Fowlds v. Evans

54 N.W. 743, 52 Minn. 551, 1893 Minn. LEXIS 462
CourtSupreme Court of Minnesota
DecidedApril 5, 1893
StatusPublished
Cited by6 cases

This text of 54 N.W. 743 (Fowlds v. Evans) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fowlds v. Evans, 54 N.W. 743, 52 Minn. 551, 1893 Minn. LEXIS 462 (Mich. 1893).

Opinion

Collins, J.

This was an action to foreclose a lien against the line-of railway owned by defendant company, under the provisions of 1878 G. S. ch. 90. Defendant Evans had contracted with the company to. construct about ninety miles of road, and plaintiff was -his subcontractor under two contracts; one dated the 16th, the other the 28th, day of July, 1887. Other subcontractors were made defendants. On findings of fact the court below ordered judgment in favor of defendant, company, and this appeal is from a judgment entered upon an order-refusing a new trial. Thirty-four assignments of error are presented by counsel for appellant, but in their brief and on the oral argument they discussed what they termed the “three main points,” all having reference to the first contract, and plaintiff’s right to a lien by. virtue of work done under it. There was not much dispute over the-facts. It appears that Evans was to be paid in the bonds of defendant company at the rate of '$7,000 per mile on the completion of each consecutive five miles of the line. These bonds were on deposit in New York city, and were to be delivered to Evans only upon the certificate of the president and chief engineer of the company that he had completed the number of consecutive miles before mentioned. The contracts for different portions of the line made between Evans and plaintiff were alike in their terms. In each was a stipulation that plaintiff should commence his work within ten days from date, and should prosecute the same with such force and. means as would, in the opinion of the chief or assistant engineer, insure the completion thereof by September 15th following. At all [558]*558times he was to be under the direction of the engineers as to the mode of doing the work, and if at any time he neglected or refused to proceed with the same as fast as, in the opinion of the engineer or of Evans, (to be communicated in writing,) was necessary to complete the work by September 15th, Evans was authorized to declare the contract abandoned, and to retain all amounts earned thereon. If plaintiff failed or neglected to comply with all the provisions of the contracts, Evans was empowered to cancel and declare them void, the plaintiff to have no claim for work already done, or for damages of any kind. Evans also reserved the right to stop any or all of the work, or to reduce the force employed, at will. It was also agreed that the chief engineer should be the umpire to decide all disputes between the parties arising out of the contracts; his decision to be final. Plaintiff was to be paid monthly, and only upon the certificates of the chief engineer, furnished to Evans, that the work therein certified to had been completely finished in every respect* and performed agreeably to the various provisions of the contracts. It was also necessary that an estimate of the quantity of the various kinds of work done by the plaintiff should be made by the engineer, and accompany the certificates. There was a stipulation that ten per centum of each estimate should be retained by Evans until the work was entirely finished. Following a provision that plaintiff should be paid only for actual work done or materials furnished were these words: “The times herein specified are of the essence of the contract,” but in no other part of the contracts was time referred to as of their essence. The court below found as a fact that between the date of the first contract and the 23d of November, 1887, plaintiff performed work and labor in carrying out the same of a certain value. The testimony clearly establishes his claim that between those dates he performed the conditions of the first contract to the satisfaction of the chief engineer and Caldwell, the general manager of the road, who seems to have been upon the ground all of the time, and who paid to plaintiff something over $9,000 on account of his work, or about one sixth of its alleged value. Nothing was paid by Evans. The testimony also shows that the plaintiff performed a large amount of work under the second con[559]*559tract, to the satisfaction of the engineer, but that he refused to proceed, because Evans failed to make payment as stipulated; that the engineer agreed that plaintiff might abandon, and that he then abandoned, further work on the second contract, leaving it uncompleted. The court found in accordance with the testimony in respect io the second contract, and also found that plaintiff’s abandonment of the same was without legal excuse. It also found that time was of the essence of each contract, and that plaintiff sublet much of the work without obtaining the written consent of contractor Evans. A clause in each contract prohibited reletting. The court found also, as to both contracts, that neither the chief engineer nor the plaintiff furnished to Evans certificates or estimates as required; that he never waived or excused this failure, and that the furnishing thereof were conditions precedent to payment under each of the contracts.

It is unnecessary for us to pass on appellant’s contention that time was not made of the. essence of the contracts. From what we have said in reference to the language found in these instruments it would appear to be a matter of grave doubt. The engineer was empowered with very great authority in the matter of pushing or retarding the work, having almost unlimited control over the plaintiff, when and how he should work, and the number of men he should employ. We are unable to discover any provision in the written agreements whereby the plaintiff positively promised to complete the work by September 15th. He did expressly contract to prosecute it with such force and means as would, in the opinion of the engineer, insure its completion by that day; and it was also provided that if he failed or neglected to use such force and means, after being notified in writing, as would, in the opinion of either Evans or the engineer, complete it on the day named, the former could declare the contracts abandoned, plaintiff forfeiting all that was his due. With these and other provisions in reference to the power and authority of Evans and the engineer to control the work, hastening or delaying it as they chose, it would seem somewhat unreasonable to declare that the sentence found elsewhere in the contracts and before quoted should be construed as requiring the full completion of [560]*560the work on September loth. But it is of no consequence. There were no allegations in the answer which raised the question. It was not alleged that plaintiff had failed to perform the work within the time agreed upon, or that damages had accrued by reason of the delay. The proof shows that all of the work under the contracts was done under the personal supervision and to the satisfaction of the engineer; that after the 15th of September, when plaintiff was about to abandon work on both contracts, (the first not being quite finished,) because he had not been paid, the engineer named as the umpire between the parties expressly requested plaintiff to complete the work provided for in the first contract, and agreed if he would do so that he should be formally released from further obligation under the second. The record is full of testimony tending to show that, even if time was made of the essence of these contracts, the delay was assented to by the chief engineer and by all other interested parties. The stipulations which gave to Evans and the engineer the right to give written notice if, in their opinion, the plaintiff was not proceeding fast enough with the work, and to declare the contracts abandoned and forfeited, were for Evans’ benefit and protection. No notice of- this or any other kind was given, and plaintiff was not only allowed, but requested, to proceed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ziegler v. Denver Hog Serum Co.
283 N.W. 134 (Supreme Court of Minnesota, 1938)
Newton v. Southern Colonization Co.
176 N.W. 501 (Supreme Court of Minnesota, 1920)
Ottumwa Bridge Co. v. Corrigan
158 S.W. 39 (Supreme Court of Missouri, 1913)
Falconer v. Simmons
41 S.E. 193 (West Virginia Supreme Court, 1902)
Fowlds v. Evans
63 N.W. 102 (Supreme Court of Minnesota, 1895)
Merchant v. Howell
55 N.W. 131 (Supreme Court of Minnesota, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
54 N.W. 743, 52 Minn. 551, 1893 Minn. LEXIS 462, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fowlds-v-evans-minn-1893.