All of Palo’s appeals were timely.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Francis J. Palo Inc v. Secretary United States Depart, Counsel Stack Legal Research, https://law.counselstack.com/opinion/francis-j-palo-inc-v-secretary-united-states-depart-ca3-2019.