Fowlds v. Evans

54 N.W. 743, 52 Minn. 551, 1893 Minn. LEXIS 462
Supreme Court of Minnesota·Decided April 5, 1893·Published·Cited by 6 cases

Opinion

Collins, J.

This was an action to foreclose a lien against the line-of railway owned by defendant company, under the provisions of 1878 G. S. ch. 90. Defendant Evans had contracted with the company to. construct about ninety miles of road, and plaintiff was -his subcontractor under two contracts; one dated the 16th, the other the 28th, day of July, 1887. Other subcontractors were made defendants. On findings of fact the court below ordered judgment in favor of defendant, company, and this appeal is from a judgment entered upon an order-refusing a new trial. Thirty-four assignments of error are presented by counsel for appellant, but in their brief and on the oral argument they discussed what they termed the “three main points,” all having reference to the first contract, and plaintiff’s right to a lien by. virtue of work done under it. There was not much dispute over the-facts. It appears that Evans was to be paid in the bonds of defendant company at the rate of '$7,000 per mile on the completion of each consecutive five miles of the line. These bonds were on deposit in New York city, and were to be delivered to Evans only upon the certificate of the president and chief engineer of the company that he had completed the number of consecutive miles before mentioned. The contracts for different portions of the line made between Evans and plaintiff were alike in their terms. In each was a stipulation that plaintiff should commence his work within ten days from date, and should prosecute the same with such force and. means as would, in the opinion of the chief or assistant engineer, insure the completion thereof by September 15th following. At all [558] times he was to be under the direction of the engineers as to the mode of doing the work, and if at any time he neglected or refused to proceed with the same as fast as, in the opinion of the engineer or of Evans, (to be communicated in writing,) was necessary to complete the work by September 15th, Evans was authorized to declare the contract abandoned, and to retain all amounts earned thereon. If plaintiff failed or neglected to comply with all the provisions of the contracts, Evans was empowered to cancel and declare them void, the plaintiff to have no claim for work already done, or for damages of any kind. Evans also reserved the right to stop any or all of the work, or to reduce the force employed, at will. It was also agreed that the chief engineer should be the umpire to decide all disputes between the parties arising out of the contracts; his decision to be final. Plaintiff was to be paid monthly, and only upon the certificates of the chief engineer, furnished to Evans, that the work therein certified to had been completely finished in every respect* and performed agreeably to the various provisions of the contracts. It was also necessary that an estimate of the quantity of the various kinds of work done by the plaintiff should be made by the engineer, and accompany the certificates. There was a stipulation that ten per centum of each estimate should be retained by Evans until the work was entirely finished. Following a provision that plaintiff should be paid only for actual work done or materials furnished were these words: “The times herein specified are of the essence of the contract,” but in no other part of the contracts was time referred to as of their essence. The court below found as a fact that between the date of the first contract and the 23d of November, 1887, plaintiff performed work and labor in carrying out the same of a certain value. The testimony clearly establishes his claim that between those dates he performed the conditions of the first contract to the satisfaction of the chief engineer and Caldwell, the general manager of the road, who seems to have been upon the ground all of the time, and who paid to plaintiff something over $9,000 on account of his work, or about one sixth of its alleged value. Nothing was paid by Evans. The testimony also shows that the plaintiff performed a large amount of work under the second con[559] tract, to the satisfaction of the engineer, but that he refused to proceed, because Evans failed to make payment as stipulated; that the engineer agreed that plaintiff might abandon, and that he then abandoned, further work on the second contract, leaving it uncompleted. The court found in accordance with the testimony in respect io the second contract, and also found that plaintiff’s abandonment of the same was without legal excuse. It also found that time was of the essence of each contract, and that plaintiff sublet much of the work without obtaining the written consent of contractor Evans. A clause in each contract prohibited reletting. The court found also, as to both contracts, that neither the chief engineer nor the plaintiff furnished to Evans certificates or estimates as required; that he never waived or excused this failure, and that the furnishing thereof were conditions precedent to payment under each of the contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Fowlds v. Evans, 54 N.W. 743, 52 Minn. 551, 1893 Minn. LEXIS 462 (Mich. 1893).

54 N.W. 743 (Fowlds v. Evans) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ziegler v. Denver Hog Serum Co.
283 N.W. 134 (Supreme Court of Minnesota, 1938)
Newton v. Southern Colonization Co.
176 N.W. 501 (Supreme Court of Minnesota, 1920)
Ottumwa Bridge Co. v. Corrigan
158 S.W. 39 (Supreme Court of Missouri, 1913)
Falconer v. Simmons
41 S.E. 193 (West Virginia Supreme Court, 1902)
Fowlds v. Evans
63 N.W. 102 (Supreme Court of Minnesota, 1895)
Merchant v. Howell
55 N.W. 131 (Supreme Court of Minnesota, 1893)