McCOMB, J.

From a judgment in favor of plaintiffs for the sum of $2,950 after trial before the court without a jury, in an action to recover damages pursuant to the provisions of section 3306 of the Civil Code for an alleged breach of an agreement for the exchange of real property, defendants appeal.

[383]*383On July 2, 1954, plaintiffs and defendants entered into an exchange agreement whereby plaintiffs, in exchange for certain industrial property, were to convey a certain house and lot to defendants and pay them $14,000 in cash. The industrial property was subject to a lease and purchase agreement between defendants as lessor-vendor and Sequoia Metalcraft Company and others (hereinafter referred to as “the tenant”) as lessee-vendee. An addendum to the exchange agreement provided:

“In the event either First Party [plaintiffs] or Second Party [defendants] is unable to deliver his property within ninety (90) days from the date of this contract, upon the terms specified, then this contract shall be null and void and each party, in that event, shall hereby release the other of and from all liability hereunder.

“First Party agrees to pay Fourteen Thousand & No/100 ($14,000.00) Dollars cash on closing of this transaction. Rents to be prorated thirty (30) days from date of execution of this contract and payable on closing. Taxes, insurance, utilities and all other expenses relative to the upkeep of the subject properties are to be prorated as of the date of closing, which is to be no later than ninety (90) days from the date of this contract. Bach party will pay expenses on property now owned by him until actual closing. Second Party agrees to complete all obligations now owing to lessee and to hold First Party harmless for any and all claims made by lessee thereunder.”

The trial court found that (1) defendants breached the exchange agreement, and (2) “defendants’ failure and refusal to perform said agreement on their part was deliberate, willful, capricious and without just cause and excuse, and without just or lawful reason therefor.”

These questions are presented for our determination:

First. Did defendants breach the exchange agreement?

Yes. Defendants claimed that they were unable within the 90-day period to deliver the industrial property “upon the terms specified” and that they were thereby released from all liability under the agreement by the provisions of the first sentence of the addendum set forth above.

Defendants were obligated under their lease-purchase agreement with the tenant to construct a building on the industrial property, and they predicate their inability to perform the exchange agreement upon the ground that the construction of this building had not been completed.

[384]*384This presents the question: Was the completion of such construction among “the terms specified” in the exchange agreement ?

It was not expressly so specified in that' clause of the agreement whereby defendants promised to convey the industrial property “free and clear of all encumbrances excepting easements, restrictions and rights of way of record and said Lease Agreement and said purchase agreement [between defendants and the tenant] and tax liens which are the responsibility of the tenant.”

An intent not to include such completion among “the terms specified” is indicated by defendants’ promise, expressed in the last sentence of the addendum, “to complete all obligations now owing to lessee and to hold First Party [plaintiffs] harmless for any and all claims made by lessee thereunder.” This promise was calculated to meet the situation that would obtain if, when the sale was consummated, the sellers had not yet completely performed all of their obligations toward the tenant, including completion of the building. It indicated that the sale was to proceed regardless of such completion. The addendum was written by defendants, and any ambiguity should be resolved against them.

Likewise, the realtor through whom the parties negotiated testified that defendant James P. Aced explained to him that a lien filed against the property by one of the building contractors, Marshall Electric Company, was in litigation and Mr. Aced explained that he thought he could have this lien released quickly but wanted the 90 days to get rid of it, ‘1 that is why we set up the 90-day closing.” It is thus clear that performance of defendants’ obligation to the tenant to complete the building was not a condition of delivering the property.

The Marshall Electric Company lien was paid off nearly 30 days before the expiration of the 90-day period; the only other lien involved was that of the general building contractor, Carlray Company, in the amount of $10,000—$1,400 of which defendants disputed as being for extras ordered by the tenant. About two weeks before the expiration of the 90 days, plaintiffs paid the $1,400 on behalf of the tenant so that the only remaining lien on the 90th day was one which defendant James P. Aced testified he did not question. He admitted that he was agreeable to paying it and conceded that the lien could have been liquidated by using a portion of the money that plaintiffs had already put in escrow to defendants’ credit.

[385]*385Since defendants failed and refused to convey the property to plaintiffs, the finding of the trial court that they had breached the exchange agreement, in view of the above evidence, is amply supported by the record.

Second: Was defendants’ breach of their contract committed in “bad faith” within the meaning of that phrase as used in section 3306 of the Civil Code?

No. Exemplary damages are not recoverable against a defendant who acts in good faith and under the advice of counsel. (Selden v. Cashman, 20 Cal. 56, 67 [81 Am.Dec. 93]; Wolfsen v. Hathaway, 32 Cal.2d 632, 649 [198 P.2d 1] ; Fetterly v. Salyer, 96 Cal.App.2d 240, 244 [5] [215 P.2d 64]; Abbott v. ’76 Land & Water Co., 103 Cal. 607, 609 [37 P. 527]; Bonesteel v. Bonesteel, 30 Wis. 511, 513; Devenny v. The Mascotte, 72 F. 684, 686; cf. Johnson v. Southern Pac. Co., 157 Cal. 333, 338 [107 P. 611]; Perry v. Washington Nat. Ins. Co., 14 Cal.App.2d 609, 617 [7] [58 P.2d 701, 59 P.2d 158]; Haydel v. Morton, 19 Cal.App.2d 697, 700 [4] [66 P.2d 204]; United States v. Homestake Min. Co., 117 F. 481, 488 [54 C.C.A. 303]; 25 C.J.S. (1941), Damages, § 123e, p. 727.)

Section 3306 of the Civil Code reads: “The detriment caused by the breach of an agreement to convey an estate in real property, is deemed to be the price paid, and the expenses properly incurred in examining the title and preparing the necessary papers, with interest thereon; but adding thereto, in case of bad faith, the difference between the price agreed to be paid and the value of the estate agreed to be conveyed, at the time of the breach, and the expenses properly incurred in preparing to enter upon the land.” (Italics added.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Farm Mutual Automobile Insurance v. Superior Court
228 Cal. App. 3d 721 (California Court of Appeal, 1991)
Pierce v. Penman
515 A.2d 948 (Supreme Court of Pennsylvania, 1986)
Hamilton County Bank v. Hinkle Creek Friends Church
478 N.E.2d 689 (Indiana Court of Appeals, 1985)
Stanton v. Astra Pharmaceutical Products, Inc.
718 F.2d 553 (Third Circuit, 1983)
Stanton v. Astra Pharmaceutical Products
718 F.2d 553 (Third Circuit, 1983)
Henderson v. United States Fidelity & Guaranty Co.
695 F.2d 109 (Fifth Circuit, 1983)
Rosener v. Sears, Roebuck & Co.
110 Cal. App. 3d 740 (California Court of Appeal, 1980)
Cory v. Jenney
80 Cal. App. 3d 514 (California Court of Appeal, 1978)
Beck v. State Farm Mutual Automobile Insurance
54 Cal. App. 3d 347 (California Court of Appeal, 1976)
Pre-Fit Door, Inc. v. Dor-Ways, Inc.
477 P.2d 557 (Court of Appeals of Arizona, 1970)
Loeb v. Wilson
253 Cal. App. 2d 383 (California Court of Appeal, 1967)
Tancredi v. Garrett
210 Cal. App. 2d 818 (California Court of Appeal, 1962)
Christensen v. Slawter
343 P.2d 341 (California Court of Appeal, 1959)
Fox v. Aced
317 P.2d 608 (California Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
317 P.2d 608, 49 Cal. 2d 381, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fox-v-aced-cal-1957.