Four Seasons Heating & Air Conditioning v. Beers Skanska.

CourtCourt of Appeals of Tennessee
DecidedDecember 23, 2003
DocketM2002-02783-COA-R3-CV
StatusPublished

This text of Four Seasons Heating & Air Conditioning v. Beers Skanska. (Four Seasons Heating & Air Conditioning v. Beers Skanska.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Four Seasons Heating & Air Conditioning v. Beers Skanska., (Tenn. Ct. App. 2003).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE AUGUST 6, 2003 Session

FOUR SEASONS HEATING & AIR CONDITIONING, INC. v. BEERS SKANSKA, INC.

An Appeal from the Chancery Court for Montgomery County No. MC CH CV CD 02-03 Carol Ann Catalano, Chancellor

No. M2002-02783-COA-R3-CV - Filed December 23, 2003

This is a breach of contract case. The defendant general contractor was hired to construct a building on a state college campus. The contractor hired the plaintiff subcontractor to perform substantial work on the job. During the course of the project, the subcontractor sought additional labor costs incurred in the project. This issue was not resolved. Later, the subcontractor sought from the contractor the retainage kept by the contractor. When the check was ready, the subcontractor sent its project manager to retrieve it. In order to get the check, the project manager was required by the contractor to sign a document releasing all claims between the contractor and the subcontractor. Later, the subcontractor filed this lawsuit, seeking the additional labor costs. The contractor filed a motion to dismiss, arguing that, by the project manager’s signature on the release, the subcontractor waived its claim to the additional labor costs. The subcontractor argued that its project manager did not have the authority to bind the company to the release. After a hearing, the trial court dismissed the subcontractor’s complaint. The subcontractor now appeals. We reverse, finding that the evidence was insufficient to establish as a matter of law that the project manager had actual or apparent authority to bind the subcontractor or to establish as a matter of law that the subcontractor ratified the release signed by the project manager.

Tenn. R. Civ. P. 3 Appeal as of Right; Judgment of the Chancery Court is Reversed and Remanded

HOLLY M. KIRBY, J., delivered the opinion of the court, in which W. FRANK CRAWFORD , P.J., W.S., and ALAN E. HIGHERS, J., joined.

David K. Taylor and Jennifer L. Ditty, Nashville, Tennessee, for the appellant, Four Seasons Heating and Air Conditioning, Inc.

Richard M. Smith and H. Brent Patrick, Nashville, Tennessee, for the appellee, Beers Skanska, Inc. OPINION

In July 1998, Respondent/Appellee Beers Skanska, Inc. (“Beers”), formerly known as Patten- Beers Constructors, Inc. (“Beers”), entered into a contract with the State of Tennessee to be the general contractor for the construction of a new science building at Austin Peay State University (“Project”). On September 24, 1998, Beers entered into a subcontract for services (“Subcontract”) with Petitioner/Appellant Four Seasons Heating and Air Conditioning, Inc. (“Four Seasons”), a corporation wholly owned by Wayne Gulledge (“Gulledge”) and his wife, Sandra Gulledge (“Mrs. Gulledge”).

By the end of the Project, the total compensation due Four Seasons under the contract with Beers exceeded $6 million. Throughout the course of the Project, Beers made partial payments based upon the pay applications submitted by Four Seasons. After each partial payment was made, Mrs. Gulledge signed a partial release and waiver indicating that the payment had been received by Four Seasons.

On December 2, 1999, in the middle of the Project, Four Seasons made a formal demand upon Beers for an additional payment of $177,991 for additional labor costs incurred by Four Seasons under the Subcontract (“Labor Claim”). The additional labor costs were based on the difference between the estimate of anticipated labor costs used by Four Seasons to calculate its bid and the state wage rates that applied to the Project. Though Four Seasons continued to work on the project, the parties continued to negotiate over the disputed discrepancy. The last communication in the record between the parties regarding the labor cost issue is a February 6, 2001 letter from Gulledge to Beers, requesting the additional payment by February 15, 2001. Beers did not respond in writing to this letter. Beers did not pay the Labor Claim. Shortly before Four Seasons filed its lawsuit in this case, Beers finally reduced its denial of the Labor Claim to writing.1

On December 2, 2001, Four Seasons’ subcontractor, Mechanical Automated Control Systems, Inc. (“MAC”), filed a lawsuit against both Four Seasons and Beers and their bonding companies (“MAC Lawsuit”), asserting claims arising out of the Project. It is undisputed that the claims in the MAC Lawsuit are unrelated to the Labor Claim.

As with many construction contracts, the Subcontract at issue between Beers and Four Seasons permitted Beers to withhold from Four Seasons portions of the Subcontract funds until the end of the work, commonly referred to as a “Retainage.” Before and after the filing of the MAC Lawsuit, Gulledge requested that Beers pay all, or at least some portion, of the Retainage to Four Seasons. Some of the undisputed Retainage funds were withheld by Beers from Four Seasons because of the MAC Lawsuit.

1 Four Seasons alleges that Beers’ failure to reduce its decision to writing in a timely manner constituted a violation of Article 14 (b) of the Sub contract.

-2- In February 2002, while the MAC lawsuit was still pending, Gulledge asked Four Seasons’ project manager, Wendell Williams (“Williams”), to call an employee of Beers, Brian Carter, and ask about payment of any undisputed funds. On February 21, 2002, Beers called Four Seasons’ office and told Four Seasons that a check in the amount of $43,249.58 was ready to be picked up. This check was not specified as payment for any portion of the Labor Claim. On that day, Gulledge sent Williams to collect the payment from Carter. When Williams arrived to pick up the check, Carter had him sign a document entitled “Final Release of Lien Waiver.” The Release states that it is a waiver and relinquishment of all of Four Seasons’ claims against Beers and others relating to “causes of action, suits, accounts, debts, and demands, whether known or unknown . . . arising out of or related to . . . the Project.” Williams was not given a copy of the Release, and Gulledge claims that he did not find out about the existence of the Release until later, through counsel in this lawsuit.

On May 28, 2002, Four Seasons filed a lawsuit against Beers in the court below, seeking payment for the Labor Claim under a breach of contract theory. On June 24, 2002, Beers filed an answer to the complaint and a motion to dismiss, denying liability and asserting, among other things, that the Release signed by Williams constituted a release of all the claims of Four Seasons against Beers, including the Labor Claim. Along with the answer and the motion to dismiss, Beers filed a memorandum of law and attached to it copies of the general contract agreement, the Subcontract, and the Release.

On October 7, 2002, Four Seasons filed a response to the motion to dismiss, maintaining that material issues of fact existed concerning the execution of the Release and whether it applied to the Labor Claim. Four Seasons attached to its response affidavits by Gulledge and Williams, asserting that Williams was not given authority to sign the Release on behalf of Four Seasons. Four Seasons noted that Mrs. Gulledge was the secretary-treasurer of the corporation, and that, during the course of the entire Project, she had been signing the partial releases to obtain payment from Beers. Four Seasons also argued in its response that Williams had no apparent authority to sign the Release, because there was no evidence that the principals of the company, the Gulledges, ever took any action to cloak him with such authority. Finally, Four Seasons argued that it did not ratify the Release signed by Williams, because its principals took no action to confirm the terms of the Release.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Staples v. CBL & Associates, Inc.
15 S.W.3d 83 (Tennessee Supreme Court, 2000)
Webber v. State Farm Mutual Automobile Insurance Co.
49 S.W.3d 265 (Tennessee Supreme Court, 2001)
Kelly v. Cliff Pettit Motors, Inc.
234 S.W.2d 822 (Tennessee Supreme Court, 1950)
Ku v. State
104 S.W.3d 870 (Court of Appeals of Tennessee, 2002)
Anderson v. Standard Register Co.
857 S.W.2d 555 (Tennessee Supreme Court, 1993)
Mechanics Laundry Service v. Auto Glass Co. of Memphis, Inc.
98 S.W.3d 151 (Court of Appeals of Tennessee, 2002)
Bells Banking Co. v. Jackson Centre, Inc.
938 S.W.2d 421 (Court of Appeals of Tennessee, 1996)
Absar v. Jones
833 S.W.2d 86 (Court of Appeals of Tennessee, 1992)
Byrd v. Hall
847 S.W.2d 208 (Tennessee Supreme Court, 1993)
White v. Methodist Hospital South
844 S.W.2d 642 (Court of Appeals of Tennessee, 1992)
Whitfield v. May
89 S.W.2d 764 (Court of Appeals of Tennessee, 1935)
Southern Ry. Co. v. Pickle
138 Tenn. 238 (Tennessee Supreme Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
Four Seasons Heating & Air Conditioning v. Beers Skanska., Counsel Stack Legal Research, https://law.counselstack.com/opinion/four-seasons-heating-air-conditioning-v-beers-skan-tennctapp-2003.