Francis J. Palo Inc v. Secretary United States Depart

Court of Appeals for the Third Circuit·Decided July 5, 2019·No. 17-3748·Unpublished

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT

No. 17-3748

FRANCIS J. PALO, INC.,

Petitioner

v.

SECRETARY UNITED STATES DEPARTMENT OF LABOR, Respondent

Petition for Review of an Order of the Occupational Safety and Health Review Commission (OSHRC No. 15-2239)

Administrative Law Judge: Carol A. Baumerich

Submitted Under Third Circuit L.A.R. 34.1(a)

September 25, 2018

Before: MCKEE, RESTREPO, FUENTES, Circuit Judges (Filed: July 5, 2019)

OPINION**

**

This disposition is not an opinion of the full Court and pursuant to I.O.P. 5.7 does not constitute binding precedent.

FUENTES, Circuit Judge.

Francis J. Palo, Inc. has filed a petition with this Court to review the Occupational Safety and Health Review Commission’s1 determination that Palo violated its workplace safety guidelines. Because we find that substantial evidence supports the Commission’s finding, we will deny the petition for review.

I.

Palo is in the business of demolishing and constructing bridges. It held a contract from the Pennsylvania Department of Transportation to demolish and reconstruct a bridge in Ridgeway, Pennsylvania. This bridge had an arched shape, and Palo’s proposed reconstruction plan—reviewed and approved by the Department of Transportation—called for Palo to demolish and rebuild the bridge in halves, allowing traffic access to one half while Palo rebuilt the other. Palo’s plan included a statement that “[a]t no time during the demolition process will men or equipment work on or from the component being demolished.” It did not specify what equipment it intended to use.

Palo’s strategy proceeded by first cutting the bridge in half longways, then cutting the first half of the bridge away from the abutments on either end of the bridge. While doing this, Palo parked a Caterpillar excavator on the half of the bridge being demolished. The excavator weighed over 90,000 pounds.2

1 The Commission, an agency within the Department of Labor, is represented by the Secretary of the Department of Labor. For consistency with the administrative proceedings, the Court here will refer to the Respondent as the “Commission.” 2 The administrative law judge found that the excavator weighed over 90,000 pounds but did not make a finding as to the specific weight. Parties assert that it weighs approximately 101,800 pounds.

When Palo had finished both the horizontal and vertical cuts on one end of the bridge, and had almost completed the cuts on the other side, that first half of the bridge collapsed from its center. The excavator and two workers fell with the collapsing half. Two workers below the bridge also sustained injuries.

The Commission began an investigation after the accident. It concluded that Palo had violated Commission guidelines by parking the excavator on the bridge without ensuring the bridge had sufficient strength to support it.

Palo contested the citation, and an administrative law judge held a hearing on the issue. Palo contended that it had lacked the requisite knowledge of the violation.

At the hearing, the administrative law judge heard evidence from the Commission’s expert, Mohammad Ayub. Ayub testified that, because the bridge was arched, its structure directed its load to its supporting abutments. When the bridge half was cut free from the abutments on either end, the half could no longer bear as much weight as it could before. The bridge was no longer strong enough to support the heavy excavator and collapsed under its weight. Ayub further testified that a reasonably experienced contractor should have known that the bridge’s structural behavior would change when it was cut free of its abutments, and that a reasonably diligent contractor would have conducted an analysis to determine whether the bridge could sustain the excavator’s weight before parking it.

Palo executives at the hearing testified that Palo had not requested any inspection reports or documentary information from the Pennsylvania Department of Transportation prior to developing its demolition plan. Executives also testified that they had not undertaken an external engineering analysis in preparing the demolition plan and had not

analyzed whether the bridge could hold the excavator. They testified that they reasonably relied on their experience in concluding the partially-demolished bridge could support the excavator. However, the Palo employee responsible for developing the demolition plan had only limited experience with arch-shaped bridges, and had thought the bridge’s arch was decorative, not structural. That employee also testified that he had reasonably assumed that the bridge was reinforced with industry-standard rebar, and only after the bridge collapsed discovered that the bridge, built in 1912, had less rebar than expected. Ayub testified in response that, even if the bridge had rebar conforming to current engineering standards, its load-bearing capacity would still have been compromised when Palo cut the bridge from its abutments.

After hearing testimony, the administrative law judge concluded that Palo failed to engage in reasonably diligent efforts to assess the strength of the bridge. The judge found that “an experienced demolition and construction contractor should not have placed mechanical equipment like the [excavator] on the bridge without conducting an engineering analysis to ascertain whether the bridge could take the load after the abutments were cut.”3 The administrative law judge found that the information Palo possessed from the Pennsylvania Department of Transportation did not support Palo’s decision to park the excavator on the bridge, and Palo’s reliance on its pre-site survey and employee experience did not overcome its failure to obtain sufficient information.

3 App. 36.

Palo appealed the administrative law judge’s ruling to the full Commission, which declined to undertake a discretionary review, and the administrative law judge’s order became final. Palo appealed that final order to this Court.4 II.

The Court reviews the Commission’s findings of fact for substantial evidence.5 Substantial evidence is “more than a mere scintilla” and “means such relevant evidence as a reasonable mind might accept as adequate to support a conclusion.”6 If such substantial evidence exists, then the Court must affirm the Commission’s interpretation of the evidence even if the Court “might have interpreted the evidence differently in the first instance.”7 The Court reviews questions of law under an arbitrary and capricious standard. It reverses the Commissions legal conclusions only when they are “arbitrary, capricious, and an abuse of discretion or otherwise not in accordance with the law.”8 To establish the violation of a standard, the Commission must show by a preponderance of the evidence that (1) the standard applied; (2) the employer failed to comply with it; (3) employees had access to the violative condition; and (4) the employer knew or should have known of the condition through the exercise of reasonable diligence.9 Here, the Secretary found that Palo violated the regulation found at 29 C.F.R § 1926.856(a),

4 All of Palo’s appeals were timely. This Court has jurisdiction over this appeal pursuant to 29 U.S.C. § 660(a). 5 Bianchi Trison Corp. v. Chao, 409 F.3d 196, 204 (3d Cir. 2005). 6 Balsavage v. Dir., Office of Workers’ Comp. Programs, 295 F.3d 390, 395 (3d Cir. 2002). 7 Id. at 395. 8 Sec’y of Labor v. Trinity Indus., 504 F.3d 397, 400 (3d Cir. 2007). 9 Sec’y of Labor v. ConocoPhil. Bayway Refinery, 654 F.3d 472, 479-80 (3d Cir. 2011).

Free access — add to your briefcase to read the full text and ask questions with AI

Francis J. Palo Inc v. Secretary United States Depart, (3d Cir. 2019).

Francis J. Palo Inc v. Secretary United States Depart (Francis J. Palo Inc v. Secretary United States Depart) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related